Tender Value
₹1.2 L
EMD Value
₹2,400
Closing Date
27 Oct 2026, 2:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer
Irrigation Division Kulgam
Construction of lining wall on RS of Amnoo Canal near RD 100 mts
2026_IFC_328354_5
eNIT No. 15 of 2026-27
Open Tender
Civil Works - Canal
Percentage
10 days
Kulgam
Please refer Tender documents.
2 documents required · 2 mandatory
₹300
MH 0702
₹2,400
15 Oct 2026
15 Oct 2026
27 Oct 2026
15 Oct 2026
27 Oct 2026
15 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in
depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth
lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.
All kinds of soil : | 17.8 | cum | 592.9 | ₹10,553.62 |
| 2 | Dumping stone excluding cost of stones.in Horizontal on level | 2.05 | cum | 237.9 | ₹487.7 |
| 3 | Supply of stone nallah (Stack measurement reduced by 15 %) incliuding CP + GST | 2.05 | cum | 896 | ₹1,836.8 |
| 4 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 1.61 | cum | 5,202.9 | ₹8,376.67 |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 12.42 | cum | 5,733.6 | ₹71,211.31 |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form work for:
Foundations, footings, bases for columns | 55.2 | sqm | 286.35 | ₹15,806.52 |
| 7Carriage of material by Mechenical transport and head load from source to actual site of work including loading,unloading,stacking complete job. | |||||
| 7.1 | Cement for an avg lead of 2 KM by MT and 20 0mts by HL | 3.01 | MT | 298.43 | ₹898.27 |
| 7.2 | Sand for an avg lead of 5 KM by MT and 200mtr by HL | 6.31 | cum | 514.48 | ₹3,246.37 |
| 7.3 | 20mm Agg by an avg lead of 5 KM by MT and 200mtr by HL | 11.18 | cum | 514.48 | ₹5,751.89 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.96 MB
BOQ_1111569.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .