| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.4 LAccepted-Finance | ₹18.4 L | L1 | Accepted-Finance BEING LOWEST |
| 2 | L2₹20.4 L+₹1.9 L (10.6%)Rejected-Finance | ₹20.4 L+₹1.9 L (10.6%) | L2 | Rejected-Finance NOT BEING LOWEST |
| 3 | L3₹22.1 L+₹3.6 L (19.6%)Rejected-Finance | ₹22.1 L+₹3.6 L (19.6%) | L3 | Rejected-Finance NOT BEING LOWEST |
| 4 | L4₹23.0 L+₹4.6 L (24.8%)Rejected-Finance | ₹23.0 L+₹4.6 L (24.8%) | L4 | Rejected-Finance NOT BEING LOWEST |
| 5 | L5₹23.5 L+₹5.0 L (27.2%)Rejected-Finance | ₹23.5 L+₹5.0 L (27.2%) | L5 | Rejected-Finance NOT BEING LOWEST |
| Sl No | Description | Qty | Unit | sagar construction L1 | M/S OMSAI ENTERPRISES L5 | BUILD ELITE ENGINEERS L4 | MAGAR INFRA APROJECTS L3 | Sky Vision Construction L6 | M/S Divyani Aadhar Patil L2 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | M&L for roof tiles Mangalore pattern interlocking at side joints, laid dry including dismantling single layer Mangalore pattern or similar tiles in roofing and rubbish off the premises complete all as specified and as directed. | 150 | SQM | 320 ₹48,000 | 400 ₹60,000 | 400 ₹60,000 | 300 ₹45,000 | 337 ₹50,550 | 100 ₹15,000 Lowest |
| 2.00 | All as above item above here-in-before but except tiles complete all as specified and as directed. | 120 | SQM | 120 ₹14,400 | 120 ₹14,400 | 190 ₹22,800 | 75 ₹9,000 | 95 ₹11,400 | 50 ₹6,000 Lowest |
| 3.00 | M&L for ridge or hip tiles to suit Mangalore pattern of roofing tiles,bedded and jointed in cement mortar (1:6) etc including dismantling of tile and rubbish off the premises complete all as specified and as directed. | 80 | RM | 280 ₹22,400 | 225 ₹18,000 | 250 ₹20,000 | 90 ₹7,200 Lowest | 317 ₹25,360 | 90 ₹7,200 Lowest |
| 4.00 | Dismantling of single layer mangalore tiles roofing including ridges complete all as specified and directed. | 20 | SQM | 80 ₹1,600 | 20 ₹400 Lowest | 90 ₹1,800 | 20 ₹400 Lowest | 25 ₹500 | 30 ₹600 |
| 5.00 | S&F 2nd class hardwood clean sawn tile battens, cross sectional area exc 5 and n.exc 15 Sqcm spaced at 30 cm centres to centres fixed with nails including dismantling Battens for tiles, shingles etc, of any size including tilting fillets n.exc 15cm spaces complete all as specified and as directed. (NOTE:Measurements shall be taken overall including both battens and spaces. Deductions shall be made only for openings exceeding 0.40sqm each) complete all as specified and as directed. | 240 | SQM | 176 ₹42,240 | 125 ₹30,000 Lowest | 290 ₹69,600 | 280 ₹67,200 | 127 ₹30,480 | 250 ₹60,000 |
| 6.00 | All as above item here-in-before but except batten complete all as specified and as directed. | 120 | SQM | 96 ₹11,520 | 50 ₹6,000 | 290 ₹34,800 | 30 ₹3,600 Lowest | 57 ₹6,840 | 50 ₹6,000 |
| 7.00 | M&L for preparation of battens, any size and spacing and treated all over (measured overall on one side only, spaces not deducted) with two coats of creosote oil complete all as specified and as directed. | 240 | SQM | 36 ₹8,640 | 30 ₹7,200 | 100 ₹24,000 | 25 ₹6,000 | 35 ₹8,400 | 20 ₹4,800 Lowest |
| 8.00 | M&L for 2nd class hard wood, clean sawn, in scantling timber work including dismantling wooden scantling of any size and position complete all as specified and as directed. | 1 | CUM | 28,000 ₹28,000 | 25,000 ₹25,000 | 125 ₹125 Lowest | 65,000 ₹65,000 | 21,777 ₹21,777 | 40,000 ₹40,000 |
| 9.00 | All as above item here-in-before but except timber complete all as specified and as directed. | 1 | CUM | 2,800 ₹2,800 | 5,000 ₹5,000 | 125 ₹125 Lowest | 4,000 ₹4,000 | 7,999 ₹7,999 | 3,000 ₹3,000 |
| 10.00 | M&L in repair 2nd class softwood Weather boarding, clean sawn, plain, 20mm thick or feather edged 15mm to 20mm thick and fixed with 30mm laps, complete as approved arch pattern any size and shape including repairs to replace old or decayed boarding in patches, including cutting out old, piecing, heading joints etc, and including removing dismantled boarding to store complete all as specified and as directed. | 25 | SQM | 960 ₹24,000 | 750 ₹18,750 | 450 ₹11,250 | 1,200 ₹30,000 | 377 ₹9,425 Lowest | 800 ₹20,000 |
Tender Value
₹30 L
EMD Value
₹60,000
Closing Date
1 Aug 2026, 6:00 pmClosed
GE I R AND D GIRINAGAR PUNE
GE I R AND D GIRINAGAR PUNE
REPAIR TO INTERNAL WATER SUPPLY SUNKEN FLOORS SANITARY FITTINGS FLOORING PLASTERING SKIRTING AND TILING INCL CERTAIN ALLIED WORKS AT DIAT GIRINAGAR PUNE 25
2026_MES_776392_1
GE I R AND D GNR TOKEN 14 OF 2026-27(8997)
Open Tender
Civil Works
Item Rate
270 days
GE I R AND D GIRINAGAR PUNE
AS PER TENDER DOCUMENT
8 documents required · 8 mandatory
₹500
GE I R AND D GIRINAGAR PUNE
₹60,000
Yes
7 Aug 2026
4 Jul 2026
3 Aug 2026
4 Jul 2026
1 Aug 2026
18 Jul 2026
4 Jul 2026 - 11 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | M&L for roof tiles Mangalore pattern interlocking at side joints, laid dry including dismantling single layer Mangalore pattern or similar tiles in roofing and rubbish off the premises complete all as specified and as directed. | 150 | SQM | - | - |
| 2 | All as above item above here-in-before but except tiles complete all as specified and as directed. | 120 | SQM | - | - |
| 3 | M&L for ridge or hip tiles to suit Mangalore pattern of roofing tiles,bedded and jointed in cement mortar (1:6) etc including dismantling of tile and rubbish off the premises complete all as specified and as directed. | 80 | RM | - | - |
| 4 | Dismantling of single layer mangalore tiles roofing including ridges complete all as specified and directed. | 20 | SQM | - | - |
| 5 | S&F 2nd class hardwood clean sawn tile battens, cross sectional area exc 5 and n.exc 15 Sqcm spaced at 30 cm centres to centres fixed with nails including dismantling Battens for tiles, shingles etc, of any size including tilting fillets n.exc 15cm spaces complete all as specified and as directed. (NOTE:Measurements shall be taken overall including both battens and spaces. Deductions shall be made only for openings exceeding 0.40sqm each) complete all as specified and as directed. | 240 | SQM | - | - |
| 6 | All as above item here-in-before but except batten complete all as specified and as directed. | 120 | SQM | - | - |
| 7 | M&L for preparation of battens, any size and spacing and treated all over (measured overall on one side only, spaces not deducted) with two coats of creosote oil complete all as specified and as directed. | 240 | SQM | - | - |
| 8 | M&L for 2nd class hard wood, clean sawn, in scantling timber work including dismantling wooden scantling of any size and position complete all as specified and as directed. | 1 | CUM | - | - |
| 9 | All as above item here-in-before but except timber complete all as specified and as directed. | 1 | CUM | - | - |
| 10 | M&L in repair 2nd class softwood Weather boarding, clean sawn, plain, 20mm thick or feather edged 15mm to 20mm thick and fixed with 30mm laps, complete as approved arch pattern any size and shape including repairs to replace old or decayed boarding in patches, including cutting out old, piecing, heading joints etc, and including removing dismantled boarding to store complete all as specified and as directed. | 25 | SQM | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.21 MB
TENDERDOCUMENTS.pdf
Tender Documents • 0.71 MB
BOQ_869427.xls
BOQ • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .