Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.8 LAccepted-AOC | ₹6.8 L | 1 | Accepted-AOC Awarded |
| 2 | 2₹6.8 LRejected-AOC | ₹6.8 L | 2 | Rejected-AOC Not Awarded |
| 3 | 3₹6.9 LRejected-AOC | ₹6.9 L | 3 | Rejected-AOC Not Awarded |
Tender Value
₹7.2 L
EMD Value
₹8,000
Closing Date
24 Feb 2020, 5:00 pmClosed
S.E., E.T.C., Bareilly
Superintending Engineer Transmission Campus Near L.I.C. Office Rampur Garden, Bareilly
Periodic (Bi-Monthly/Quarterly) Routine Patrolling/Emergency Patrolling and Periodic Cutting/Lopping and Chopping of Trees in Line Corridor of 220KV Transmission Lines under E.T.D., Budaun during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021
2020_UPTCL_432507_1
E-Tender No. 83 / W / ETC(B) / 2019 - 20
Open Tender
Electrical Works
365 days
Budaun
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
A/c No 10897666087 IFSC SBIN0000615 S.B.I. Bly
₹8,000
16 Sept 2020
7 Feb 2020
25 Feb 2020
7 Feb 2020
24 Feb 2020
7 Feb 2020
7 Feb 2020 - 24 Feb 2020
Amount
Following Works are to be Carried out on 220KV Transmission Lines under E.T.D., Budaun during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021, with all Cost of Men, Misc. Consumables, T&Ps etc. Required for Satisfactory Completion of the Work as per Technical Specifications & Direction of the Supervising Engineer : (1) Periodic (Bi-Monthly / Quarterly) Routine Tower to Tower Patrolling from one end to other end of Following Transmission Lines and Submission of Patrolling Report in Triplicate in Prescribed Proforma Mentioning the Stolen / Missing Tower Parts & Tower Accessories; Trees Falling in the Range of Line Corridor; Damage to Earthwire, Conductor, Jumper, Insulator & other Line Accessories; damage to Foundation, Coping, Chimney, Earthing etc. The Patrolling shall be done Every Month during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021, with all due Care of Safety & Precautions : (a) 220KV S.C. C.B. Ganj - Budaun Transmission Line (Line Length 52.40 Km; 52.40 Km × 4 Quarter = 209.60 Km)
(b) 220KV D.C. Roza - Budaun Transmission Line (Line Length 96.825 Km; 96.825 Km × 6 Bi-Month = 580.95 Km)
(2) Emergency Patrolling of the above Transmission Lines in the event of Tripping / Break Down of the Line (to Commence within 2 hrs. of Intimation for the same, if Tripping / Breakdown in Day Time and by 07:00 A.M., if Tripping / Breakdown in Night Hours) as per Instructions of Supervising Engineer during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021, as per Details given below : (a) Emergency Patrolling of Line (Patrolling of Line Length upto 20 Km Distance) (1 Job for each Emergency Patrolling).
(b) Emergency Patrolling of Line (Patrolling of Line Length for more than 20 Km to 50 Km Distance) (1 Job for each Emergency Patrolling).
(c) Emergency Patrolling of Line (Patrolling of Line Length for more than 50 Km Distance) (1 Job for each Emergency Patrolling).
(3) Periodic Cutting of different types of Trees like Mango, Neem, Sheesham, Peepal, Semal, Eucalyptus, Popular etc. having Girth 0.5 Meter to 1.0 Meter and Falling in the Range of Corridor of above Transmission Lines to Provide Minimum Clearance of about 8 Meter between the Tree & Conductors on both side of the Towers / Line with all due Care of Safety & Precautions to Avoid any damage to nearby Buildings, Power & Telephone Lines passing nearby, Crops, other nearby Trees etc. The Work also includes Removing, Eliminating & Cleaning the Line Sites after Cutting of the Trees during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021. (100 No. Trees x 4 Times in a Year = 400 No. Trees).
(4) Periodic Lopping & Chopping of Branches of different types of Trees like Mango, Neem, Sheesham, Peepal, Semal, Eucalyptus, Popular etc., Falling in the Range of Corridor of the above Transmission Lines to Provide the Minimum Clearance of about 8 Meter between the Tree & Conductors on both side of the Towers / Conductors of above said Transmission Line with all due Care of Safety & Precautions to Avoid any Damage to nearby Buildings, Power & Telephone Lines Passing nearby, Crops, other nearby Trees etc. The Work also includes Removing, Eliminating & Cleaning the Line Sites after Lopping & Chopping of the Trees during the Period of 1 Year w.e.f. 01.03.2020 to 28.02.2021. (700 No. Trees x 4 Times in a Year = 2800 No. Trees)
LASHANI ENTERPRISES
SHRI BALAJI ENGG. WORKS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid