Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.1 LAccepted-Finance | L1 | Accepted-Finance L1 | |
| 2 | L2₹7.2 L+₹1.1 L (17.8%)Accepted-Finance | L2 | Accepted-Finance L2 | |
| 3 | L3₹7.6 L+₹1.5 L (24.5%)Accepted-Finance | L3 | Accepted-Finance L3 |
Tender Value
₹7.7 L
EMD Value
₹15,300
Closing Date
29 May 2026, 6:00 pmClosed
Executive Enigneer
PWD Division Udhampur
PRE-FABRICATED STRUCTURE AT DC RESIDENCE UDHAMPUR
2026_PWDJK_310744_1
e-NIT No. 29 of 2026-27 dated 23.05.2026
Open Tender
Civil Works
Percentage
90 days
Udhampur
Please refer Tender documents.
2 documents required · 2 mandatory
₹600
Executive Engineer PWD Division Udhampur
₹15,300
2 Jun 2026
23 May 2026
30 May 2026
23 May 2026
29 May 2026
23 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling tile work in floors and roofs laid in cement mortar including
stacking material within 50 meters lead.
15.23.1 For thickness of tiles 10 mm to 25 mm | 15.68 | SQM | 57 | ₹893.76 |
| 2 | Demolishing cement concrete manually/by mechanical means including
disposal of material within 50 meters lead as per direction of Engineer-in charge:
1:3:6 or richer mix (i/c equivalent design mix) | 0.78 | CUM | 1,725.2 | ₹1,345.66 |
| 3 | Engagment OF PLUMBER FOR SHIFTING OF geyser, WASHBASIN ETC 2NO. @ 2Day | 4 | days | 806 | ₹3,224 |
| 4 | Engagment OF Labour for dismantling sun shade 2NO. @ 2Day | 4 | days | 553 | ₹2,212 |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°,
landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral
stair cases upto five level including curing but excluding the cost of centring, shuttering,
finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size | 0.86 | CUM | 9,821.85 | ₹8,446.79 |
| 6 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness)
including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses,
string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills,
fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering
and finishing with. 1:5:10 (1 cement : 5 coarse sand : 10 graded brick aggregate 40 mm nominal size | 2.04 | CUM | 4,469.25 | ₹9,117.27 |
| 7 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness)
including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses,
string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills,
fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering
and finishing with. 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 0.78 | CUM | 7,564.8 | ₹5,900.54 |
| 8 | Steel reinforcement TMT for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete UPTO and above plinth level | 80.7 | KG | 123.2 | ₹9,942.24 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for:Lintel, beams, plinth beams, girders, bressumers and cantilevers. | 7.45 | SQM | 577.55 | ₹4,302.75 |
| 10 | 6mm cement plaster to ceiling of mix 1 : 3 (1 cement: 3 fine sand) | 7.45 | SQM | 241.25 | ₹1,797.31 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.61 MB
BOQ_1005098.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .