| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹66.5 LAccepted-AOC NEAR GRAM PANCHAYAT BHAVAN WAIGAON GHOTULI UMRER DIST NAGPUR | UMRER | NAGPUR | MAHARASHTRA | ₹66.5 L Quoted ₹56.3 L | L1 | Accepted-AOC L-1 Being the lowest bidder |
| 2 | L2₹58.7 L+₹2.3 L (4.17%)Rejected-Finance 02 UMRER PIPLA UDASA APTUR ROAD VILLAGE TOWN APTUR CITY UMRER NAGPUR MAHARASHTRA 441204 INDIA | NAGPUR | MAHARASHTRA | 441204 | ₹58.7 L+₹2.3 L (4.17%) | L2 | Rejected-Finance Quoted value higher than L-1 |
| 3 | L3₹58.7 L+₹2.4 L (4.22%)Rejected-Finance LAKSHMI NAGAR CHINDWARA ROAD SAWNER DISTRICT NAGPUR 441107 | NAGPUR | MAHARASHTRA | 441107 | ₹58.7 L+₹2.4 L (4.22%) | L3 | Rejected-Finance Quoted value higher than L-1 |
| 4 | L4₹59.6 L+₹3.2 L (5.73%)Rejected-Finance TILAK CHOWK WARORA TEHSIL WARORA DISTRICT CHANDRAPUR MS 442907 | WARORA | CHANDRAPUR | MAHARASHTRA | 442907 | ₹59.6 L+₹3.2 L (5.73%) | L4 | Rejected-Finance Quoted value higher than L-1 |
| 5 | L5₹60.0 L+₹3.7 L (6.54%)Rejected-Finance | ₹60.0 L+₹3.7 L (6.54%) | L5 | Rejected-Finance Quoted value higher than L-1 |
Tender Value
₹91.4 L
EMD Value
₹1.1 L
Closing Date
22 Aug 2026, 6:00 pmClosed
SO(Civil), Umrer Area
O/o AGM, Umrer Area
Making 08 Nos foundation and ramp for shifting of existing 100 MT Weigh Bridges at new location of MKD-I OC Mine of Umrer Area.
2026_WCL_363302_1
um4550-civ-0024-2026-27
Open Tender
Civil Works - Others
Percentage
180 days
Umrer
Please refer tender documents
5 documents required · 5 mandatory
₹1.1 L
18 Sept 2026
7 Aug 2026
24 Aug 2026
7 Aug 2026
22 Aug 2026
7 Aug 2026
7 Aug 2026 - 15 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Item Description/ Heading | |||||
| 1.01 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil | 1 | Cum | 1 | ₹1 |
| 1.02 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | - | Cum | - | - |
| 1.03 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources: 6 graded stone aggregate 40 mm nominal size derived from natural sources). | 1 | Cum | 1 | ₹1 |
| 1.04 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) | - | Cum | - | - |
| 1.05 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 1 | Cum | - | - |
| 1.06 | Centering and shuttering including strutting, propping etc. and removal of form for. Foundations, footings, bases of columns, etc. for mass concrete | 1 | Sqm | 1 | ₹1 |
| 1.07 | Centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | 1 | Sqm | - | - |
| 1.08 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Hot rolled deformed bars | - | Kg | - | - |
| 1.09 | Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge | 1 | Cum | - | - |
stage.html
html • 0.06 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.32 MB
BOQ_376218.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .