Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹6.0 L
Closing Date
30 Apr 2026, 3:00 pmClosed
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
14 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or "V" whichever is less ;where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of 'total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet
(a)The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work costing not less than the amount equal to 60% of advertised value of the tender. (b)(1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii)One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender.
Defination of Similar Work :- The tenderer should have done/completed "Design, supply, erection , testing and Commissioning of 50 HZ, single phase,25 KV AC Overhead equipment ".
22 conditions · 5 needing a document upload
Tender Form (First Sheet) as per 'Annexure-'
For Sole Proprietorship firm a)Affidavit as per 'Annexure'. b)Special power of Attorney as per proforma given in 'Annexure' to be submitted by sole proprietor firm duly notarized. (Not required if tender documents are submitted by proprietor himself) (Mandatory)
For Partnership firm a)Self/Notary attested copies of Partnership deed. b)Special Power of Attorney as per proforma given in 'Annexure' to be submitted by Partnership firm. (Not required if one or more partners are authorized in Parternership deed to sign on behalf of the firm.)
For Limited Company a) Copy of Memorandum & Articles of Association of Company. b)Self /Notary attested copy of resolution passed by Board of Directors authorizing its Director/Employee to deal with tender on behalf of company. c) Attested copy of Notarized Special Power of Attorney including ratification clause duly signed by person authorized by the company.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
All material third party inspection has to be ensured. Any exemption from Third party inspection will be given by SRDEE/TRD/Office.
Agency should give there email id and mobile no. on which instruction for daily work will be issued for different site. 12 hour will be given after mail/message for arranging labor and site supervisor
No work can be carried out without availability of site supervisor. if site supervisor is not available , then work will be stopped and penalty of Rs 50,000/ day per site will be imposed for it.
All staff at site should wear all safety gears and follow all safety precaution to avoid any untoward incident .If staff is found without proper safety gear, then work will be stopped and penalty of Rs 50,000 per day per site will be imposed
If staff as per message of SSE/Office is not provided by Agency, then penalty of Rs 50,000 per day per site will be imposed for delay in work on Agency
For any block burst, penalty will be imposed as per train detention cost analysis by operating department.
Work will be need to be done at multiple site at same time. No excuse will be entertained by Administration regarding working at multiple site. In case , staff is not provided by Agency for multiple site, then penalty of Rs 1,00,000 per site per day will be imposed on the Agency.
For any damage to railway, recovery will be made as per cost of damage to railway.
TRD works in connection with Rebuilding of bridge no. 491, 497 and 523 having non-standard plate girders of 9.15m span by PSC Slab with temporary/Permanent diversion in DN line of BG-I section of RNY division.
EL-RNY-TRD-01-2026-27
EL-RNY-TRD-01-2026-27
Open
Works - General
12 Months
Kamrup, Assam
₹0
₹6.0 L
30 Apr 2026
9 Apr 2026
16 Apr 2026
3 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 2,98,77,449.01 | ||
| for details. | Breakup | — | — | ||
| TRD works in connection with Rebuilding of bridge no. 491, 497 and 523 having non-standard plate girders of 9.15m span by PSC Slab with temporary/Permanent diversion in DN line of BG-I section of RNY division. | — | — | — | 2,98,77,449.01 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC-2022-ACSupto61.pdf
ATTACHMENT
GCC_April-2022_2022.pdf
ATTACHMENT
2026_03_13IndianRailwaysStandardGeneralConditionsofContractApril2022AdvanceCorrectionSlipNo_111.pdf ACS GCC 2
ATTACHMENT
PENALTY.pdf
ATTACHMENT
2026_03_13IndianRailwaysStandardGeneralConditionsofContractApril2022AdvanceCorrectionSlipNo_111.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .