| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹26.5 LAccepted-AOC | L-1 | Accepted-AOC some rates are on higher side | |
| 2 | L-2₹28.0 L+₹1.3 L (4.88%)Rejected-Finance DISTT KANGRA HP | KANGRA | HIMACHAL PRADESH | 176001 | L-2 | Rejected-Finance rates are on higher side | |
| 3 | L-3₹32.0 L+₹5.3 L (20.1%)Rejected-Finance | L-3 | Rejected-Finance rates are on higher side | |
| 4 | L-4₹35.8 L+₹9.2 L (34.3%)Rejected-Finance | L-4 | Rejected-Finance rates are on higher side | |
| 5 | L-5₹37.6 L+₹10.9 L (41.0%)Rejected-Finance | L-5 | Rejected-Finance rates are on higher side |
Tender Value
Refer Docs
EMD Value
₹55,851
Closing Date
21 Dec 2020, 5:00 pmClosed
Executive Engineer Jal Shakti Division Chamba
Executive Engineer Jal Shakti Division Chamba
construction of civil work as per NIT
2020_HPIPH_43233_1
EE-JSD-CBA-2020-13532-82 dated 15.12.2020
Open Tender
Civil Works
Item Rate
365 days
Executive Engineer Jal Shakti Division Chamba
Please refer Tender documents.
8 documents required · 8 mandatory
₹400
₹55,851
Yes
12 Mar 2021
15 Dec 2020
22 Dec 2020
15 Dec 2020
21 Dec 2020
15 Dec 2020
15 Dec 2020 - 21 Dec 2020
Amount
Excavation in foundation trenches etc. in earth work in all depths and in all classification of earth work such as pick work,jumper work,saturated soil including bailing or pumping out of water, blasting soft or hard rock or chiselling or wedging out of soft/hard rock, where blasting is prohibited,in all lifts including trimming and dressing or dies, levelling of beds to correct grade including shoning structuring, planking timbering and dewatering whereever required staking the excavatd soil not or than 3 mtr clear form edge of excavation and then returning the stacked soil in 15 cm layer when required into plinths, side of foundation etc. consolidating each deposited layer by ramming and watering and then disposing the surplus excavated earth as directed with in all leads & lifts as per direction as satisfaction of Engineer-in-Charge.
Providing and laying cement conrete 1 : 3 :6 . ( 1 cement : 3 sand and : 6 grade stone aggregate 40mm nominal size) and curing complete excluding cost of form work in foundation and plinth upto all leads and lifts as per the direction and to the entire satisfaction of Engineer-in-Charge.
Providing and laying cement concrete 1:3:6(1: cement :3 sand :6 graded crushed stone aggregate of 20mm. Nominal size) and curing complete excluding the cost of form work in foundation and plinth with in all leads and lifts as per direction of the Engineer-in-charge.
Providing and laying cement concrete 1:1.5:3(1: cement :1.5 sand :3 graded crushed stone aggregate of 20mm. Nominal size) and curing complete excluding the cost of form work and reinforcement for reinforced concrete work in :-
Foundation footing bases of column and the like mass concrete with in all leads and lifts as per direction of the Engineer-in-charge.
Wall ( any thickness but not less than 0.10 mtr. Thickness) including attached pilasters buttersses, plinth and string courses etc, from top of foundation upto floor two level with in all leads and lifts as per direction of the Engineer-in-charge.
Suspended floor roofs, landing and shelves and their support balconies, beams, girders, bressumers and contilever upto floor two level with in all leads and lifts as per direction of the Engineer-in-charge.
Providing and laying cement concrete 1:2:4(1: cement :2 sand :4 graded crushed stone aggregate of 20mm. Nominal size) and curing complete excluding the cost of form work in
Foundation and plinth with in all leads and lifts as per direction of the Engineer-in-charge.
Wall ( any thickness but not less than 0.10 mtr. Thickness) including attached pilasters buttersses, plinth and string courses etc, from top of foundation upto floor two level with in all leads and lifts as per direction of the Engineer-in-charge.
Suspended floor roofs, landing and shelves and their support balconies, beams, girders, bressumers and contilever upto floor two level with in all leads and lifts as per direction of the Engineer-in-charge.
Providing form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as to give a fair finish including centring, shuttering strutting and propping etc. with wooden batten and ballies, in all heights of propping and centring below supporting floor to ceiling and removal of the same for insitu-reinforced concrete and plain concrete work in :-
Vertical surfaces such as wall (any thickness) partitions and the like including attached pillasters, buttresses plinth and string courses and the like within all leads and lifts as per direction and to the entire satisfaction of Engineer-in-charge.
In flat surfaces with steel plates such as soffits of suspended floors, roofs, landing and the like floor etc upto all thickness within all leads and lifts as per direction and to the entire satisfaction of Engineer-in-charge.
Edge of slab brakes in floors and walls under 20mm wide within all leads and lifts as per direction of the Engineer-in-charge.
Foundation footing bases of column, foundation drains etc.within all leads and lifts as per direction of the Engineer-in-charge.
Providing mild steel/tor steel (reinforcement for RCC work) within bending,binding and placing in positioncomplete in all respect including all leads and lifts as per the direction and entire satisfaction of Engineer-in-Charge.
Finishing wall with water profing cement paint of approved brand and manufacture and of required shade on undecorated wall surfaces (two coats) to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials as per direction of Engineer-in-charge
Providing and fixing steel fiber reinforcement cement concrete (SFRC) man hole cover (Medium duty) and frame conforming to IS 12592 (Part-I) 1988 with latest ammendsments internal dia 500mm(Medium Duty) with in all leads and lifts as per direction of the Engineer-in-charge.
Providing & placing in horizontal layers Filtering media duly graded screened washed and cleaned as specified by the Engineer-in-charge.
Top layer Fine sand (Eff: size 0.20mm to 0.40 and Uniformity-co-efficient 2.00 to 3.00)
Second Layer : Coarse and 3mm-6mm
Third Layer:-Bajri 6mm to 20mm
Forth Layer:- 20mm tp 25mm
Bottem Layer:- Broken stone 50mm to 75mm
Providing Precast RCC slab 0.075 cm thick over CC 1:3:6 work below filter media. The Size of slab 48x22 or as [er site required with nominal reinforcement in cement concrete 1:2:4 (1 cement:2 sand: 4 graded stone aggregate 20mm nomial size) with inall leads and lifts as per the direction of Engineer-in-Charge)
Steel work welded in built-up section,trusses and framed work including cutting housting, fixing in position and applying a primering coat of red lead paint in grating, framed guard bar, ladders, railing, brackets and similars work with in all leads and lifts as per the direction of Engineer-in Charge.
Laying, Jointing in trenches galvanized mild steel tubes including fittings complete (earth work in trenches to be measured and paid for seperately as per the direction of the Engineer-in-charge with in all leads and lifts of the following nominal bores:.
65mm dia Nominal bore
50mm dia Nominal bore
25mm dia Nominal bore
20mm dia Nominal bore
15mm dia Nominal bore
Providing and fixing Cast iron Sluice valve (with hand wheel) as per IS: 780 class-I of following diameter including brass spindle with in all leads and lifts as per direction of the Engineer-in-charge.
65mm dia Nominal bore PN 1.00
50mm dia Nominal bore PN 1.00
Providing and fixing brass full way wheel valve of ISI marked of following dia Complete with in all leads and lifts as per direction of the Engineer-in-charge.
25mm dia Nominal bore
20mm dia Nominal bore
15mm dia Nominal bore
Providing and fixing of Brass Tap 15mm dia for house hold connection Complete with in all leads and lifts as per direction of the Engineer-in-charge.
Baldev Singh
Tirath Singh
OM PARKASH KAPOOR
MAHINDER NARYAL
SANJAY SAINI
Gourav Ratra
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .