| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 CrAdmitted-Finance SURAT GUJARAT | JAMNAGAR | GUJARAT | 360110 | L1 | Admitted-Finance | |
| 2 | L2₹4.8 Cr+₹2.8 L (0.59%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | L3₹5.2 Cr+₹47.0 L (9.83%)Admitted-Finance | L3 | Admitted-Finance | |
| 4 | L4₹5.4 Cr+₹63.3 L (13.3%)Admitted-Finance | L4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | R D Water System Pvt Ltd L1 | Genesis International L2 | KUSHYA PROJECTS AND PROCUREMENTS LLP L4 | S Cube Infrastructures L3 |
|---|---|---|---|---|---|---|---|
| 1.00Interception & Diversion of Nallahs with STP works Project of Nayagaon town under SBM 2.0 | |||||||
| 1.10 | 1. Design and build sewage treatment plant of installed capacity 1 MLD and all appurtenant structures and allied works
2. Survey, review the designs, redesign where necessary, and diversion works of Nallahs with pumping main & gravity main of about 1435 m length (Dia-150mm-500mm,DI-K7/NP3) including survey, design, construction of 02 No. of Pumping stations and all appurtenant structures and allied works.
3. Construction of Interception and Diversion Structure – 2 nos.
4. Construction of Drain length 150m.
5. Arrangement of Reuse of Treated wastewater including Collection Sump, Pumps & Pipe.
6. Providing HT Feeder connection upto STP (for 1 km) | 1 | Lump-Sum | 2,84,77,620 ₹2,84,77,620 | 2,90,00,000 ₹2,90,00,000 | 2,70,27,120 ₹2,70,27,120 Lowest | 2,84,77,680 ₹2,84,77,680 |
| 1.20Operation and Maintenance Cost next 10 Years | |||||||
| 1.30 | 1st Year | 1 | Lump-Sum | 6,00,000 ₹6,00,000 Lowest | 6,80,000 ₹6,80,000 | 8,64,200 ₹8,64,200 | 7,50,000 ₹7,50,000 |
| 1.40 | 2nd Year | 1 | Lump-Sum | 6,00,000 ₹6,00,000 Lowest | 7,20,000 ₹7,20,000 | 9,16,052 ₹9,16,052 | 7,95,000 ₹7,95,000 |
| 1.50 | 3rd Year | 1 | Lump-Sum | 6,25,000 ₹6,25,000 Lowest | 7,68,000 ₹7,68,000 | 9,71,015 ₹9,71,015 | 8,42,700 ₹8,42,700 |
| 1.60 | 4th Year | 1 | Lump-Sum | 6,50,000 ₹6,50,000 Lowest | 8,00,000 ₹8,00,000 | 10,29,276 ₹10,29,276 | 8,93,262 ₹8,93,262 |
| 1.70 | 5th Year | 1 | Lump-Sum | 6,75,000 ₹6,75,000 Lowest | 8,24,000 ₹8,24,000 | 10,91,033 ₹10,91,033 | 9,46,858 ₹9,46,858 |
| 1.80 | 6th Year | 1 | Lump-Sum | 7,00,000 ₹7,00,000 Lowest | 8,51,000 ₹8,51,000 | 11,56,495 ₹11,56,495 | 10,03,669 ₹10,03,669 |
| 1.90 | 7th Year | 1 | Lump-Sum | 7,25,000 ₹7,25,000 Lowest | 8,80,000 ₹8,80,000 | 12,25,884 ₹12,25,884 | 10,63,889 ₹10,63,889 |
Tender Value
₹3.2 Cr
EMD Value
₹1.6 L
Closing Date
12 Aug 2026, 5:30 pmClosed
CMO
NAGAR PARISHAD NAYAGAON
Interception Diversion of Nallahs with STP works Project of Nayagaon town under SBM 2.0
2026_UAD_520607_1
1056/UWM/2026
Open Tender
Civil Works - Others
Lump-sum
365 days
NAGAR PARISHAD NAYAGAON
Please refer Tender documents.
3 documents required · 3 mandatory
₹15,000
₹1.6 L
9 Oct 2026
13 Jul 2026
14 Aug 2026
13 Jul 2026
12 Aug 2026
13 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Interception & Diversion of Nallahs with STP works Project of Nayagaon town under SBM 2.0 | |||||
| 1.1 | 1. Design and build sewage treatment plant of installed capacity 1 MLD and all appurtenant structures and allied works
2. Survey, review the designs, redesign where necessary, and diversion works of Nallahs with pumping main & gravity main of about 1435 m length (Dia-150mm-500mm,DI-K7/NP3) including survey, design, construction of 02 No. of Pumping stations and all appurtenant structures and allied works.
3. Construction of Interception and Diversion Structure – 2 nos.
4. Construction of Drain length 150m.
5. Arrangement of Reuse of Treated wastewater including Collection Sump, Pumps & Pipe.
6. Providing HT Feeder connection upto STP (for 1 km) | - | Lump-Sum | 3,23,61,000 | - |
| 1.2 | Operation and Maintenance Cost next 10 Years | - | - | - | - |
| 1.3 | 1st Year | - | Lump-Sum | 8,64,200 | - |
| 1.4 | 2nd Year | - | Lump-Sum | 9,16,052 | - |
| 1.5 | 3rd Year | - | Lump-Sum | 9,71,015 | - |
| 1.6 | 4th Year | - | Lump-Sum | 10,29,276 | - |
| 1.7 | 5th Year | - | Lump-Sum | 10,91,033 | - |
| 1.8 | 6th Year | - | Lump-Sum | 11,56,495 | - |
| 1.9 | 7th Year | - | Lump-Sum | 12,25,884 | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.56 MB
TENDERDOCUMENT.pdf
Tender Documents • 1.97 MB
WORKDETAIL.pdf
Other Document • 2.64 MB
BOQ_627055.xls
BOQ • 0.25 MB
UWMCORIGENDUM.pdf
PDF • 0.96 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .