| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹68.8 LAccepted-AOC | L1 | Accepted-AOC DUE TO L1 | |
| 2 | L2₹87.7 L+₹18.8 L (27.4%)Rejected-Finance | L2 | Rejected-Finance Due to L2 | |
| 3 | L3₹89.0 L+₹20.1 L (29.3%)Rejected-Finance | L3 | Rejected-Finance Due to L3 | |
| 4 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
Refer Docs
EMD Value
₹1.9 L
Closing Date
8 Apr 2022, 1:30 pmClosed
SE IWC MIRZAPUR
SE IWC IRRIGATION COLONY FATHA, MIRZAPUR
nti Erosion Work for the Protection of right bank of River Ganga Near Hargarh Pump House-II,Mirzapur
2022_UPIDC_683704_2
13/SE/2021-22
Open Tender
Civil Works - Water Works
Item Rate
120 days
Near Hargarh Pump House-II
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹1.9 L
12 May 2022
2 Apr 2022
8 Apr 2022
2 Apr 2022
8 Apr 2022
2 Apr 2022
Amount
Excavation of Foundation for launching appron and slope cutting for boulder stepping etc in all type of soil including all lead, lift & labour chagres etc for proper completion of work.
Earth work filling with earth for making proper base behind the crated boulder stepping work including compaction all cost of material lead, lift & labour chagres etc for proper completion of work.
Supplying and laying E.C Bag filled with R.B.M for making platform behing the crated boulder stepping work on slope including cost of all material,labour T&P etc. for proper Completion of work.
Supplying and placing in position E.C Bag filled with R.B.M tying and sewing with machine Synthetic thread in Nylon Crate of Size 1.0 m × 1.0 m × 1.0 m with mesh Knot Size 200 × 200 × 200 mm. for making platform of launching appron made with crated boulder, including cost of all material, labour T&P etc. for proper completion of work.
Supplying & Making 8 SWG G.I Wire crate of Size 2.00 m × 1.50 m × 1.00 m. made with mesh size 0.20 × 0.20 m. for crated boulder stepping over slope & launching appron including all cost of material labour and T&P etc for Proper Completion of work.
Supplying and placing Stone boulder in G.I wire crate of Size 2.00 m × 1.50 m × 1.00 m. in stepping and launching appron including all cost of material labour and T&P etc but excluding cost of G.I Wire Crate.
Construction of granular sub-base providing well graded material spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotavator at OMC and compacting with smooth whell roller to achieve the desired density complete as per technical Specification clause 401
Laying C.C (1:3:6) in foundation with cement,course sand and hard stone ballast including all cost of material, labour, T&P, Taxes etc required for proper completion of work.
Laying C.C (1:2:4) for laying Pump House pipe with cement,course sand FM not less than 2.0 and hard Stone grit 4.75 to 20 mm including all cost of material, labour, T&P, Taxes etc. required for proper completion of work.
J P S CONSTRUCTION
R.B.S. CONSTRUCTION
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .