| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.3 CrAdmitted-Finance | +27.00% | ₹3.3 Cr | L1 | Admitted-Finance |
Tender Value
₹2.6 Cr
EMD Value
₹5.1 L
Closing Date
11 Aug 2026, 10:00 amClosed
Superintending Engineer, Western Circle II
Office of The SE, Western Circle II, Station Road, Midnapore, Paschim Medinipore, I and W Dte, PIN 721101
Construction of Single Lane R.C.C. Bridge over Branch Channal of river Buriganga, at Mouza-Suratpur Padima Shyamchak in Block and P.S - Keshpur, and Dist.- Paschim Medinipur in connection with Ghatal Master Plan.
2026_IWD_1030651_2
WBIW/SE/WC-II/NIT-02e/2026-27 2nd Call of e-NIT No WBIW/SE/WC-II/NIT-06e/2025-26 Sl 01,02 , 03
Open Tender
CIVIL WORKS
Percentage
540 days
BLOCK KESHPUR
AS DEPICTED IN THE NIT
7 documents required · 7 mandatory
₹5.1 L
Yes
3 Sept 2026
8 Jul 2026
12 Aug 2026
8 Jul 2026
11 Aug 2026
8 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing Bored Cast-in-situ R.C.C. pile in position as per specifications in all kinds of soil including cost of boring using drilling mud to stabilize the bore and flushing the bore of excess mud with freshly prepared drilling fluid by using pumps prior to placing concrete by tremie pipe in one continuous operation and including the cost of all materials and labour for placing of concrete and also including the cost of mobilization and hire charges of all equipment necessary for boring, welding of reinforcement cage as necessary and lowering of reinforcement cage, preparation and placing of concrete, including the cost of concrete but excluding the cost of reinforcement and labour for bending binding etc. complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m. Work to be executed as per IS: 2911 (Part II Sec 2).
(b) Using tripod, winches
v) Pile diameter - 1000 mm. | 0.2 | METRE | 8,722.04 | ₹1,735.69 |
| 2 | Providing MS casing pipe around RCC cast-in-situ bored piles of different diameters in position including cost of all materials, fabrication, handling etc. complete as per direction of Engineer-in-Charge. | - | MT | 73,911.45 | - |
| 3 | Excavation for Structures
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling with approved material complete as per direction of the Engineer-in-Charge.
I. In all sorts of soil excluding marshy soil & rocks (soft or hard) by manual means.
a) upto 3 m depth
(i) With pumping out water including shoring as required. | - | CUM | 147.78 | - |
| 4 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling with approved material complete as per direction of the Engineer-in-Charge.
In all sorts of soil excluding marshy soil & rocks (soft or hard) by manual means.
3 m to 6 m depth
With pumping out water including shoring as required. | 1 | CUM | 196.65 | ₹196.45 |
| 5 | Earthwork in filling in foundation trenches with good earth in layers not exceeding 15cm. including watering and ramming layer by layer complete with earth obtained from excavation of foundation or from fresh excavation of land arranged by Department within a lead of 150 m. | 1 | CUM | 109.65 | ₹109.54 |
| 6 | Providing and laying Design Mix concretefor plain / reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost of labour and materials for formwork & reinforcement works.
M-15 Grade: Using concrete mixer. | 1 | CUM | 6,345.29 | ₹6,338.94 |
| 7 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications.
RCC Grade M30
Using concrete mixer | - | CUM | 7,759.2 | - |
| 8 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications.
PCC Grade M20 | - | CUM | 7,445.15 | - |
| 9 | Cement Concrete for Reinforced Concrete in Pile Cap complete as per drawing and Technical Specification.
RCC Grade M30
Using Concrete Mixer | 0.2 | CUM | 8,198.14 | ₹1,631.43 |
| 10 | Supplying, fitting and placing un-coated HYSD bar reinforcement in Bridge Foundation including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications and direction of Engineer-in-charge
ii) a. Tor Steel rods / HYSD bars /
TMT bars (SAIL/ TATA/ RINL )
(Fe 415 /Fe 500 /Fe 500D, conforms to IS: 1786) | 0.6 | TONNE | 72,617.03 | ₹43,570.22 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.53 MB
Tendernotice_2.pdf
PDF • 0.30 MB
Tendernotice_3.pdf
PDF • 2.22 MB
BOQ_2530845.xls
BOQ • 0.36 MB
Corrigendum_I.pdf
PDF • 0.66 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .