| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹2.0 L+₹8,814 (4.57%)Admitted-Finance 59 R G S ROAD USHAGRAM DURGAMANDIR ASANSOL BARDHAMAN 713303 WEST BENGAL INDIA | ASANSOL | BARDHAMAN | WEST BENGAL | 713303 | L2 | Admitted-Finance | |
| 3 | Rejected-Technical KHANDRA BARDHAMAN 713363 WEST BENGAL INDIA | KHANDRA | BARDHAMAN | WEST BENGAL | 713363 | - | Rejected-Technical as per approved TCR |
| Sl No | Description | Qty | Unit | ROY ENTERPRISE L2 | NEW ELECTRICAL CONCERN L1 |
|---|---|---|---|---|---|
| 1.01 | DISMANTLING OF CORE AND WINDING FROM TANK AND CLEANING OF ALL PARTS PROPERLY | 1 | LS | 5,800 ₹5,800 | 5,500 ₹5,500 Lowest |
| 1.02 | MATERIAL COST BAR COPPER CONDUCTOR FOR PRIMARY COIL | 150 | kg | 905 ₹1,35,750 Lowest | 905 ₹1,35,750 Lowest |
| 1.03 | MATERIAL COST BAR COPPER CONDUCTOR FOR SECONDARY COIL | 162 | kg | 905 ₹1,46,610 Lowest | 905 ₹1,46,610 Lowest |
| 1.04 | MATERIAL COST TPC FOR BAR COPPER CONDUCTOR FOR PRIMARY AND SECONDARY COILS | 439 | kg | 165 ₹72,435 | 150 ₹65,850 Lowest |
| 1.05 | MATERIAL COST BRAZING RUPATON ROD, OXYGEN,DA FOR BRAZING OF ALL PRIMARY AND SECONDARY INTERCONNECTION | 1 | LS | 2,750 ₹2,750 | 2,500 ₹2,500 Lowest |
| 1.06 | SUPPLY AND FITTING OF NEOPRENE SYNTHETIC GASKET AT TOP COVER AND INSPECTION COVER | 1 | LS | 4,250 ₹4,250 | 4,000 ₹4,000 Lowest |
| 1.07 | SUPPLY AND FITTING OF NEW TAP CHANGER MECHANISM COMPLETE | 1 | LS | 8,500 ₹8,500 | 8,200 ₹8,200 Lowest |
| 1.08 | INSULATING MATERIALS, VARNISH PAPER, OIL,DUCT, COTTON TAPE, WEBBING TAPE, ETC | 1 | LS | 12,950 ₹12,950 | 12,800 ₹12,800 Lowest |
| 1.09 | PAINTING OF ABOVE TRANSFORMER BY ONE COST OF PRIMER PAINT AND TWO COATS OF METALLIC PAINT | 1 | LS | 2,200 ₹2,200 | 2,000 ₹2,000 Lowest |
| 1.10 | LABOUR CHARGES | 1 | LS | 8,250 ₹8,250 | 8,000 ₹8,000 Lowest |
Tender Value
₹2.3 L
EMD Value
₹2,900
Closing Date
14 Mar 2026, 4:00 pmClosed
GM SSA
Office of the General Manager, Satgram-Sripur Area, PO-Devchandnagar, WestBengal-713332
Complete Overhauling and Necessary repairing of one No Lighting Transformer 500KVA, 11KV/440 Volts of Sripur Office under Satgram-Sripur Area
2026_ECL_355468_1
ECL/SSA/GM/E M/E-NIT/2025-26/148 dt 02.03.2026
Open Tender
Electrical and Maintenance Works
Item Rate
7 days
Sripur Colliery
Please refer Tender documents.
4 documents required · 4 mandatory
₹2,900
23 Mar 2026
5 Mar 2026
16 Mar 2026
5 Mar 2026
14 Mar 2026
5 Mar 2026
5 Mar 2026 - 9 Mar 2026
DISMANTLING OF CORE AND WINDING FROM TANK AND CLEANING OF ALL PARTS PROPERLY
MATERIAL COST BAR COPPER CONDUCTOR FOR PRIMARY COIL
MATERIAL COST BAR COPPER CONDUCTOR FOR SECONDARY COIL
MATERIAL COST TPC FOR BAR COPPER CONDUCTOR FOR PRIMARY AND SECONDARY COILS
MATERIAL COST BRAZING RUPATON ROD, OXYGEN,DA FOR BRAZING OF ALL PRIMARY AND SECONDARY INTERCONNECTION
SUPPLY AND FITTING OF NEOPRENE SYNTHETIC GASKET AT TOP COVER AND INSPECTION COVER
SUPPLY AND FITTING OF NEW TAP CHANGER MECHANISM COMPLETE
INSULATING MATERIALS, VARNISH PAPER, OIL,DUCT, COTTON TAPE, WEBBING TAPE, ETC
PAINTING OF ABOVE TRANSFORMER BY ONE COST OF PRIMER PAINT AND TWO COATS OF METALLIC PAINT
LABOUR CHARGES
PROFIT
transportation charges
Less Old Unused Scrap Value
Total impact of GST for the purpose of CTC
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.07 MB
Tendernotice_2.pdf
PDF • 0.79 MB
BOQ_368310.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .