DRDA Building,Near Employment office,Theni
Strengthening of road and Construction of 3 paver block roads in Chinnamanur Block under SCPAR 2020-2021
2021_RDTN_193901_1
2990/2019/D5 Dated 02.02.2021
Open Tender
Civil Works
Item Rate
180 days
Theni
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹30,000
17 Jun 2021
5 Feb 2021
12 Feb 2021
5 Feb 2021
12 Feb 2021
5 Feb 2021
Amount
Construction of Paver Block with drain in Rice mill street at AD colony
Earth work execavation abd depositing on bank with in intial lead of 10 mts and lift of 2 mts in narrow trenches for laying the pipes in all kinds of soils as directed by the departmental officers
Cement Concrete 1:4:8 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Centering and shuttering charges for side wall side works including cost and conveyance of all labour charges
Cement Concrete 1:3:6 Using 20 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Cement Concrete 1:3:6 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Supplying Fabricating and placing in position of HSD steel rods for reinforcement including the cost of steel and binding wire etc, complete as per standard specification.
Reinforced Cement concrete1:1.5:3 mix by using 20mm HBG metal including all other labourcharges etc complete
Supply and filling well gravel from approved quarry including all other labourcharges etc complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Supplying and laying of 60mm thick high strength type of inter locking pavement block in required shap in CM 1:1.2 using 10 -12mm size HBG stone jelly including cost of centering shuttering laying vibrating ( Mechanical vibrating) finishing, curing land the cost including transporting charges etc., complete.
plastering in CM 1:5 Mix12mm Thick including all other labour charges etc complete
Construction of Paver Block with drain at new AD colony
Earth work execavation abd depositing on bank with in intial lead of 10 mts and lift of 2 mts in narrow trenches for laying the pipes in all kinds of soils as directed by the departmental officers
Cement Concrete 1:4:8 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Centering and shuttering charges for side wall side works including cost and conveyance of all labour charges
Cement Concrete 1:3:6 Using 20 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Cement Concrete 1:3:6 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Supplying Fabricating and placing in position of HSD steel rods for reinforcement including the cost of steel and binding wire etc, complete as per standard specification.
Reinforced Cement concrete1:1.5:3 mix by using 20mm HBG metal including all other labourcharges etc complete
Supply and filling well gravel from approved quarry including all other labourcharges etc complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Supplying and laying of 60mm thick high strength type of inter locking pavement block in required shap in CM 1:1.2 using 10 -12mm size HBG stone jelly including cost of centering shuttering laying vibrating ( Mechanical vibrating) finishing, curing land the cost including transporting charges etc., complete.
plastering in CM 1:5 Mix12mm Thick including all other labour charges etc complete
Construction of Paver Block road in Sudha house to Panjammal house
Earth work execavation abd depositing on bank with in intial lead of 10 mts and lift of 2 mts in narrow trenches for laying the pipes in all kinds of soils as directed by the departmental officers
Cement Concrete 1:4:8 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Centering and shuttering charges for side wall side works including cost and conveyance of all labour charges
Cement Concrete 1:3:6 Using 20 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Cement Concrete 1:3:6 Using 40 mm HBG metal for basement and flooring layers not more than 15cm thick including cost and conveyance of materials to site and all other labour charges including consolidation as per standard specification.
Supplying Fabricating and placing in position of HSD steel rods for reinforcement including the cost of steel and binding wire etc, complete as per standard specification.
Reinforced Cement concrete1:1.5:3 mix by using 20mm HBG metal including all other labourcharges etc complete
Supply and filling well gravel from approved quarry including all other labourcharges etc complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Supplying and laying of 60mm thick high strength type of inter locking pavement block in required shap in CM 1:1.2 using 10 -12mm size HBG stone jelly including cost of centering shuttering laying vibrating ( Mechanical vibrating) finishing, curing land the cost including transporting charges etc., complete.
plastering in CM 1:5 Mix12mm Thick including all other labour charges etc complete
Strengthening of west burial ground road Km0/0-0/0/4
Clearing scrub jungle by uprooting including all cutting charges and depositing of the products and clearing as directed by the departmental officers including all incidental charges etc. complete.Sl.No. 17(3)
Earth work excavating and depositing on bank with an initial lead of 10m and initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, muram, gravel stoney earth and earth mixed with small size boulders SS 20 A including laying and spreading in layers of 250mm loose thick each, sectioning, watering and compacting etc.., complete as per MORT & H 301-305
Collection and Supply of Red gravel from the approved quarry incl cost and conveyence of all materials to site incl all labour charges for spreading and compaction with power roller etc for shouklders etc to complete
Picking the existing metal surface 7.5 cm much removing the picked up stuff to the sides, collection all useful metal leveling and sectioning top camper power roller ansolidation by power roller etc.,
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying premix carpet with seal coat type A, 20mmconsolidated thickness using IRC size machine broken HBG metal 0.18cum of 13.2mm and 0.09cum of machine crushed broken HBG metal of 11.20mm with 14.60kg of bitumen for premixing for 10sqm of premix carpet and 0.09cum 0.09cum of 6.70mm IRC size machine broken HBG metal with 9.80kgs of bitumen for sealcoat including cost and conveyance of all materials from approved quarry including the cost of bitumen which will be supplied departmentally and cost will be recovered at the rates specified in the special condition appended herewith and including conveyance bitumen to workspot handling charges for the same at both ends including labour charges for heating the bitumen to required temperature and mixing the required quantity of metal and bitumen using mini hot mix plant conveying the mix by wheel borrow including labour charges for spreading the mix to grades,lines and profile and consolidation with power roller rolling etc.,including hire,fuelcharges and running charges for mini hot mix plant,power roller and all other tools and plants employed &all incidental charges.No.509&513 of MOST.
Provision for HM stone
sign board
Name board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
P SENTHILKUMAR
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .