Loading…
Loading…
Tender Value
₹5.2 L
EMD Value
₹10,420
Closing Date
11 Sept 2026, 3:00 pm
Block Development officer (BP)
kandhili block
Repair and Renovation work of PUM School South facing RCC Roof Building at Goundapanur in Sevathur Panchayat
2026_RDTN_698260_1
A2/420/2026
Open Tender
Civil Works
Item Wise
180 days
Kandhili block
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹10,420
27 Aug 2026
27 Aug 2026
12 Sept 2026
27 Aug 2026
11 Sept 2026
27 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Repair and Renovation work of PUM School South facing RCC Roof Building at Goundapanur in Sevathur Panchayat | - | - | - | - |
| 2 | Dismantling of pressed tiles including all cost and conveyance of men and materials etc/. All complete | 82.8 | Sqm | - | - |
| 3 | Dismantling of Ceiling plastering including all cost and conveyance of men and materials etc/. All complete | 82.8 | Sqm | - | - |
| 4 | Weathering course in brick jelly lime concrete using broken brick jelly of size 20mm uniform gauge in pure slaked lime (no crushed stone M.Sand to be used) to the proportion of brick jelly to lime being 32:12.5 by volume and laid over the RCC roof slab in a single layer of required slope and finished by beating the concrete with wooden beaters of approved pattern, keeping the surface constantly wet by sprinkling lime jaggery water, etc., complete as per standard specification and as directed by the deparmental officers. | 6.21 | Sqm | - | - |
| 5 | Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers | 82.8 | Sqm | - | - |
| 6 | Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. | 85.8 | Sqm | - | - |
| 7 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete). The Putty should be got approved by the Executive Engineer before use on work. (Based on SoR 2023-24) | 82.8 | Sqm | - | - |
| 8 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer | 188.28 | Sqm | - | - |
| 9 | Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358 | 170.56 | Sqm | - | - |
| 10 | Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) | 21.36 | Sqm | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.90 MB
Tendernotice_2.pdf
PDF • 1.14 MB
BOQ_839351.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].