Construction of Archaka Residential Quarters(G+1) and Balance work of Adyathmika Bhavan at Sri Venkateswara Swamy Temple in Wanaparthy District,Est.Cost:198.00 Lakhs
737613
NIT No. 49/2026-27,Dt:24.09.2026 of the Regional Officer,PR Wanaparthy(1st call)
OPEN
Buildings
WANAPARTHY, TELANGANA
17 documents required · 17 mandatory
₹5,816
₹1.6 L
28 Sept 2026
28 Sept 2026
28 Sept 2026
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308) including cost and conveyance of all material and labour charges and contractors profit & over heads but excluding GST & seignorage charges etc., complete. for Mechanical Means Upto 3.0mts Depth
Plain Cement Concrete of (1:4:8:) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG M/c (SS5) metal with concrete mixture including cost and conveyance of all materials like cement, sand(unscreened), coarse aggregate, water etc. to site, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, overhead charges & Contractors profit etc., complete but excluding GST & seigniorage charges, sales & other taxes on all materials,for finished item of work for Foundations (APSS No. 402).
Construction of RR Masonry in CM (1:6) Cement: Sand) using hard granite stones from approved quarry including cost and conveyance of all materials like Granite stones, cement, sand, water, etc., to site including cost and conveyance of all material and all operational, incidental, and labor charges such as cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc., and including over heads & contractor's profit, but excluding GST and seigniorage charges complete for finished item of work for foundation and basement (APSS No. 601 & 615)
Supply and filling of gravel in trenches, sides of foundations and basement with initial lead in layers by watering and ramming including cost and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310) including cost and conveyance of all material and labour charges, and contractors profit & over heads but excluding seignorage charges and GST etc., complete.
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 400 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for footings
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 400 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for Pedastals
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 400 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for Plinth Beams
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 400 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for columns in GF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 400 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for columns in FF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof beams in GF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof beams in FF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof slabs 125mm thick GF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof slabs 125mm thick FF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof slabs 150mm thick GF
Reinforced Cement Concrete M 20 Nominal Mix ( by weigh batching/concrete mixer ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work but excluding seigniorage charges (APSS No. 402 & 403) for roof slabs 150mm thick FF
Providing high yield strength deformed (HYSD) steel TMT bars (Fe 415 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including Cost and Conveyance of bars from approved sources to site of work with all taxes including Cost and Conveyance of binding wire, cover blocks chains, overlaps, spacess, dowels, wastage etc, and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and other taxes,on cost of all materials complete for finished item of work (APSS No.126) in all floors
Providing brick work of 230mm thick in CM (1:6) prop., using common burnt clay bricks of class as per Table-1 of IS:1077-1992 Non-Modular or traditional size , including cost & conveyance of all material and labour charges, centering & scafolding charges, and overhead charges & Contractors profit etc., complete as per APSS No.501 for Super structure and others but excluding GST and seignorage chages. GF
Providing brick work of 230mm thick in CM (1:6) prop., using common burnt clay bricks of class as per Table-1 of IS:1077-1992 Non-Modular or traditional size , including cost & conveyance of all material and labour charges, centering & scafolding charges, and overhead charges & Contractors profit etc., complete as per APSS No.501 for Super structure and others but excluding GST and seignorage chages.FF
Reinforced Brick Masonry 115mm thick in superstructure with CM (1:4) prop: using 2nd class Bricks from approved source having minimum crushing strength of 50 kg/cm2 and placing 2 No.s of 6mm dia MS bars in every 3rd layer with free ends keyed into mortar joints including all operational & incidental, scaffolding, lift & labour charges, and Cost and Conveyance of all materials etc., complete for finished item of work but excluding seigniorage charges. (APSS No. 501 & 504) GF
Reinforced Brick Masonry 115mm thick in superstructure with CM (1:4) prop: using 2nd class Bricks from approved source having minimum crushing strength of 50 kg/cm2 and placing 2 No.s of 6mm dia MS bars in every 3rd layer with free ends keyed into mortar joints including all operational & incidental, scaffolding, lift & labour charges, and Cost and Conveyance of all materials etc., complete for finished item of work but excluding seigniorage charges. (APSS No. 501 & 504) FF
Plastering to brick masonary wall with 12mm thick double coat in CM (1:5) 8 mm thick base coat and CM (1:3) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for Internal Walls.GF
Plastering to brick masonary wall with 12mm thick double coat in CM (1:5) 8 mm thick base coat and CM (1:3) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for Internal Walls.FF
Plastering to brick masonary wall with 20mm thick double coat in CM (1:6) 16 mm thick base coat and CM (1:4) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for outer Walls.GF
Plastering to brick masonary wall with 20mm thick double coat in CM (1:6) 16 mm thick base coat and CM (1:4) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for outer Walls.GF
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalent and shade over Priming Coat with Cement Primer Waterbase Exterior Gr- 1 Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding other taxes etc, complete for finished item of work as per SS 912 for external walls.GF
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalent and shade over Priming Coat with Cement Primer Waterbase Exterior Gr- 1 Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding other taxes etc, complete for finished item of work as per SS 912 for external walls.FF
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalent and shade over Priming Coat with Cement Primer Waterbase Interior Gr- 1 Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding other taxes etc, complete for finished item of work as per SS 911 for internal walls GF
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalent and shade over Priming Coat with Cement Primer Waterbase Interior Gr- 1 Asian/ Berger/ Nerolac/ Saicoat/Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding other taxes etc, complete for finished item of work as per SS 911 for internal walls FF
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per bag of cement laid over roof when it is green including over heads & contractor profitcost and conveyance of all materials and all operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab but excluding other taxes and seignorage charges etc,, complete for finished item of work
Flooring with vitrified tiles of 1st quality Double charged / multi charged stain free full body porcelain vitrified tiles with double layer pigment of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost and conveyance of all materials like cement, sand, and water and flooring tiles etc., complete, including over heads & contractor profit, labour charges etc., complete for finished item of work, but excluding other taxes and seignorage charges GF
Flooring with vitrified tiles of 1st quality Double charged / multi charged stain free full body porcelain vitrified tiles with double layer pigment of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost and conveyance of all materials like cement, sand, and water and flooring tiles etc., complete, including over heads & contractor profit, labour charges etc., complete for finished item of work, but excluding other taxes and seignorage charges FF
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including over heads & contractor profit cost and conveyrance of all materials like tiles, cement, sand and water etc., complete but excluding other taxes and seigniorage charges, etc., complete for finished item of work. GF
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including over heads & contractor profit cost and conveyrance of all materials like tiles, cement, sand and water etc., complete but excluding other taxes and seigniorage charges, etc., complete for finished item of work. GF
Flooring with Ceramic non skid tiles of not less than 7.3mm thick 1st quality laid over floor bed /VRCC slab set over 12.0 mm th.in CM (1:8 ) prop. base coat and neat grey cement slurry of honey like consistence spread at the rate of 3.3 kg of cement per Sqm and jointed with neat white cement paste mixed with pigment of matching shade including cost and conveyance of all materials to site, including cost of mixing of mortar and watering, leveling to proper slope and curing including over heads & contractor profit, all labour charges etc., and excluding GST and seignorage charges for finished item of work but excluding cost of CC bed and dadooing to walls GF
Flooring with Ceramic non skid tiles of not less than 7.3mm thick 1st quality laid over floor bed /VRCC slab set over 12.0 mm th.in CM (1:8 ) prop. base coat and neat grey cement slurry of honey like consistence spread at the rate of 3.3 kg of cement per Sqm and jointed with neat white cement paste mixed with pigment of matching shade including cost and conveyance of all materials to site, including cost of mixing of mortar and watering, leveling to proper slope and curing including over heads & contractor profit, all labour charges etc., and excluding GST and seignorage charges for finished item of work but excluding cost of CC bed and dadooing to walls FF
Providing dadooing to walls with glazed red or white full body ceramic wall tiles of size glazed red or white full body ceramic wall tiles of size 300 x 600 mm and thickness between 6-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including over heads & contractor profit, cost of all materials like tiles, cement, sand and water etc., complete including complete for finished item of work, but excluding other taxes and seignorage charges. (BLD-CSTN-9-18) GF
Providing dadooing to walls with glazed red or white full body ceramic wall tiles of size glazed red or white full body ceramic wall tiles of size 300 x 600 mm and thickness between 6-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including over heads & contractor profit, cost of all materials like tiles, cement, sand and water etc., complete including complete for finished item of work, but excluding other taxes and seignorage charges. (BLD-CSTN-9-18) FF
Supply and fixing of Medium Teak wood Door frame of size 1.20x 2.10M section of size 100x75MM and as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications
Supply and fixing of sal wood Door frame of size 0.90x 2.10M section of size 100x75MM and as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications
Supply and fixing of Country wood Door shutter of frame size 0.90x2.10m with fully pannlled single door shutter and shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm and intermediate rails of 125 x 38 mm and panels - 3 no's are of 25mm thick as per approved design with fixtures of 300 mm long Stainless Steel aldrop-1 no,125mm long Stainless steel butt hinges 3 No's, Door stoppers-1no, 200mm long Stainless steel Tower bolt - 1no's MS powder coated 300mm long latches - 1no's Stainless steel handles 150mm long 2no's, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications ( Without Frame)
Supply and fixing of Country wood Door shutter of frame size 1.20x2.10m with fully pannlled single door shutter and shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm and intermediate rails of 125 x 38 mm and panels - 3 no's are of 25mm thick as per approved design with fixtures of 300 mm long Stainless Steel aldrop-1 no,125mm long Stainless steel butt hinges 3 No's, Door stoppers-1no, 200mm long Stainless steel Tower bolt - 1no's MS powder coated 300mm long latches - 1no's Stainless steel handles 150mm long 2no's, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications ( Without Frame)
Supplying and fixing of Unplasticized Poly Vinyl Chloride (UPVC) 3 track sliding windows with mesh shutter – (2-glass shutters and 1-mesh shutter) duly manufactured using UPVC reinforced profiles (Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin) of (94 mm x 45 mm)/(80 mm x 52 mm) x 2.20 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x 2.20 mm for sliding shutter frames capable of mounting single glazing system structurally reinforced with hot dip galvanized up to 50 microns of minimum thickness of 1.0/1.2 mm prefabricated & welded through fusion welding. The window sash shall be fitted with 5 mm thick clear float glass of reputed make and mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2.0 mm fitted with Vinyl Coated Fibre mesh- on rollers/ pulley duly fixed with Grey colour TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour soft PVC. System shall have single point locking with Touch Lock and the system is to be installed at the site using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories, labour charges for transportation, erection at site complete for finished item of work.
Providing brick work of 230mm thick in CM (1:6) prop., using common burnt clay bricks of class as per Table-1 of IS:1077-1992 Non-Modular or traditional size , including cost & conveyance of all material and labour charges, centering & scafolding charges, and overhead charges & Contractors profit etc., complete as per APSS No.501 for Super structure and others but excluding GST and seignorage chages.
Reinforced Brick Masonry 115mm thick in superstructure with CM (1:4) prop: using 2nd class Bricks from approved source having minimum crushing strength of 50 kg/cm2 and placing 2 No.s of 6mm dia MS bars in every 3rd layer with free ends keyed into mortar joints including all operational & incidental, scaffolding, lift & labour charges, and Cost and Conveyance of all materials etc., complete for finished item of work but excluding seigniorage charges. (APSS No. 501 & 504)
Plastering to brick masonary wall with 12mm thick double coat in CM (1:5) 8 mm thick base coat and CM (1:3) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for Internal Walls.
Plastering to brick masonary wall with 20mm thick double coat in CM (1:6) 16 mm thick base coat and CM (1:4) of 4mm thick top coat with dubara sponge finish including cost and conveyance of all material and labour charges, over heads & contractor profit, all operational, incidental such as scaffolding charges, lift charges, including cutting of Grooves,finishing, curing, but excluding GST and seignorage charges, etc., complete for for finished item of work. (APSS 901,903 & 904) (CSSR) for outer Walls.
Flooring with vitrified tiles of 1st quality and of size not less than 600 x 600 mm x 8 mm thickness glossy finish double charged permium colours, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost and conveyance of all materials like cement, sand, and water and flooring tiles etc., complete, including over heads & contractor profit, labour charges etc., complete for finished item of work, but excluding GST and seignorage charges.
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including over heads & contractor profit cost and conveyrance of all materials like tiles, cement, sand and water etc., complete but excluding GST and seigniorage charges, etc., complete for finished item of work.
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat / Indocem or Equivalent and shade over Priming Coat with Cement Primer Waterbase Interior Gr- 1 Asian/ Berger/ Nerolac/ Saicoat / Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding GST etc, complete for finished item of work as per SS 911 for internal walls
Painting to new walls with 2 coats of acrylic Emulsion Paint Asian/ Berger/ Nerolac/ Saicoat / Indocem or Equivalent and shade over Priming Coat with Cement Primer Water base exterior Gr- I Asian/ Berger/ Nerolac/ Saicoat / Indocem or Equivalenton New Plastered Surfaceafter thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges but excluding GST etc, complete for finished item of work as per SS 912 for external walls.
Supply and fixing of Medium Teak wood Door frame of size 1.20x 2.40M section of size 125x100MM and as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications
Supply and fixing of Medium teak wood Door frame of size 1.80 x 2.40M section of size 125x100MM and as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications
Supply and fixing of Medium Teak wood Door frame of size 0.90x 2.40M section of size 100x75MM and as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, with necessary screws complete including cost and conveyance of all materials and labour charges etc. complete as per specifications
Supplying and fixing of Unplasticized Poly Vinyl Chloride (UPVC) 3 track sliding windows with mesh shutter – (2-glass shutters and 1-mesh shutter) duly manufactured using UPVC reinforced profiles (Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin) of (94 mm x 45 mm)/(80 mm x 52 mm) x 2.20 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x 2.20 mm for sliding shutter frames capable of mounting single glazing system structurally reinforced with hot dip galvanized up to 50 microns of minimum thickness of 1.0/1.2 mm prefabricated & welded through fusion welding. The window sash shall be fitted with 5 mm thick clear float glass of reputed make and mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2.0 mm fitted with Vinyl Coated Fibre mesh- on rollers/ pulley duly fixed with Grey colour TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour soft PVC. System shall have single point locking with Touch Lock and the system is to be installed at the site using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories, labour charges for transportation, erection at site complete for finished item of work.
Providing thermo mechanically treated (TMT) /HYSD reinforcement (Fe-500/550D grade as per IS 1786-2008of different diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying including soverhead charges & Contractors profit but exlcuding other taxes and other taxes on all materials etc., complete for finished item of work in all floors.( APSS No.126)
Providing Mild steel flats and bars for fabricating steel works like Window Grills, Compound Wall Grills, Iron Doors, Windows including cost of welding rods, power charges, including cost of fixing in position as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, all operational, incidental, and labour charges such as cutting, bending, placing in position etc., but excluding GST for finished item of work (APSS No.126) in all floors. For window grills, staircase railing & Compound wall grills etc
Supplying and fixing of SWR PVC pipes (Prince/ Sudhakar /Kisan/ Supreme or any ISI brand) 4 Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)b)110mmdia
Supplying and fixing of SWR PVC pipes (Prince/ Sudhakar /Kisan/ Supreme or any ISI brand) 4 Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)b)75mmdia TBSP-H.I-01
Supply and Fixing of CPVC Pipes ( 28.60 mm OD Pipe - SDR 13.5 )and Fittings to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" ton 2" SDR 11 and SDR 13.5 pipes are made from idential CPVC compounds having the same physical Properties for Hot and Cold Water (IS 15778:2007) of Ashirvad / Ajay Flowguard including cost and conveyance of all material, labour charges, and over heads but excuding VAT.
Supply and Fixing of CPVC Pipes ( 22.20mm OD Pipe - SDR 13.5 )and Fittings to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" ton 2" SDR 11 and SDR 13.5 pipes are made from idential CPVC compounds having the same physical Properties for Hot and Cold Water (IS 15778:2007) of Ashirvad / Ajay Flowguard including cost and conveyance of all material, labour charges, and over heads but excuding VAT.
Providing & Placing on Terrace (at all floor levels) polyethylene water storage tank with Double layer approved brand & manufacture with cover and suitable locking arrangement & making necessary holes for inlet & outlets and over flow pipes but without fittings & base support for tanks
Supply & fixing 580mm x 440mm size white virerous orissa pan with attached footrests of approved make confirming to IS 2556 (part - III) with 'P' or 'S' trap, including 10 lit. low level PVC flusihing system confirming to IS 7231 with all internal fittings, CI brackets, 32mm dia CP flush pipe, 15mm dia 450mm long PVC connerctor, 15mm dia Cp brass strop cock 300 grams of ISI make, cutting and making good the walls and floors wherever required including cost & conveyance of all material to work site, all labour charges for all operations for fixing etc., complete for finished item of work.
S&F of 15 mm brass body CP finish bib tap of not less than 300 grams weight screw type (full turn) with internal / external threaded connection conforming to IS 8931
Supplying and fixing 25.4mm dia 609.6mm long aluminium anodised towel rods with brackets and alluminium screews etc., complete for finished item of work including cost and conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc., complete for finished item of work for All Floors but excluding GST.
Supplying and fixing of CP brass soap dish with SCREWS including cost and conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc., complete for finished item of work for All Floors. Excluding GST.
Constructing 457.2mm x 457.2mm ( 1'-6" x 1'-6") brick in CM (1:6) prop. Masonry inspection chamber upto 914.4mm (3'-0") and fitted with light weight 457.2mm x 457.2mm ( 1'-6" x 1'-6") C.I. frame and cover of 20Kg. including cost and conveyance of all materials to site, all labour charges, but excluding seignorage charges and VAT complete for finished item of work.
Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks of 230 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, and all incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing, but excluding seignorage charges and VAT etc., complete for finished item of work. (A.P.S.S. No. 1325).
Supply and fixing of 3" (76.2 mm ) Nahany Trap with Jali - UPVC/SWR Pipe fittings (Prince/Sudhakar or any ISI Brand) including cost and conveyance of all materials and labour charges etc., complete for All Floors. including cost and conveyance of all materials and all incidental and operational, labour charges, lift charges, but excluding seignorage charges and VAT etc., complete for finished item of work. (A.P.S.S. No. 1325).
Supply and Laying of 25mm outer dia heavy (2.20mm thickness) grade with IS:9537 part 3 regid PVC pipe of makes Sudhakar / Maco Plast / Modi. make concealed in Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges, cost and conveyance of all material, all labour charges, and contractor profit etc., complete but excluding VAT.
Supply and laying of 25mm dia 1.8mm thick P.V.C.pipe ISI mark of Sudhakar / Maco Plast / Modi make concealed in wall with PVC / Metallic junction boxes and all required accessories including masonary work for light, fan and separate plug point with supply and fixing of suitable size Metallic deep box including all labour charges etc., complete including masonary work, including cost and conveyance of all material, all labour charges, and contractor profit etc., complete but excluding VAT.
Wiring with run of 2 of 14/0.3mm (1.0 Sq.mm) FR / FRLS PVC insulated flexible ISI mark copper cable ( 100V grade as perIS:694/1990 ) of KEI / Polycab / Havells / GM / Million / HPL / Gold Medal / Power Flex / RPG / Anchor / Great White / Sun Cab / Fortune Art make in existing pipe with 6A 1 Way flush type Swich of makes GM G Home / Gold Medal Olive / Million Zoom / Anchor Penta Cherry / Great white Omega, Ceiling rose 3 Plate of makes Anchor / Gold Medal Olive / Million Zoom. and Supply of Decolam Board of Size 8" x 10" as switch control box including cost and conveyance of all material and all labour charges but excluding VAT etc., complete for light, bell, fan and exhaust fan points including cost and conveyance of all material and labour charges but excluding VAT.
Supply and Fixing of 16A 3pin and 6A 3pin plug socket with indicator lamp and 16A fuse unit and 16A switch control (5 in 1) duly recessed in wall with wooden deep box of 6" x8" x2 1/2" size covered with hylam sheet including earth connections and all labour charges etc., complete.
Supply and run of 2 of 36/0.3mm (2.5 Sq.mm) and 1 of 22/0.3mm (1.5 Sqmm) F.R.L.S P.V.C. insulated flexible copper cable of Makes : Finolex / RR kabel / Havells in existing pipe for mains inlcuding all labour charges etc., complete.
Supply and Run of 2 of 2.5 Sqmm WPSC (Weather Proof Single Core) ISI Alluminium Wire of makes Finolex / GM / Million / V-Guard / Payal / Nakoda / Gold Medal / HPL / RPG along with No.10 SWG G.I bearer wire through PVC cleats with all accessories including labour charges etc., complete for service mains including cost and conveyance of all material and labour chages but excluding VAT..
Supply and fixing of 6A ISI mark Flush type switch of makes GM G Home / Gold Medal Olive / Million Zoom / Anchor Penta Cherry / Great white Omega with 6A 3/2 pin flush type plug socket of GM G Home / Gold Medal Olive / Million Zoom / Anchor Penta, Cherry / Great white Omega make on a common switch board with earth connections in surface / consealed wiring including cost and conveyance of all material and labour charges but excluding VAT.
Supply and Transportation of 1x40W patty type tube light luminaire with copper choke, starter etc., including 1No 40W tube etc., complete.
Providing independent earthling by excavating a trench to a depth of 2.25 M in all soils, as per size specified in the Data, using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with necessary accessories with hume pipe ring duly providing staggered holes including filling with equal proportion of Salt and Charcoal in layers and all labour charges etc., complete for small quarters including cost & conveyance of all material, all labour charges, and all taxes etc., complete for small quarters but excluding VAT.
Supply and fixing 4 Way SPN DB with IP 20 Protection as per IS:13032 and suitable for 4Nos S.P out goings and for 1 No Incommer etc complete of makes Legrand / Schneider. with IP-20 protection suitable for single phase 40A DP Isolator of make Legrand / Schneider. as incomer and 6-32A 10KA TP MCB, C/D Curve ISI Mark of make Legrand / Schneider as out going including internal connection and labour charges for surface / flush mounting etc., complete. including cost and conveyance of all material, all labour charges, and contractor profit etc., complete but excluding VAT.
Supply, Transportation and Fixing of 1200mm (48") Sweep ISI mark Ceiling Fan as per IS 374 - 1979 and, with double ball bearings but without Regulator of makes Crompton / Bajaj Kassels 50 / Usha atom make with all standard accessories but without regulator including all labour charges etc., complete including cost and conveyance of all material and labour charges but excluding VAT.
Supply, Transportation and Fixing of 9" (225mm), Light duty exhaust fan with double ball bearing and wire guard etc complete of makes Crompton / Bajaj Bahar WG / Havells Ventil Air-DS / Orient hill air. Make exhaust / Fresh Air fan with metallic body and blades including making hole in wall and masonary work and all labour charges etc. including cost and conveyance of all material and labour charges but excluding VAT.
Supply and fixing of Anchor / Gold Medal Olive / Million Zoom make ISI mark batten holder / slanting holder in lieu of ceiling rose of light point complete with all connections and all labour charges with 9.0W LED Lamp (for new installation ) including cost and conveyance of all material and labour charges but excluding VAT.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Nit 49 SBD.doc
TENDER_DOCUMENT • 0.60 MB
Nit No 49 BOQItemswb.xls
TENDER_DOCUMENT • 0.29 MB
Schedules-Archaka Quarters.xlsx
TENDER_DOCUMENT • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .