| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.4 LAccepted-AOC JAWAHAR ROAD NEAR HANUMAN MANDIR PO CHITARPUR PS RAJRAPPA DIST RAMGARH 825101 | CHITARPUR | RAMGARH | JHARKHAND | 825101 | ₹3.4 L | L1 | Accepted-AOC L1 accepted bidder |
| 2 | L2₹3.6 L+₹16,328.88 (4.81%)Rejected-Finance C 81 JP MARKET DHURWA RANCHI JHARKHAND 834002 | RANCHI | RANCHI | JHARKHAND | 834002 | ₹3.6 L+₹16,328.88 (4.81%) | L2 | Rejected-Finance Not being L1 |
| 3 | L3₹3.7 L+₹26,676.82 (7.86%)Rejected-Finance | ₹3.7 L+₹26,676.82 (7.86%) | L3 | Rejected-Finance Not being L1 |
| 4 | L4₹3.8 L+₹41,534.20 (12.2%)Rejected-Finance | ₹3.8 L+₹41,534.20 (12.2%) | L4 | Rejected-Finance Not being L1 |
| 5 | L5₹3.9 L+₹47,135.38 (13.9%)Rejected-Finance RATU RD PISKA MORE LAXMI NAGAR DISTT RANCHI JHARKHAND 834 005 | RANCHI | RANCHI | JHARKHAND | 834005 | ₹3.9 L+₹47,135.38 (13.9%) | L5 | Rejected-Finance Not being L1 |
Tender Value
₹5.6 L
EMD Value
₹7,100
Closing Date
3 Jun 2026, 5:00 pmClosed
General Manager (Civil)/WnS , CCL, Ranchi
Office of GM(Civil)/WnS, CCL , Ranchi- 834029
Extension of Gandhi Nagar Colony Substation boundary wall for installation of New transformers, VCBs and ACBs at GNC, CCL, Ranchi
2026_CCL_360080_1
CCL/GM(WnS)/NIT/26-27/861-70 dated 22.05.2026
Open Tender
Civil Works - Others
Percentage
28 days
Gandhi Nagar Colony CCL
As per NIT
3 documents required · 3 mandatory
₹7,100
18 Sept 2026
22 May 2026
5 Jun 2026
22 May 2026
3 Jun 2026
23 May 2026
22 May 2026 - 27 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar (ReferCCL SOR 2025- 15.7.4) | 15.25 | cum | 1,541.1 | ₹23,501.77 |
| 1.02 | Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of : G.S. Sheet. (ReferCCL SOR 2025-15.28.1) | 19.65 | cum | 124.25 | ₹2,441.51 |
| 1.03 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. (CCL SOR 2025 2.8.1) | 23.26 | cum | 207.3 | ₹4,821.8 |
| 1.04 | Supplying and filling in plinth with Jamuna sand under floors, including watering, ramming, consolidating and dressing complete. (CCL SOR 2.27) | 9.76 | cum | 1,473.6 | ₹14,382.34 |
| 1.05 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand 4 graded stone aggregate 20 mm nominal size derived from natural sources) (CCL SOR 4.1.3) | 8.36 | Cum | 7,795.5 | ₹65,170.38 |
| 1.06 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 5 in foundation and plinth in: Cement mortar 1:6 (1cement : 6coarse sand) (ReferCCL SOR 2025- 6.1.2 DR) | 4.72 | Cum | 7,152.15 | ₹33,758.15 |
| 1.07 | Brick work with clay flyash F.P.S. (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor five level in : Cement mortar 1:6 (1 cement: 6 coarse sand) (CCL SOR 6.32.2) | 19.35 | cum | 7,031.05 | ₹1,36,050.82 |
| 1.08 | 12 mm cement plaster of mix : 1:6 (1cement: 6fine sand) (CCL SOR 13.1.2) | 54.57 | sqm | 267.85 | ₹14,616.57 |
| 1.09 | Finishing walls with water proofing cement paint of required shade : New work (one or more coats @ 2.20 kg/10 sqm) complete ((CCL SOR 13.44.1 ) | 125.37 | sqm | 92.5 | ₹11,596.73 |
| 1.1 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. (CCL SOR 10.01) | 378.9 | Kg | 110.65 | ₹41,925.28 |
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.85 MB
BOQ_372949.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .