| 1 | L1₹75.2 LAccepted-AOC AT SAMALEI VIHAR PANCHGACHHIA PO BARAIPAH | ₹75.2 L | L1 | Accepted-AOC AWARDED BEING L1 |
| 2 | L2₹76.8 LRejected-Finance ANGUL ODISHA 759132 INDIA UDYAM OD 01 0005071 | ANUGUL | ODISHA | 759132 | ₹76.8 L | L2 | Rejected-Finance REJECTED NOT BEING L-1 |
| 3 | L3₹76.9 LRejected-Finance AT SUSUDA PO ANKULA DIST ANGUL ODISHA 759132 | ANUGUL | ODISHA | 759132 | ₹76.9 L | L3 | Rejected-Finance REJECTED NOT BEING L-1 |
| 4 | L4₹86.7 LRejected-Finance AT BIDYUT COLONY P O VIKRAMPUR FCI TALCHER DIST ANGUL PIN 759116 | ANUGUL | ODISHA | 759116 | ₹86.7 L | L4 | Rejected-Finance REJECTED NOT BEING L-1 |
| 5 | L5₹90.2 LRejected-Finance AT SHARMA CHHAK PO TALCHER ANGUL ODISHA DIST ANGUL ODISHA 759100 | ANUGUL | ODISHA | 759100 | ₹90.2 L | L5 | Rejected-Finance REJECTED NOT BEING L-1 |
Tender Value
₹1.5 Cr
EMD Value
₹1.8 L
Closing Date
6 Jan 2026, 5:00 pmClosed
STAFF OFFICER CIVIL BHARATPUR AREA
STAFF OFFICER CIVIL BHARATPUR AREA N.S.NAGAR ANGUL ODISHA-759148
Repair and Renovation of Existing Drain as per requirement on patch basis and Stone Boulder pitching along Kuccha drain at N.S Nagar Colony under BA
2025_MCL_349752_1
GM(BA)/SO(C)/e Tender/2025-26/804 Dt.20.12.2025
Open Tender
Civil Works - Others
150 days
BHARATPUR AREA
AS PER NIT
5 documents required · 5 mandatory
₹1.8 L
12 Mar 2026
22 Dec 2025
8 Jan 2026
22 Dec 2025
6 Jan 2026
22 Dec 2025
22 Dec 2025 - 30 Dec 2025
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil.
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar
Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete.
Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth 1:3:6 (1 Cement : 3 coarse sand (zone-Ill) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3(1 cement: 1.5 coarse sand (zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more.
Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
Brick work with Fly Ash Brick (230x115x75 mm size) bricks of class designation 10 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand)
12 mm cement plaster of mix: 1:6(1 cement: 6 fine sand)
Neat cement punning.
Total impact of GST plus Labour Cess [@ 1 % (BOCW Cess to be deducted from the RA bill as per the value of the work progress)] for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.06 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.30 MB
Tendernotice_2.pdf
PDF • 1.36 MB
BOQ_362509.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid