| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹77.1 LAccepted-AOC 401 402 AMIT CRYSTAL ABOVE BANK OF BARODA SENAPATI BAPAT ROAD PUNE 411016 SHIVAJI NAGAR PUNE MAHARASHTRA 411016 | PUNE | MAHARASHTRA | 411016 | L1 | Accepted-AOC L1 | |
| 2 | L2₹94.3 L+₹1.3 L (1.35%)Rejected-Finance | L2 | Rejected-Finance L2 |
Tender Value
Refer Docs
EMD Value
₹1.2 L
Closing Date
7 Jun 2022, 5:30 pmClosed
Director COEP
College of Engineering Pune
INVITING Re QUOTATIONS for Waterproofing works for the Center of Excellences Building Complex at Chikhali Campus COEP
2022_DTEDM_795933_3
COEP/PEC/2022-23/27
Open Tender
Civil Works - Buildings
Item Wise
60 days
Chikhali Campus, PCMC
As per Tender Document
2 documents required · 2 mandatory
₹12,000
₹1.2 L
27 Jan 2023
2 Jun 2022
8 Jun 2022
2 Jun 2022
7 Jun 2022
2 Jun 2022
2 Jun 2022 - 7 Jun 2022
NOTES (to be carefully read and considered before filling in the rates) All items mentioned below are inclusive but not limited to providing and supplying material, labour with toold, tackles and plant and machinery (if required) for preparation of the surface, laying, fabricating, placing it in position, fixing, finishing and protecting the surface prior to the next step of the works including all leads and lifts etc. complete. Below mentioned items are "generic" in nature and should be considered as a guideline for this specialized works. This is being specifically mentioned because each manufacturer will have a different methodology of working and application process. In the Technical Bid, the bidder should attach a separate sheet which explains the below items of works in details with the proposed specifications, methodology as well as the application process in complete considering the variety in products. It is assumed and all bidders should strictly visit the site and get the now-how of the site conditions before quoting the item rates.
Surface preparation: Inspect the surface available at site, prepare the surface as per the guidance and directions of the manufacturer for the required surface of application.
RAFT/ footing and ALLIED AREAS - Supplying and installing of minimum 1.2 mm thick pre-applied HDPE membrane having puncture resistance of minimum 800N as per ASTM E 154, tensile strength of minimum 21 Mpa, and hydrostatic head resistance not less than 70 m water head as per ASTM D 5385 and elongation of minimum 500% as per ASTM D 412, peel adhesion to concrete of minimum 1200 N/m as per ASTM D 903, Lap peel adhesion > 450N/m as per ASTM D1876. The pre-applied, fully bonded HDPE sheetmembrane shall be loosely laid on PCC and gets bonded to the underneath of the poured concrete of base/ raft slab and confined retaining wall. incuding application for embeded anchore bar at footing whereever applicable
RETAINING WALL: Treatment of all concrete defects Opening the joints/cracks such as cold joints, tie-rod holes, construction joints, cracks, corner joints and areas around honeycomb in the RCC by forming appropriately shaped groove and thereafter providing and sealing with polymer modified mortar complete as per manufacturer’s instructions. Membrane: Providing and laying of minimum 1.5 mm thick self-adhesive, cold applied waterproofing membrane comprising of a self-adhesive rubberized asphalt with cross laminated HDPE film topped with solar reflective film, SmartCare Self Adhesive SBS Membrane with HDPE lining or approved equivalent, confirming to the requirements of DIN EN 1849-1 for thickness with a puncture resistance of >220 N/cm as per ASTM D5147, puncture resistance of 200N as per ASTM E 154, providing ancillary products and finish complete including cleaning the surface, priming the surface with cold applied bituminous primer. The membrane should be sealed properly at joints and maintaining minimum 150 mm overlap between the membrane selvedge and minimum 200 mm overlap on the end joints s of the membrane over the surface, Including scaffolding etc., complete as per manufacturers specification.
Providing and laying high density polyethylene (HDPE) dimpled protection and drainage sheet; over the waterproofing membrane on the retaining walls. The protection and drainage sheet shall consist of dimpled HDPE sheet with fused on hydrophilic polypropylene geotextile; confirming to EN 13252, etc. complete as per manufacturer specifications.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .