Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 LAccepted-AOC 01 NAUJARPUR BASAI KAJI SASNI HATHRAS UTTAR PRADESH 202150 | ALIGARH | UTTAR PRADESH | 202150 | L1 | Accepted-AOC Accept | |
| 2 | L2₹2.6 L+₹20,210 (8.35%)Rejected-AOC 1 BAMANAI LUHETA HATHRAS HATHRAS UTTAR PRADESH 204101 | HATHRAS | UTTAR PRADESH | 204101 | L2 | Rejected-AOC Accept | |
| 3 | L3₹2.7 L+₹27,233 (11.2%)Rejected-AOC | L3 | Rejected-AOC Accept |
Tender Value
₹3 L
EMD Value
₹2,000
Closing Date
14 Oct 2020, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC Hathras
SE EDC Hathras
Work
2020_DVVNL_518615_1
EDCH-64/2020-21
Open Tender
Electrical Works
Item Rate
120 days
SE EDC Hathras
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
DVVNL
₹2,000
18 Dec 2020
9 Oct 2020
14 Oct 2020
9 Oct 2020
14 Oct 2020
9 Oct 2020
30 days
Amount
Carriage of following from 132 KV Hathras store center to 33/11 KV Substations through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50 Kms.)
8.5 Mtr. long PCC Poles.
9/11 Mtr. S.T. Poles
11 KV Piler Proof Metering Cubical
11 KV Pole Mounted Metering Units CTR 15/5Amp
11 KV XLPE Cable
11 KV X-Arms, weasal conductor, G.I wire,Disc Insulators, Pin insulators, clamps Abc Bunch and other required line material, if any.
Carriage of following from 132 KV Store center Hathras to 33/11 KV Substations through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.)
25 KVA T/F
Erection of following Poles including Cutting of kharanja/mettalic road/concrete portion while digging pit & complete H.T./L.T. fittings as per RESPO manual and as per direction of Engineer Incharge including the cost of labour, T&P and carrier etc. required for proper completion of work.
8.5 Mtr. long PCC Poles.
STP (SP-33) 9.0/11 Mtr.
Double pole complet fitting
Stud Pole
Erection and grouting of stays as per RESPO manual and as per direction of supervising engineer. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost.
Fixing of earthing rod as per RESPO manual and as per direction of supervising engineer.
Fixing of following accessories.
11 KV Disc Insulator with fitting.
11 KV Pin with insulator
11 KV X-Arm
F Clamp
Dropper Channal/Top Channel
11 KV Jointing Kit
LT Distribution Box
11 KV Piler Proof Metering Cubical
11 KV Pole Mounted Metering Units CTR 15/5Amp
GI Pipe 6'' Dia
11 KV TPMO
Providing & Fixing Danger Board
Laying, sagging and stringing and jumpering / binding etc. of new & old ACSR Weasal conductor / GI in 11 KV / LT lines as per RESPO manual and as per direction of supervising engineer.
ACSR Weasal conductor
AB Cable
11 KV XLPE Cable
ACSR Dog conductor
Cutting, chopping, triming of tree branches to clear the line route to give 2 mtr. horizontal and vertical clearance to the line coming in the route of different feeders as per direction of supervising engineer
Installation of following T/F on newly constructed double pole in proper alignment direction & making HT/LT connection.
25 KVA T/F
Construction of Round Pole Plinth
Re Guarding / Guarding of 11 KV line by laying, stringing, sagging and binding of 2 Nos. parallel GI wire 6 SWG after providing, fabrication and fixing of guarding angle and fabrication and fixing of X-guards (Tillis) of GI wire at distance of 3 Mtr.
Grouting of Pole (wherever required) with cement, sand and brick ballast/stone ballast in ration 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. As per actual site requirement.
Installation of extra ''T'' on the erected poles wherever required alongwith all fitting as per direction of supervising engineer including the cost of labour, T&P etc, required for proper completion of work. The "T" pole shall be grouted with cement, sand and brick ballast/stone ballast in ratio 1:4:8 including the cost of material.
Bobby Electricals
SHRI BANKEY BIHARI ELECTRICALS
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .