PUBLIC e bid in two bids system are invited for PIPELINE LAYING JOB AT HPCL BARAUNI IRD as per
2300011171-HD-07120
5100011171
Open Tender
Beed, Maharashtra
₹0
₹10 L
5 Apr 2024
13 Mar 2024
5 Apr 2024
5 Apr 2024
13 Mar 2024 - 25 Mar 2024
| Item No | Item Title | Description | Qty | Unit |
|---|---|---|---|---|
| 1 | LAYING OF PIPELINE | LAYING OF PIPELINE — L WORK FOR LAYING OF 14 INCH DIAMETER CARBONSTEEL PIPELINE (API 5L GRADE X 56 TO X 65 ERW 6.4TO 9.5 MM WT, EXTERNALLY COATED WIT 3 LPE/LPP)IN UNDERGROUND CONDITION WITH CLEAR COVER OF 1.2METER TO 1.5 METER IN ALL TYPE OF SOIL, THROUGHUNDERGROUND CASING PI , THROUGH PIPE CULVERT INNON ROU SECTION. DETAIL OF JOB AS PER SOQ ITEMDETAIL AND TENDER SPECIFICATION. | - | Running Meter |
| 2 | INSTALLATION OF PIPE | INSTALLATION OF PIPE — PER DETAILED SCOPE OF JOB ATTACHED. | - | meter |
| 3 | CASED XING BORING+CASING 1712-BARAUNI POL IRD | CASED XING BORING+CASING 1712-BARAUNI POL IRD — SED CROSSING (BY JACKING / BORING / OPEN CUT)CASED CROSSING INCLUDING INSTALLAITON OF CASEDPIPE AND INCLUDING SUPPLY , INSTALLAT N &TRANSPORTATION OF CASING PIPE FOR MAINLINE AND CSCONDUIT FOR OFC FROM CONTRACTOR'S STORAGE POINTTO WORKSITE. INSTALLATION O CASING PIPE BYJACKING/ BORING OR OPEN CUT FOR RAIL, ROAD ORCANAL CROSSINGS WHEREVER REQUIRED IN ALL TYPES OFSOILS AND TERRAIN D ALL OTHER MATERIALS VIZ.CASING INSULATORS AND CASING END SEALS AS PERENCLOSED DRAWING, , MATERIALS FOR CASING VENTSAND DRAIN ETC. INCLUDING SUPPLY OF ALL OTHERMATERIALS, EQUIPMENTS, CONSUMABLES, MANPOWER,WELDING INCLUDING VISUAL INSPECTION OF ALL WELD OINTS, INSTALLATION OF CASING INSULATORS, ENDSEALS, VENTS AND DRAIN-OFF PIPES, BACKFILLING ANDRESTORATION AS ORIGINAL OF THE FAC ITY CROSSEDAND PERFORMING ALL WORKS AS PER DRAWINGS,SPECIFICATIONS AND INSTRUCTIONS OFENGINEER-IN-CHARGE AND PROVISIONS OF CON ACTDOCUMENT. INSTALLATION OF 2 NOS OF 6" CS CONDUITBY BORING & JACKING INCLUDING SUPPLY OF CASINGPIPE AND ITS COATING FOR HDP DUCT OFC(RAILWAYS), 6" API 5LGRB/ IS : 3589 WALLTHICKNESS 6.4 MM | - | meter |
| 4 | WARNING SIGN WITH | WARNING SIGN WITH — RNING SIGN, WARNING PIPELINE MARKER: WARNINGSIGN WITH POST AND FOUNDATIONS AS PER DRAWING. ITSHALL BE POWDER COATED ONLY AND BEF E INSTALLINGTAKE APPROVAL FROM THE ENGINEER-IN-CHARGE. DETAILSPECIFICATION AS GIVEN IN TENDER DOCUMENT. | - | Each |
| 5 | SPLY AND INSTLN OF ROU | SPLY AND INSTLN OF ROU — PPLY AND INSTALLATION OF PIPELINE ROU BOUNDARYMARKER AS PER STANDARD AND SPECIFICATION. | - | Each |
| 6 | PM:DIRECTION MARKERS | PM:DIRECTION MARKERS — RMANENT MARKERS SUPPLY, FABRICATION ANDINSTALLATION OF FOLLOWING TYPES OF PERMANENTMARKERS ALONG THE ROUTE INCLUDING ALL ASSOCIA DCIVIL WORKS SUCH AS EXCAVATION IN ALL TYPES OFSOIL, CONSTRUCTION OF PEDESTALS AND GROUTING WITHCONCRETE, CLEARING, SU | - | Each |
| 7 | SPLY,APPLY & WRAPPING | SPLY,APPLY & WRAPPING — PPLY AND APPLICATION OF PRIMER AND COATING ANDWRAPPING, OF THE PIPELINES TO BE LAID UNDERGROUNDWITH PRIMER AND COATING MATERIALS UPPLIED BYCONTRACTOR WITH MANUFACTURER SPECIFIED HANDWRAPPING MACHINE. QUOTED RATES SHALL INCLUDESURFACE PREPARATION TO SA 2 ? SUPPLY ANDAPPLICATION OF CHLORINATED RUBBER SYNTHETICPLASTICIZER OLVENT BASE PRIMER WITH DENSITY OF 0.9 TO 0. 95 G/CC; SUPPLY D APPLICATION OFPIPEKOTE TAPE CONFIRMING TO IS: 10221 ANDAWWA-C-203 WITH APPLICATION BY WIDE MOUTHED TORCHHEATING; OVERLAPS S LL BE MIN. 10-12 MILLIMETREAND TAPE WIDTH SHALL BE 200 TO 300 MILLIMETRE ANDTHICKNESS OF TAPE 4 MILLIMETRE(MIN). VENDORSHOULD RICTLY FOLLOW MANUFACTURER'S APPLICATIONPROCEDURE. RATE TO INCLUDE THE EXECUTION OF THEJOB AS PER LATEST CODAL PROVISIONS, ATTAC DTECHNICAL SPECIFICATIONS AND AS DIRECTED BY EIC.AFTER APPLICATION AND BEFORE BACKFILLING OFTRENCHES, HOLIDAY TESTING OF THE C TED PIPES TOBE CARRIED OUT AND IF REQUIRED RECTIFICATIONSHALL BE DONE. THE CONTRACTOR SHALL ARRANGE FORHOLIDAY TESTING EQUIPME S. QUOTED RATES AREDEEMED TO INCLUDE TESTING OF MATERIALS ASREQUIRED. | - | square meter |
| 8 | WLDG - PL | WLDG - PL — LDING OF STAINLESS STEEL PIPELINE JOINT:WELDING OF HPCL SUPPLIED STAINLESS STEEL PIPE ONINCH-DIA BASIS. TAKING OVER HPCL SUPPLIE FREEISSUE MATERIAL NAMELY, PIPE, ELBOW, TEE, REDUCER,FLANGE AND ANY OTHER FITTINGS, CUTTING,FABRICATION, EDGE PREPARATION FOR E PIPE,FITTING AND FLANGE INCLUDING BEVELLING ANDGRINDING, ALIGNING WITH CLEATS/TACKS, FIT-UP,WELDING WITH REQUIRED RUNS GRIND G AFTER EACHRUN. ROOT RUN SHALL BE WITH E-6010 ELECTRODE ANDINTERMEDIATE AND FINISH RUNS SHALL BE WITH E- 6013ELECTRODE. | - | Inch Dia |
| 9 | MODIFICATION OF PIPING | MODIFICATION OF PIPING — PING MODIFICATION INCLUDING FLUSHING, CUTTING(COLD OR HOT), DISMANTLING OF EXISTING PIPELINES,EDGE PREPARATION OF PIPES, WELDING RE-LAYING INDESIRED ALIGNMENT, HYDRO-TESTING, SAND BLASTING,PAINTING ETC., COMPLETE AND AS DIRECTED BY EIC.JOB ALSO INCLUDES F AL HOOKING UP OF THEPIPELINES TO THE EXISTING DELIVERY/ RECEIPTLINES. JOB TO INCLUDE SHUT DOWN ACTIVITIES LIKEDRAINING OF PROD T TO DRUM FROM SECTION OFPIPELINES, DROPPING / INSTALLATION OF VALVES/FLANGES/ SPOOL PIECE ETC. PARTY TO MAKEARRANGEMENT FOR S RING THE PRODUCT ANDTRANSPORTING THE SAME TO UG TANKS OR AS DIRECTEDAT SITE. THIS WILL BE TIME BOUND ACTIVITIES ANDMAY BE CARR D OUT AFTER NORMAL OPERATION HOURS.THE JOB ALSO INCLUDES FABRICATION OF PIPE LINESAND CONNECTIONS TO EXISTING DELIVERY/ RECEIPT INES, DISMANTLING OF VALVES AND REINSTALLATIONAS PER JOB REQUIREMENT. JOB INCLUDES HOOKING UPWITH THE MAIN LINE ON BOTH SIDES O THECROSSING/ABOVE GROUND LINE INCLUDING CUTTING,BEVELING, GRINDING, ALIGNING, FIT-UP, TIE-INWELDING, RADIOGRAPHY, CARRYING OUT EPAIR IF ANY, JOINT COATING WITH APPROVED COATING MATERIALAND PROCEDURE, HYDRO-TESTING OF ENTIRE SECTION TOA PRESSURE OF 16.5 /CM2 AS SPECIFIED IN THETECHNICAL SPECIFICATIONS. ANY LEAKS DETECTEDDURING HYDROSTATIC TESTING SHALL BE RECTIFIED ATNO EXTRA C T AS PER APPROVED PROCEDURE. THE JOBINCLUDES SEEKING VARIOUS PERMISSIONS/PERMITS FROMPROJECT/OPERATING AUTHORITIES OF HPCL AND ECUTING THE JOBS ON SHUT DOWN BASIS, SHIFTINGTHE DISMANTLED MATERIAL TO THE STORE OF HPCL ASDIRECTED COMPLETE . THE SAFETY IS OF TMOSTIMPORTANT FOR THESE JOBS AS THESE ARE BASICALLYOPERATING FACILITIES AND VARIOUS PRE DISMANTLINGACTIVITIES LIKE ISOLATION, LUSHING, DISABLING OFLIVE STATUS OF VARIOUS FACILITIES IS MANDATORYBEFORE COMMENCEMENT OF THE JOB. THE EXECUTION OFTHE JOB AS R LATEST CODAL PROVISIONS/ SOUNDENGINEERING PRACTICES AND AS DIRECTED BY EIC. | - | Lump Sum |
| 10 | LEAKS/ BURSTS | LEAKS/ BURSTS — AKS/ BURSTS (ATTRIBUTABLE TO OWNER): ALL WORKSFOR LEAK/BURST (OCCURRING DURING HYDROSTATICTESTING) INCLUDING NECESSARY REPAIR/RE ACEMENTOF DEFECTIVE PIPE LENGTH, INCLUDING CUTTING ANDREMOVING OUT DEFECTIVE PIPES, WELDING, NDT OFWELDS, REPAIR AND R | - | Inch Meter |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
2300011171-HD-07120.pdf
TENDER_DOCUMENT • 24.68 MB
Download all tender documents and submit your bid