Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 LAccepted-AOC | ₹4.8 L | L1 | Accepted-AOC As per LOA |
| 2 | L2₹5.0 L+₹28,981.46 (6.10%)Rejected-Finance NIL | ₹5.0 L+₹28,981.46 (6.10%) | L2 | Rejected-Finance L2 Agency |
Tender Value
₹4.9 L
EMD Value
₹11,680
Closing Date
26 Mar 2026, 5:00 pmClosed
Raj Kumar
Municipal Committee Nilokheri
Construction of Street with Laying of Storm Water Pipeline from H/o Vipin Mehta to Vishnu Bakhshi Via Rattan Lal in Ward No. 12, M.C. Nilokheri.
2026_HRY_508929_1
2026892EC778 5338 471A 9731 A25C7E4790FD311ULB
Open Tender
Civil Works
Works
90 days
Nilokheri
2 documents required · 2 mandatory
₹1,000
₹11,680
Yes
12 Jun 2026
18 Mar 2026
27 Mar 2026
18 Mar 2026
26 Mar 2026
18 Mar 2026
[10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate]
[13.29.2]Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 2. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works [Through Rate]
[22.218.1]Providing and Supplying of class SN 8 structured wall Polyethylene Piping system (Pipe with online/ offline coupler and elastomeric sealing ring) with non smooth external annular corrugated and smooth internal surface (double wall) for non-pressure underground sewerage and drainage application as confirm to IS 16098 (part II):2013 including transportation, frieght charges, inspection charges, loading, unloading, complete as specified and directed by Engineer In-Charge. 1. 250 mm Internal Diameter [Through Rate]
[22.219.1]Lowering, Laying and jointing of class SN 8 structured wall (External Annular Corrugated and Smooth Internal Surface Polyethylene Piping and fitting with the help of coupler(online/ offline) attached with one end of pipes, sliding over the elastomeric sealing rubber ring placed on the specified valley of the corrugation at the spigot end, lowering the same into the trench, laying on the lower bedding (constructed at bottom of trenches) at prescribed gradient, depth and alignment, testing the water tightness of the joints, ensuring the continuity tests of specified pipe segment etc. complete as per drawing, specification and detailed engineering, including cartage of pipes and fitting etc. as per direction of Engineer-in-charge. 1. 1250 mm Internal Diameter [Through Rate]
[3.1.1]By Mechanical Transport including loading, unloading and stacking 1. Lime, moorum, building rubbish [3km]
[3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [3km]
[4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate]
[5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate]
[6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.39.1]Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete. 1. 1:1½:3 (1 Cement: 1½ coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate]
[6.43]Providing, hoisting and fixing above plinth level up to floor four level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate]
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.73 MB
BOQ_587703.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .