| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹29.5 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹31.6 L+₹2.1 L (7.00%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹33.8 L+₹4.2 L (14.3%)Admitted-Finance 1853 2ND FLOOR BHAGIRATH PALACE SURYA BAZAR CHANDI CHOWK NORTH DELHI DELHI 110006 | NORTH | DELHI | 110006 | L3 | Admitted-Finance |
Tender Value
₹45.2 L
EMD Value
₹90,326
Closing Date
12 May 2026, 11:00 amClosed
Executive Engineer (Elect.)
Executive Engineer (E),PWD NES/M-251, LM Bund Road, Ramesh Park, Delhi
(Sub Head- Providing day to day Street light and Sub Station Maintenance at Signature Bridge, Wazirabad Delhi.)
2026_PWD_290835_1
13/EE(E)/PWD NES ED/2026-27
Open Tender
Electrical Works
Percentage
365 days
M-2511
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹90,326
Yes
13 May 2026
5 May 2026
12 May 2026
5 May 2026
12 May 2026
5 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Sub Head-I (Opt. & Maint) | |||||
| 2 | Operation & Maintenance of Substation, DG Set, transformer, HT/LT panel set, APFC Panel round the clock on all the days i/c Sundays & holidays. The job also includes recording of all parameters like HT & LT voltages, current, power factor etc. & routing periodical checking & testing as per terms and conditions.
1). Wireman– 3 Nos. (Round the Clock) (6 AM to 2 PM, 2 PM to 10 PM, 10 PM to 6 AM)
2). Khallasi – 1 Nos. (In General Shift) (9 AM to 5 PM) | - | Months | 0.29 | - |
| 3Providing of Wireman and Khallasi for day to day attending complain of Street lights, High Mast, Security lights, Flyover lights, feeder pillars, cables, all other relevant equipment T & P as required for smooth, healthy & proper illumination on Signature Bridge & attending all type of complaints from PWD portal WIMS, PGMS, LG Listerning, CP Grams & instruct department i/c inspection report of roads submit to concern JE(E) & updating the inventory regularly (including addition/Removal of poles/ High Mast pole fitting / /removal or installation Feeder Pillars) all days including Sunday & Holiday. a) Wireman – 1 Nos. (As per direction of Engineer-in-Charge) b) Khallasi – 1 Nos. (As per direction of Engineer-in-Charge) | |||||
| 4Hiring of truck mounted tower wagon/sky lifter of capacity not less than 16 mtr approach height for maintenance of street light on signature bridge delhi as per site required including all maintenance driver, POL as reqd as per terms and conditions etc complete as required. | |||||
| 5Sub Head-II (E.I. Works) | |||||
| 6LED Street light fixture, powder coated pressure die cast aluminium body (System lumen efficacy ≥120 <135 lm/Watt) Supplying, installation, Testing & Commissioning of Street light LED fixture powder coated pressure die cast aluminium body with driver as per the requirement with Driver efficiency >85%, Input voltage: 140-270 Volt AC, frequency 50/60 hz, Operating temp range -5 0C to 50 0C, internal surge protection of 5 KV L,N,E as per IEC 61000-4-5, Driver efficiency >85%,THD < 10% as per IEC 61000-3-2, P. F.≥0.95, IP-66,IK-10, CRI >70, under voltage and over voltage protection, EMIEMC As per CISPR 15 , lenses for beam angle as per IESNA type I/II/III as per the width of the road and the project requirement., suitable to fit in up to 65mm dia pipe, life time (LED, Driver & electrical circuitry) of minimum 50000 Burning Hours with 70% of initial Lumen maintained till life ends as per LM80 extrapolation IES TM-21-11 report, CCT 3000°K / 4000°K / 5700°K /6500°K (As per ANSI Bin), SDCM(Standard Deviation Colour Matching) <5, Maximum power consumption should not more than the specified rating and Fixture shall be of relevant BIS standard complete in all respect i/c external connections with 1.5 sq mm FRLS/HFFR, PVC insulated copper conductor single core cable and earthing etc. as required with Minimum 5 year OEM warranty. System lumen efficacy ≥120 <135 lm/Watt output . LM79 & LM80 Test report and all testing required for LED fixtures as per BIS shall be submitted. Shape size and CCT shall be as approved by Engineer-in-Charge as per requirement. (Thermal management: heat sink of aluminium housing such that LED junction temperature shall not rise above 90°C). a)200 watt | |||||
| 7Rewiring for light point/ fan point/ exhaust fan point/call bell point with 1.5 sq.mm FRLS/HFFR PVC insulated copper conductor single core cable and 1.5 sq.mm FRLS/HFFR PVC insulated copper conductor single core cable as earth wire in existing surface/ recessed steel/PVC conduit including dismantling as required. Group C | |||||
| 8Supplying and drawing following sizes of FRLS/HFFR PVC insulated copper conductor, single core cable in the existing surface/ recessed steel/ PVC conduit as required. | |||||
| 8.1 | 3 x 1.5 sq. mm | - | Mtr | - | - |
| 8.2 | 3 x 4 sq. mm | - | Mtr | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.26 MB
BOQ_385916.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .