| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.1 CrAccepted-AOC | ₹9.1 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹9.4 CrRejected-Finance | ₹9.4 Cr | L2 | Rejected-Finance Highest Rates |
| 3 | L3₹10.0 CrRejected-Finance BEHIND WATER WORKS ST NO 4 JAIN NAGRI ROAD ABOHAR | ₹10.0 Cr | L3 | Rejected-Finance Highest Rates |
| 4 | L4₹11.6 CrRejected-Finance | ₹11.6 Cr | L4 | Rejected-Finance Highest Rates |
Tender Value
₹10.9 Cr
EMD Value
₹21.8 L
Closing Date
2 Dec 2020, 5:00 pmClosed
Executive Engineer
SPK Dam and Head Regulator Division No II
Construction of 968.5 mts balance portion of Ravi Canal joining existing Ravi Canal at RD 8300 on J and K Side on Items Rate Basis.
2020_WR_55841_1
01/2020
Open Tender
Civil Works - Canal
365 days
Basantpur righ bank of river Ravi
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹21.8 L
Yes
Committee Room
10 Mar 2021
7 Nov 2020
4 Dec 2020
7 Nov 2020
2 Dec 2020
7 Nov 2020
19 Nov 2020
Amount
Construction of 968.5 mts balance portion of Ravi Canal
Excavation in Soil (any type) using Hydraulic Excavator CK 90 with hydraulic excavator of 0.9 cum bucket capacity including cutting, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, including all lifts and combined lead upto 30m.Earth work carrying to the screening plant/dump at site including dewatering if any.
Rehandling, Screening of the excavated material to get the material having sizes not more than 150mm , loading , transporting & placing the screened material on embankments in the layers not exceeding 250 mm thick in the random fill zone & suitably compacted to achieve minimum relative density of not less than 70% as per instructions of the Engineer . Complete in all respects.
Construction of Dowel on the canal banks including excavation, carriage of good earth including dressing as per drawings , design , Specification & the instructions of the Engineer, complete in all respects
Earthwork excavation of good earth / Imperviuos Material carried to the compaction Zone spreaded in layers of 200mm thick & compacted to 150 mm, watering , rolling & compaction to achieve max. DBD of 98% at optimum moisture content, including compensation of Earth, loading & unloading as per drawings, design, Specification & the instructions of the Engineer, complete in all respects.
Earth work for lip cutting in filling for lining of irrigation Ravi Canal inclusive of all allowances ,lead and dressing with depth exceeding 3 mtr but upto 4.5 meter as per drawings, design, specifications and the instructions of the engineer incharge, complete in all respects.
Cement concrete lining 10cm. thick in bed of Ravi Canal Laid manually, using cement concrete M-20 mixed in an automatic computerized Batching & Mixing Plant and transported to the site in transit mixers in bed including, supply & carriage, loading & unloading of cement, shingle & sand etc as per drawings, design Specification & the instructions of the Engineer, complete in all respects.
Cement concrete Sleepers 225mmx110mm thick of Ravi Canal Laid manually, using cement concrete M-20 mixed in an automatic computerized Batching & Mixing Plant and transported to the site in transit mixers including, supply & carriage, loading & unloading of cement , shingle & sand etc as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Cement concrete lining 10cm. thick in slopes of Ravi Canal Laid manually, using cement concrete M-20 mixed in an automatic computerized Batching & Mixing Plant and transported to the site in transit mixers including , supply & carriage, loading & unloading of cement , shingle & sand etc as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing & Laying 150 mm thick Boulder/Stone Pitching on the Bed & Side slopes of the drains including carriage , loading & unloading of surplus boulders/ stones of required size and weight available after the Rehandling /screening of excavated material of Ravi Canal from the Screening Site to the site of work & grouted with 1:3:6 cement concrete including excavation of drain , supply & carriage, loading & unloading of cement , shingle & sand as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing & Laying Burlap/ Tar Paper to prevent clogging of filter during lining including supply , carriage cutting , wastage etc as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing, Carrying & Laying 150mm thick filter material behind Concrete Lining in two layers of thickness 75mm each in the Bed and side slopes of Ravi Canal including carriage of Finished aggregates from the Quarry to Site of Work etc , as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing, carrying & laying Sand, Graded gravel fill material (RBM)of sizes varies from ± 5 mm to 40mm around the PVC Perforated Pipe in Longitudinal Drain & Pressure Relief Valve in bed & Side Slopes of Ravi Canal l , including carriage of Finished aggregates from the Quarry to Site of Work etc , as per drawings , design , Specification & the instructions of the Engineer, complete in all respects
Providing & fixing in position PVC Perforated Pipe in the Longitudinal Drain & Transverse Drain of the Ravi Canal including Cost of Material, carriage , loading & unloading, tools and wastage as per Design , Drawings , specifications & the instructions of the Engineer, complete in all respects .
Providing & fixing in position PVC Pressure Release Valves along with PVC pipe in the bed & Side Slopes of the Ravi Canal including cost of material ,carriage , loading & unloading, tools and wastage etc as per Design , Drawings , specifications & the instructions of the Engineer, complete in all respects .
Providing & fixing in position ladder of Iron rungs on Lined Slopes as per IS 3873 - 1993 of 25 mm dia. , 2050 mm long MS Bars including bending to the required shape smoothening & painting of the exposed surface with all leads & lifts as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing , carrying & applying primer on top of film on sleepers & Side of panel Confirming to IS Code 3384-1986 (Reaffirmed 2016 ) 250mm mm wide LDPE Film of 150 Microns thickness with all leads & lifts as per drawings , design , Specification & the instructions of the Engineer, complete in all respects.
Providing , carrying & laying gravels and cobbles in Zone 4 of Ravi Canal including carriage of Finished aggregates from the Quarry to Site of Work , Compaction etc , as per drawings , design , Specification & the instructions of the Engineer, complete in all respects..
Construction of a metalled road 3.0 m wide on the inspection bank of Ravi Canal including all leads & lifts for all materials required for the road work strictly following the specification given as under as per direction of the Engineer, Complete as per technical Clause 406 , 502 , 503 , 504 & 508 of MORT& H Specifications respectively , complete in all respects..
Providing & fixing distance marks 200 M apart on the inspection bank of Ravi Canal as per drawings , design , Specification & the instructions of the Engineer, complete in all respects (LS)
Providing & fixing distance marks 1000 M apart on the inspection bank of Ravi Canal as per drawings , design , Specification & the instructions of the Engineer, complete in all respects (LS)
Putting 1:3 ( Cement : Water) slurry with cement @2.25 Kg per Sqm on prepared Bed & Side Slopes before laying concrete on Bed & Side Slopes
Trikuta Builders
M/s Khara Contractors
S B CONSTRCTION COMPANY
stage.html
html • 0.05 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid