| 1 | L1₹9.6 CrAdmitted-Finance AGRC ROAD HIJUGURI P O P S HIJUGURI DIST TINSUKIA ASSAM PIN 786192 | TINSUKIA | ASSAM | 786192 | ₹9.6 Cr | L1 | Admitted-Finance |
| 2 | L2₹9.6 Cr+₹32,017.52 (0.03%)Admitted-Finance | ₹9.6 Cr+₹32,017.52 (0.03%) | L2 | Admitted-Finance |
| 3 | L3₹9.6 Cr+₹4.2 L (0.43%)Admitted-Finance | ₹9.6 Cr+₹4.2 L (0.43%) | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | KAUSHAL SHARMA L1 | M/s AMUN MOTOR PARTS AND ENGINEERING WORKS L2 | MAITUNG TIKHKA L3 |
|---|---|---|---|---|---|---|
| 1.00(SH:EARTH WORK/WIDENING) | ||||||
| 1.01 | Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) | 13,556.62 | Cum | 300 ₹40,66,986 Lowest | 305 ₹41,34,769.1 | 310 ₹42,02,552.2 |
| 1.02 | Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres ) | 9,037.75 | Cum | 373 ₹33,71,080.75 Lowest | 375 ₹33,89,156.25 | 375 ₹33,89,156.25 |
| 2.00(SH: 3MTR HT.RRM/RETAINING WALL) | ||||||
| 2.01 | Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.)
(I) Ordinary Soil
(A) Manual Means
(i)Upto 3m depth(without de-watering) | 112.5 | Cum | 300 ₹33,750 Lowest | 305 ₹34,312.5 | 310 ₹34,875 |
| 2.02 | PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) | 10.46 | Cum | 8,143 ₹85,175.78 Lowest | 8,150 ₹85,249 | 8,160 ₹85,353.6 |
| 2.03 | Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification.
b) Random Rubble Masonry | 147.93 | Cum | 6,550 ₹9,68,941.5 | 6,500 ₹9,61,545 Lowest | 6,510 ₹9,63,024.3 |
| 2.04 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
Granular material | 12.75 | Cum | 1,620 ₹20,655 Lowest | 1,650 ₹21,037.5 | 1,660 ₹21,165 |
| 2.05 | 12mm Cement Plaster 1:4 ( 1 cement :4 fine sand | 28.59 | Sqm | 217 ₹6,204.03 Lowest | 220 ₹6,289.8 | 225 ₹6,432.75 |
| 2.06 | Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications | 44.12 | Each | 242 ₹10,677.04 Lowest | 250 ₹11,030 | 250 ₹11,030 |
Tender Value
₹9.6 Cr
EMD Value
₹9.6 L
Closing Date
20 Jan 2025, 11:00 amClosed
EE Changlang Division PWD
Office of the EE Changlang Division PWD
C/o Road from Changlang Town to Kuchep Village-II in Changlang Dist (Ph-I).
2024_PWDAP_2037_1
CHD/P-10/2024-25/1462
Open Tender
Civil Works – Roads
Item Rate
730 days
Changlang
Please refer Tender documents.
4 documents required · 4 mandatory
₹5,000
EE PWD Changlang Division
₹9.6 L
O/o the Executive Engineer, Changlang Division,PWD
27 Jan 2025
30 Dec 2024
20 Jan 2025
30 Dec 2024
20 Jan 2025
30 Dec 2024
10 Jan 2025
Amount
(SH:EARTH WORK/WIDENING)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres )
(SH: 3MTR HT.RRM/RETAINING WALL)
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) (I) Ordinary Soil (A) Manual Means (i)Upto 3m depth(without de-watering)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification. b) Random Rubble Masonry
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification Granular material
12mm Cement Plaster 1:4 ( 1 cement :4 fine sand
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
3MTR HT.RRM/BREAST WALL
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) (I) Ordinary Soil (i)Upto 3m depth(without de-watering)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification. b) Random Rubble Masonry
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification Granular material
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
(SH:5MTR HT.RRC/RETAINING WALL
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) (I) Ordinary Soil (A) Manual Means (i)Upto 3m depth(without de-watering)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Furnishing and placing Reinforced / Prestressed cement concrete in super structure as per drawing and Technical specification. Case -I Using concrete mixer A. R.C.C.Grade M 20 q. Height upto 5m
a) Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
(SH:,RCC SLAB CULVERT 1.5 MTR SPAN AND 9 MTR LENGTH
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) (I) Ordinary Soil (A) Manual Means (i)Upto 3m depth(without de-watering)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications. (a) P.C.C. grade M15 (Height upto 5 m)
Plain/Reinforced Cement Concrete in Open Foundation complete as per drawing and technical specifications RCC Grade M20 Using Concrete Mixer
Furnishing and placing Reinforced/Prestressed cement concrete in super-structure as per drawing and technical specification RCC Grade M20 Using Concrete Mixer Height up to 5 m
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification Granular Material
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AP pipe, extending through the full width of the structure with slope of 1V:20H towards drawing foce. Complete as per drawing and technical specifications
(SH: PAVEMENT WORKS)
Granular Sub-base with Close Graded Material (Table:- 400-1) By Mix in Place Method Construction of granular sub-graded Material, mixing in a mechanical mix plant at OMC, carriage ofbase by providing close mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401) (i) For Grading- I Material
Wet Mix Macadam (Providing, laying, spreading stone aggregate to wet mix macadam specification including premixing the and compacting graded Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base /base course on well prepared surface and compacting with vibratory roller to achieve the desired density.)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.) (ii) for Grading II ( 19 mm nominal size )
(Tack Coat)Providing and applying tack coat with bitumen emulsion pressure distributor at the rate of 0.20 kg per sqm on theemulsion using prepared bituminous/granular surface cleaned with mechanical broom
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects) For Grading-II ( 10 mm nominal size )
(SH:CC DRAIN)
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil Manual Means (Depth upto 3 m)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Centring and shuttering including strutting, propping etc and removal of form work for : a) Foundation, footings, bases of columns etc. and mass concrete.
12 mm cement plaster 1 : 6(1 cement : 6 fine sand)
M/s AMUN MOTOR PARTS AND ENGINEERING WORKS (BID ID -6202)
MAITUNG TIKHKA (BID ID -6204)
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.27 MB
TenderDocument.pdf
Tender Documents • 2.51 MB
BOQ_2194.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .