Tender Value
₹20.3 L
EMD Value
₹21,000
Closing Date
8 Dec 2022, 3:00 pmClosed
The Block Development Officer VP
BDO Office Bargur
Krishnagiri Dt Bargur Block AGAMT II 2022_23 3 Works for1_Strengthening of Bund, Weir Repair and Revetment work 2_Strengthening of Bund, Weir Repair and Revetment work 3_Strengthening of Bund, Weir Repair and Revetment work Pak No BRG_38
2022_RDTN_267458_1
RocNo_5214_2022_R10_12_10_2022
Open Tender
Civil Works - Water Works
Item Rate
180 days
Bargur
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹21,000
BDO Office Bargur
14 Dec 2022
24 Nov 2022
8 Dec 2022
24 Nov 2022
8 Dec 2022
24 Nov 2022
28 Nov 2022
Amount
1.Strengthening of Bund, Weir Repair and Revetment work @ Vediyappan Kuttai H/O Varattanapalli Estimate Amount : 6.300 Lakhs
Clearing jungle clearance
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders And Hard Gravelly Soil As per SS 20b
Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 m to 100 m deploying earth moving machinary and tippers including benching formation of bunds breaking clods sectioning etc complete., Add Consolidation charges by Machinary
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed
Supplying & Erecting centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle
Below Ground Level
Above Ground level
Cement concrete 1:3:6 using 40mm HBG metal including cost and conveyance of all materials and labour charges etc., complete.,
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Rough stone dry packing for revetment
Provision for Name Board charges
2.Strengthening of Bund, Weir Repair and Revetment work @ Kanniyappan Kuttai H/O Varattanapalli Estimate Amount : 5.200 Lakhs
Clearing jungle clearance
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders And Hard Gravelly Soil As per SI62 Inflow Channel Clearance
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders And Hard Gravelly Soil As per SI62
Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 m to 100 m deploying earth moving machinary and tippers including benching formation of bunds breaking clods sectioning etc complete., Add Consolidation charges by Machinary
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed
Supplying & Erecting centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle
Below Ground Level
Above Ground level
Cement concrete 1:3:6 using 40mm HBG metal including cost and conveyance of all materials and labour charges etc., complete.,
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Rough stone dry packing for revetment
Provision for Name Board charges
3.Strengthening of Bund, Weir Repair and Revetment work @ Silukan Eri MI Tank H/O Varattanapalli Estimate Amount :8.800 Lakhs
Clearing Light jungle clearance
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders And Hard Gravelly Soil As per SI62 Inflow Channel Clearance
Earthwork excavating & depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders And Hard Gravelly Soil As per SI62
Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 m to 100 m deploying earth moving machinary and tippers including benching formation of bunds breaking clods sectioning etc complete., Add Consolidation charges by Machinary
Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 m to 100 m deploying earth moving machinary and tippers including benching formation of bunds breaking clods sectioning etc complete., Foreshore Bund
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed
Supplying & Erecting centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle
Below Ground Level
Above Ground level
Cement concrete 1:3:6 using 40mm HBG metal including cost and conveyance of all materials and labour charges etc., complete.,
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Rough stone dry packing for revetment
Provision for Name Board charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M/s.VCN Construction
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .