Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹34.5 LAccepted-Finance | L1 | Accepted-Finance OK | |
| 2 | L2₹34.8 L+₹29,503.77 (0.86%)Accepted-Finance | L2 | Accepted-Finance OK | |
| 3 | L3₹35.5 L+₹99,100 (2.87%)Accepted-Finance | L3 | Accepted-Finance OK | |
| 4 | L4₹35.9 L+₹1.4 L (4.00%)Accepted-Finance | L4 | Accepted-Finance OK | |
| 5 | L5₹37.5 L+₹3.0 L (8.58%)Accepted-Finance | L5 | Accepted-Finance OK |
Tender Value
₹40 L
EMD Value
₹80,000
Closing Date
16 Jan 2024, 6:00 pmClosed
GE Utility Secunderabad
GARRISION ENGINEER U SECUNDERABAD
REPAIR/ REPLACEMENT OF PUMP CONTROL PANEL, PUMP, MOTORS, EARTHING, SOLAR WATER HEATER, COPPER CABLE, AVIATION LIGHTENING PROTECTION, WATER LEVEL INDICATORS AND ALLIED WORKS ZONE IIA UNDER AGE E/M NO II OF GE (UTILITY) SECUNDERABAD
2023_MES_628448_2
GE(U)/SEC/TOKEN/47 OF 2023-24
Open Tender
Civil Works - Water Works
Item Rate
270 days
SECUNDERABAD
AS PER TENDER DOCUMENTS
8 documents required · 8 mandatory
₹500
GE (UTILITY) SECUNDERABAD
₹80,000
Yes
31 Jan 2024
21 Dec 2023
23 Jan 2024
21 Dec 2023
16 Jan 2024
4 Jan 2024
Amount
Dismantling and strip opening the centrifugal/ monoblock pump including disconnecting the suction, delivery, vaccum pipe lines and coupling for repairs to pump and refixing the same after repairs including overhauling the pump set, renewal of gasket to pump suction and delivery lines, gland packing, greasing nuts, bolts and washers,Metal Sleeves, painting ,all kind of grinding & welding work , replacement of bearing, etc as required for arresting any kind of water leakages including testing and commissioning complete all as specified and directed for the following capacities as mentioned below :
Pump 3 phase 200 to 220 HP capacity.
Pump 3 phase 150 to 180 HP capacity.
Motor 3 Phase 200 to 220HP capacity.
Motor 3 Phase 150 to 180 HP capacity.
M&L for rewinding the centifugal/ Monoblock electric motor startor or rotor with PVC insulated, super enamelled copper conductor with ‘F’ class heavy grade insulation weight and turns to achieve its full efficiency inclduing tying the winding and connecting the coils and brining the connections as that of exisitng one including applying insulating varnish, heating and backing the windings thoroughly including taking down old existing copper winding complete all as specified and directed of following capacities :- NOTE : Quoted rates inclusive of dismentling, refixing and transportation
Stator winding of Electric motor, 3 phase,150 to 220 HP capacity.
Supply only the following spares suitable for make existing at site of pump 2 stage 70 LPS capacity for repairs complete all as specified and directed :-
Pump shaft suitable for 2 stage impeller of capacity 70 LPS.
Cast Iron impeller Ist stage suitable for 70 LPS pump
Cast Iron impeller IInd stage suitable for 70 LPS pump.
Cast Iron bearing cover for drive and non drive end for pump of capacity 70 LPS
Cast iron inter stage ring for pump of capacity 70 LPS.
Rubber for water reflector for pump
Cast Iron shaft sleeve for drive end for pump of capacity 70 LPS.
Cast Iron shaft sleeve for non drive end for pump of capacity 70 LPS..
Cast Iron spacer sleeve for drive end for pump of capacity 70 LPS.
Cast Iron spacer sleeve for non drive end for pump of capacity 70 LPS..
Lock nut round type for pump of capacity 70 LPS.
Bronze nut for shaft sleeve for pump
Stuffing box bush cast Iron for pump
Gland packing for pump of capacity 70 LPS.
Set of key for pump set
Set of ‘O’ ring for pumps
Set of gaskets 3.0mm thick as per sample set of ‘O’ ring for pumps.
Cast iron gland set of 2 halves for pump of capacity 70 LPS Make of Pumps & Motors for item Nos: 1 to 4.18:- KIRLOSKAR/BEACON WEIR/DECON AIRCON/CG or as per existing make at site.
Supply only the spare part of Non Drive End Bearing suitable for make of motor existing at site as in repairs for the following capacities of motors complete all as specified and directed :-
Motor, 3 phase, capacity 200 to 220 HP.
Motor, 3 phase, capacity 150 HP to 180 HP.
Supply only the spare part of Drive End Bearing suitable for make of motor existing at site for epairs of the following capacities of motors complete all as specified and directed :-
Motor, 3 phase, capacity 200 to 220 HP.
Motor, 3 phase, capacity 150 HP to 180 HP.
Supply only the ball bearing/roller bearing (For Non-Drive End) suitable for make of pump existing at site for repairs of the following capacities of pumps complete all as specified and directed :-
Pump, fitted with 3 phase motor of capacity 200 to 220 HP.
Pump fitted with 3 phase motor of capacity 150 to 180 HP.
Supply only the ball bearing/roller bearing (For Drive End) suitable for make of pump existing at site for repairs of the following capacities of pumps complete all as specified and directed :-
Pump, fitted with 3 phase motor of capacity 200 to 220 HP.
Pump fitted with 3 phase motor of capacity 150 to 180 HP.
Supply and fix thermal overload relay with built in single phase prevention (CT Operated), 3 phase of capacity 180-300 Amps suitable for 3 phase star delta starter, 440 volts with necessary fixing materials including disconnecting and removing the old existing one complete all as specified and directed.
Supply and fix electronic timer switch ST 100, 240/360/415 volts, Range 3 to 30 sec with mounting kit suitable for old existing ET 100 replacement complete all as specified and directed.
S&F in replacement power contactor with coil voltage of 440 volts, 50 cycle confirming to IS, 225 / 300 Amps, 3 pole, with necessary inter connections suitable for 180 to 220 HP electric motor, testing and commissioning including removing the old existing one complete all as specified and directed.
S&F for spare contact kit of voltage of 440 volts, 50 cycle conforming to IS, 200 to 250 Amps, 3 pole, OF l&t with kit necessary inter connections suitable for200 HP electric motor, testing and commissioning including removing the old existing one complete all as specified and directed.
S&F for spare coil for power contactor of 440 volts, 50 cycle confirming to IS, 200 to 250 Amps rating suitable for 40 HP to 220 HP electric motor, testing and commissioning including removing the old existing one complete all as specified and directed.
Supply and fix in replacement of Copper cable lugs of size 120 to 150 sq mm complete all as specified and directed :-
S&F for replacement of carbon brush suitable for Electric motor of capacity 150 -220 HP complete all as specified and directed :-
Supply and replace coupling including rubber / belt of 150 HP to 220 Hp motor including necessary arrangements complete all as specifed and directed. Note : Quoted rates inclusive all arrangements including M & L required for replacement of Coupling
Material and labour for detachable Coupling cover fo safety of operator fof 150 HP to 220 HP motor madeout of 2 MM thick CRCA sheet duly painted og length 1.1 m and width 30 CM including necessary arrangeme for fixing at Base frame by using Nut and Bolts . Note : Quoted rates inclusive all arrangements required for fixing the protection cover
Supply and replace Unserviceable pressure guage stainless steel of pressure range 100 PSI Suitable for 70 LPS Pumps complete including necessary arrangements including supporting pipes complete all as directed Note : Quoted rates inclusive all arrangements required for replacement of Pressure Guage
Serviceaning / periodical checking of Starter panel board suitable for 150 HP to 220 HP Motor by replacing all unserviceable parts , checking for any kind of loose contact , identification of fault etc complete all as specifed and directed . Note : All spare to be replaced and measured under relivent items.
Disconnecting and removing the water and electric connections carefully from the existing submersible pump sets of capacity 3 HP to 10 HP and taking out the pump set alongwith pipes and fittings for flushing the bore well upto 450 feet depth or repair the pump set and strip opening the pump set for repairs/replacement of worn out spares, refixing of serviceable spares, assembling the pump set completely, testing of pump set, lowering the pump set inside the bore well after repairs including connecting back the water and electric connections, commissioning of pump set for satisfactory operation on its full load complete all as specified and directed. Note :- The spares required for repair the pump sets and rewinding of motors will be measured and paid seperetely.
Disconnecting and removing the water and electric connections carefully from the existing submersible pump sets of capacity 5 HP upto 15 HP and taking out the pump set alongwith pipes and fittings for flushing the bore well above 450 feet and upto 750 feet depth or repair the pump set and strip opening the pump set for repairs/replacement of worn out spares, refixing of serviceable spares, assembling the pump set completely, testing of pump set, lowering the pump set inside the bore well after repairs including connecting back the water and electric connections, commissioning of pump set for satisfactory operation on its full load complete all as specified and directed. Note :- The spares required for repair the pump sets and rewinding of motors will be measured and paid seperetely.
Disconnecting and removing the water and electric connections carefully from the existing submersible pump and motor sets of capacity upto 15 HP and taking out the pump and motor set alongwith pipes and fittings above 750 feet and upto 1100 feet depth of bore and repair the pump/motor set and strip opening the pump and motor set for repairs/replacement of worn out spares, refixing of serviceable spares, assembling the pump set completely, testing of pump set, lowering the pump set inside the bore well after repairs, including connecting back the water and electric connections, commissioning of pump set for satisfactory operation on its full load complete all as specified and directed. Note for item No 20 to 22 :(i) The spares required for repair the pump sets and rewinding of motors will be measured and paid seperately. (ii) Due to more depth existing coloumn pipes are welded bysuing GI Strip . Quoted rates inclusive of cutting of strip during removing and welding of new strip during refixing as well as any other arrangements required for the same.
M&L for rewinding the Submersible pump Motor with PVC insulated, super enamelled copper conductor with ‘F’ class heavy grade insulation weight and turns to achieve its full efficiency inclduing tying the winding and connecting the coils and brining the connections as that of exisitng one including applying insulating varnish, heating and backing the windings thoroughly including taking down old existing copper winding complete all as specified and directed for Submersible pump motor of following capacity :-
Submersible Motor upto and including 5 HP.
Submersible Motor above 5 HP up to 10 HP.
Supply only the following spares suitable for existing make of submersible pump set 3 to 10 HP capacity, multi stage for repairs complete all as specified and directed :-
Gun metal Impeller.
Stage casing.
SS Sleeves.
Middle bush.(LB)
Middle sleeve.
Discharge outlet.(LB)
Pump coupling.
SS Sleeve.
Suction bush.
Pump Shaft
Complete removal of existing treatment including preparation of old painted surfaces by washing, rubbing down and stopping of painted surfaces, painting with one coat of synthetic enamel paint of approved colour on centrifugal pump set of 150 HP to 220 HP capacity including inlet, outlet mains, couplings, sluice valve, non return valve, base plate, pulley with safe gaurd, vacume pipe line, LT panel board and writting the MES / SM number with black paint of suitable size of letters complete all as specified and directed.
All as per item No-25 above but for 10 HP to 40 HP centrifugal pump set.
All as per item No-25 above but for up to 7.5 HP centrifugal pump set Note for item No 25 to 27 : Name plate to be covered in suitable manner to avoid paint on name plate.
Supply and replace heavy duty long socket suitable for 50 mm dia heavy duty GI pipe complete all as specified and directed
S&F PVC insulated, unarmoured, heavy duty electric cables of 150 Sqmm single core with stranded copper conductor, 1100 volts laid in trenches, ducts, pipes, drawn across the roads/paths/drains/along poles/walls/floors / equipment etc cutting to required length connecting with necessary end ferrules / water proof joints and jointing and testing including disconnecting/taking out old existing cable complete all as specified and directed. Note : S & F of suitable DWC/HDPE pipe including fixing for cable protection is deemed to be included in the quoted rates.
S&F PVC insulated Copper conductor, sheathed, Submersible flat cables of size 4 Sqmm, 3 core, for Submersible Pumps, 1100 Volts grade, conforming to IS:694/1990 with latest amendments cutting to required length connecting with necessary end ferrules / water proof joints and jointing and testing including disconnecting/taking out old existing cable complete all as specified and directed.
S&F PVC insulated Copper conductor, sheathed, Submersible flat cables of size 2.5 Sqmm, 3 core, for Submersible Pumps, 1100 Volts grade, conforming to IS:694/1990 with latest amendments cutting to required length connecting with necessary end ferrules / water proof joints and jointing and testing including disconnecting/taking out old existing cable complete all as specified and directed.
M & L of insulating mats 2.5mm thick made of elastometer (a generic term that includes rubbers, latex and elastometric compounds that may be natural or synthetic or a mixture or a combination of both) for use as floor covering for the protection of workers on ac and dc installations with the system voltages up to 11 KV ac and 240 V dc and as per cl 5 of IS 15652 latest class B Cat II of size 1mX2m complete with relevant test reports and fixing on floor with suitable adhesives all as specified and as directed. Note : The mat should be permanently pasted with the held of suitable adhesive/resin. All joints and corners shall be filled/covered with insulating material of matching colour. Matching colour and matching designed tapes should be used to maintain an aesthetic look of the installation.
Material labour for removing submerceable pump motor set of capacity up to 10 HP stuck in side the borewell of depth up to 100 meter including by flushing the existing borewells of any size with drilling compressor mounted on truck at a pressure of 7 Kg / Sqcm with compressed air and flushing the sand, mud including flushing out tree roots etc from the bore well till discharge of the fresh water and then clear the bore by using Rod drilling using Bore well drilling machine from any kind of obstruction, reinstall the motor and coloumn pipe , necessary electric connection and testing complete all as specified and directed . Note; rate quoted by the contractor inclusive of Flushing by using suitable compressure , rod drilling for clearing of bore well, Removing the submerceable pump set stuck inside the boire well and reinstall the same after repair including removing and refixing of coloumn pipe , electrical connections, testing ets as required .
Supply & fixing HDPE heavy duty coloumn pipe in Bore well internal dia 50mm PN 16kq/Sqmm including all necessary fittings and fixtures as requited for fixing with submerceable motor Complete all as specified and directed. Note: Quoted rate inclusive of fixing of pipe with submerceable motor and lowring in existing bore well
Supply and fixing of DOL Starter suitable for upto 7.5 HP Motor, 5.5 KW and relay max range 20-32 Amp as in repairs complete all as specified and as directed.
Supply and fixing of single phase preventer suitable for upto 7.5 HP motor as in repairs complete all as specified and as directed.
Supply and installation pump starter electric control panel board, for out door use, DOUBLE door dust & vermin proof floor mounted made out of CRCA steel sheet of 3.15 mm thick angle iron legs of size50x50x5mm, having electrolytic high conductivity insulated bus bar made out of aluminium strips of rating 100 Amps for 3 phase, 415 Volts, 50 C/S 4 wire system, with cable enty jprovision, with suitable lugs gland, voltmeter, Ammeter and phase indicator complete, duly painted with two coats of stove enameled power coated paint over a coat of red oxide primer complete all as including necessary PCC work of height 300 cm from the ground level including disconnecting/taking out old existing unsv pump panel complete all as specified and directed of suitable size as per standards to accomodate ( Leg of the panel should not be less than 0.75 M and size of the panel should not be less than 70CmX60CMX30CM)) :- INCOMMING :- (a) MCCB, 4 pole, 415 Volt, 40 Amps, 16 KA - 01 No (b) 3 Phase LED Voltmeter, class - 01 No (c) 3 Phase LED Ammeter, class - 01 No (d) LED Indicator lamp in three colour RYB - 01 Set OUTGOING :- (a) MCB, 3 pole, 10 KA c Curve 415 volts, 32 Amps -01 No (b) DOL starter in sheet enclosure Motar rating AC-3 duty, 415 volts, 50 Hz suitable FOR 7.5 HP relay max rang 15-25 Amps-01 No. (c) Single hase preventor realy
Supply and fix BRASS n non return (reflux) valve screwed end with gun metal seat type of size 50 mm e Kartar/kirloskar/durga/zoloto
Supply and fix BRASS n non return (reflux) valve screwed end with gun metal seat type of size 40 mm e Kartar/kirloskar/durga/zoloto
Supply and fix Cast iron foot valve swing type flanged of size 50 mm as per IS 4038 .
Supply and fix Cast iron foot valve swing type flanged of size 65 mm as per IS 4038 .
Supply and fix Cast iron foot valve swing type flanged of size 80 mm as per IS 4038 .
Supply and fix Contactor 40 amps 3 phase coil operating operating voltage 230 volt
Supply and fix Contactor 25 amps 3 phase coil operating operating voltage 230 volt
Supply and fix MCB SP&N 32 Amps 10 KA C Curve .
Supply and fix MCB SP&N 25 Amps 10 KA C Curve .
Supply and fix MCB SP&N 20 Amps 10 KA C Curve .
Supply and fix MCB TP&N 20 Amps 10 KA C Curve .
Supply and fix MCB TP&N 32 Amps 10 KA C Curve . Note for item No 38 to 49 : Minor modifications and connected items for fixing above are deemed to be included in rates quoted.
Disconnecting, dismantling and taking aside the Pump set of 05 to 7.5 HP capacity for replacement of existing base frame with new one from the installed position and dismantling of existing PCC / RCC foundation and refixing the same motor by preparing sufficient PCC foundation and base frame reqiured for 5hp/7.5 hp HP pump including connecting items like nuts, bolts and setting the alignemnt of motor and pump set testing and commissioning all as specified and directed. Note:The quoted rate will be inclusive of required replacement of baseframe/MS channel and PCC / RCC for foundation.
Disconnecting, dismantling and taking aside the centrifugal motor and Pump set of 150 to 220 HP capacity for replacement of existing base frame with new one from the installed position and dismantling of existing PCC / RCC foundation and refixing the same motor by preparing sufficient PCC foundation and iron base frame reqiured for 150 hp to 220 HP pump and Motor including connecting items like nuts, bolts and setting the alignemnt of motor and pump set testing and commissioning all as specified and directed. Note:The quoted rate will be inclusive of required replacement of baseframe/MS channel and PCC / RCC for foundation.
Arresting lekages from pumps of motor capacity 05 HP to 25 HP by replacing gasket, nutbolts, gland packing etc as required complete all as directed Note: Rate quoted by the contractor inclusive of all items as requiree to arrest the leakages from pumps
M&L for flushing of existing borewells of any size upto 150 Mtrs depth with drilling compressor mounted on truck including surging and flushing the bore at a pressure of 7 Kg / Sqcm with compressed air and flushing the sand, mud including flushing out tree roots etc from the bore well till discharge of the fresh water including testing of water samples for chemical and bacteriological tests and complete all as specified and directed .
M&L for flushing of existing borewells of any size upto 250 Mtrs depth with drilling compressor mounted on truck including surging and flushing the bore at a pressure of 7 Kg / Sqcm with compressed air and flushing the sand, mud including flushing out tree roots etc from the bore well till discharge of the fresh water including testing of water samples for chemical and bacteriological tests and complete all as specified and directed .
M & L for shifting of cetrifugal monoblock Motor of capacity 5 HP to 10 HP to a new location as directed after disconnecting from existing position including making base by using PCC (!:2:4 by using 20 mm gravel of size not less than 1 M X0.75 X0.75 M and base by using C Channel of suitable size and making electric and water connection complete all as specified and directed. Note : Quoted rates inclusive all arrangements required for Shifting of Pumpset. Including provision and fixing of suitable channel and connected items are demmed to be included in rate quoted.
Servicing / periodical checking of Starter panel board suitable for 15 HP to 40 HP Motor by replacing all unserviceable parts , checking for any kind of loose contact , identification of fault etc complete all as specifed and directed . Note : All spare to be replaced and measured under relivent items.
Servicing / periodical checking of Starter panel board suitable for 5 HP to 10 HP Motor by replacing all unserviceable parts , checking for any kind of loose contact , identification of fault etc complete all as specifed and directed . Note : All spare to be replaced and measured under relivent items.
Servicing of Submerceable pump motor set of capacity up to 10 HP complete all as directed
Taking up or down steel tubing laid in trenches, on wall/in floor, in plinth protection of Bldg including segregation of serviceable pipes and keep in safe custody for reuse, complete with all fittings and connections of the following sizes:-
25 mm dia
40 mm dia
50 mm dia
Supply and laying steel water tubing medium grade, galvanised with all fitting, laid in wall / trenches and testing for leakages complete all as specified and directed for the following sizes:- NOTE : rate quoted by the contractor incluisive of all kind of fittings, bends, flenge , thread cutting etc as required for proper fixing of pipe
25 mm dia
40 mm dia
50 mm dia
Excavation in trenches not exceeding 1.5 m width and not exc 1.5 m in depth and getting out in hard/dense soil for removing/laying of pipe line complete all as specified and directed.
Returning, filling in, including spreading, leveling, watering and well ramming in layers not exc 25 cm in any type of soil complete all as specified and directed.
Removing excavated material (soils) n exc. 50m and depositing where directed at a level n exc. 1.5 m above the starting point complete all as specified and directed.
M&L for Disconnecting the suction and delivery pipe line and electric connections of centrifugal monoblock pump set 7.5 HP to 25 HP capacity and removing it from its position carefully and transporting the same to the work shop and refixing the same in its original position after carryout the repairs and connecting back the water and electric connections including testing and commissioning complete all as specified and directed.
M&L for Disconnecting the suction and delivery pipe line and electric connections of centrifugal monoblock pump set 1 HP to 5 HP capacity and removing it from its position carefully and transporting the same to the work shop and refixing the same in itsoriginal position after carryout the repairs and connecting back the water and electric connections including testing and commissioning complete all as specified and directed.
M&L for rewinding of centrifugal motor with super enameled copper conductor of same guage, weight and turn to achieve its full efficiency including tying the windings and connecting the coils and brining the connections as that of existing one including renewal of worn out/unserviceable bearings etc complete all as specified and directed for following capacity :-
(a) Centrifugal motor 20 /25 HP capacity.
(b) Centrifugal motor 10/15 HP capacity.
(b) Centrifugal motor 5.0/7.5 HP capacity.
(c) Monoblock motor 1/3 HP capacity.
M&L in repair of centrifugal pump set of 1 to 5 HP capacity to achieve the water discharge as per manufacturer recommendation including replacement of worn out unserviceable parts complete all as specified and directed. Notes :- (i) Expendable stores like cotton waste/cleaning materials, lubricants, gland packing, metal filling, matchining and transportation to and from site to work shope are deemed to be included in unit rate quoted. (ii) Labour against this item for replacement of spares (supply only items) shall be deemed to be included in the rate quoted. (iii) Spare parts like SS sleelves, impeller, stage casing etc shall be measured and paid separately under relevant item of Sch 'A'.
Supply only the following spares for repairs of centrifugal / monoblock pump set of up to 5 HP capacity complete all as specified and directed :-
Ball bearing suitable for induction motor.
Ball bearing for non drive end suitable for pump.
GM bush.
CI impeller.
MS pump shaft.
Gland cover.
M&L in repair of centrifugal pump set of 7.5 to 25 HP capacity to achieve the water discharge as per manufacturer recommendation including replacement of worn out unserviceable parts complete all as specified and directed. Notes :- (i) Expendable stores like cotton waste/cleaning materials, lubricants, gland packing, metal filling, matchining and transportation to and from site to work shope are deemed to be included in unit rate quoted. (ii) Labour against this item for replacement of spares (supply only items) shall be deemed to be included in the rate quoted. (iii) Spare parts like SS sleelves, impeller, stage casing etc shall be measured and paid separately under relevant item of Sch 'A'.
Supply only the following spares for repairs of Centrifugal pump set of 7.5 to 25 HP capacity complete all as specified and directed :-
(a) Ball bearing drive end for suitable size.
(b) Ball bearing for non driving end of suitable size.
(c) Gun Metal bush.
(d) CI impeller.
(e) MS pump shaft.
(f) Gland cover.
(g) Gland.
M&L for dismantling of defective sluice valve for repairs, such as repacking stuffing box of sluice valve spindle, refacing, grinding, stuffing and threading of spindle, replacement of worn out check nut, repairs to gate assembly etc, replacement of jointing materials such as rubber sheets, nuts, bolts, washers and gland rope etc and refixing in its original position, testing on completion complete all as specified and directed for the following sizes:-
(a) 100 mm Dia
(b) 150 mm Dia
(c) 200 mm Dia
Supply and fix in replacement of unserviceable Gun metal (Bronze) Gate, globe & check valves IS : 778/1980 CL-1 connected with iron wheel head, screwed at both ends for iron pipes and fixed complete all as specified and directed for the following sizes:-
(a) 20mm dia bore
(b) 25mm dia bore
(c) 40mm dia bore
(d) 50mm dia bore.
Supply and fixing in replacement of DI D/F Gate valve (Soft Sealed) Resilient Seated Soft Sealing gate valves( Sluice valves NON-RAISING TYPE ) with body bonnet of ductile cast iron of grade GGG-40/SG- 400/15 or GGG-50/SG-500/7 or equivalent grade Wedge fully rubber lined with EPDM Food grade quality and Seals of NBR and the valve should be vacuum tight and 100 % leak proof with face to face dimension as per BS 5163-89/IS 14846-2000/DIN 3202 F 4. and Valves should be electrostatic powder coating both inside and outside pocket less body passage class PN 1.6 including all jointing materials ( Gasket , Nut bolts etc) connecting and testing complete all as specified and directed. Note : OLD SRRVICEABLE VALVES TO BE DEPOSITED TO the DEPARTMENT store FOR FURTHER USE as directed by Engr-In-Charge)
100 mm Dia
150 mm Dia
200 mm Dia
M&L Cement Concrete 1:2:4 (20mm Graded Stone Aggregate) as in Side Wall of Cable Duct, etc., complete all as specified and as directed.
Advance Maintenance Free G.I. SAFE EARTHING Electrode with PIPE of not less than 50 mm outer dia( THICKNESS NOT LESS THAN -2.5MM) and two meter length, The electrode should be of galvinised (80 -100 micron) along with earth lead as Galvanised steel strip of size 32 X6 mm 7.5 m . The GI Electrode shall be pre-filled with Cristaline Conductive Material (CCM) . The GI electrode shall be surrounded with 25 kg BackFill compound to provide maximum contact between the electrode and Back Fill Compound. .The earting pit should be cover with pcc(1:2:4 , B1) cover ,of 450 x 450 mm complete all as specified and directed make ASHLOK / INDELEC/JMV /TERCEL/True Power.
S&F, connecting and testing in repair of Cast Iron foot Valves 150 mm dia flanged ends swing type operation with rubber seat as per IS : 4038 single disc with all standard accessories and tested including replacement of nuts, bolts, washers, gaskets, packings etc complete all as specified and directed.
S&F, connecting and testing in repair of Cast Iron foot Valves 200 mm dia flanged ends swing type operation with rubber seat as per IS : 4038 single disc with all standard accessories and tested including replacement of nuts, bolts, washers, gaskets, packings etc complete all as specified and directed.
S&F Transciever automation for the water level Detector and controller with the feature mentioned here under:- 1. S& F Transciever must communicate at a distance of 3km -5kms range with each module must have the LORA/GSM or suitable communication module ( long range antenna) must work above 500 mhz and each module shall have a processor module connecting to the sensor, with the facility that the processor module to sense the low level (10-20%) and high level of the water level (90-100%) so as to raise the hooter and communicate with the other hardware modules with antennas. S&F transducer module wiring through the D sub connectors (MIL industrial grade are to be used). All the wiring must be shielded optical co-axial cable for connection to flasher and hooter. Rates quoted are deemed to be included for suitable flasher and hooter. S&F Hooter 12V/5 Amp with suitable converter or hooter suitable for 230V AC Supply must be provided standard suspended rust proof stand Note: All the NPT cable glands must be used for the sensor interface and MCB controller board. S&F 12V flasher with suitable converter or flasher suitable for 230V AC Supply connected with suitable 3 Core Co axial cable suitably crimped nicomatic connector. Note: All the cables to be drawn through suitable medium grade conduit suirtably fixed with clamps. S &F of LED display board with superior night vision display to be provided at the receiver station. S&F controller Board confirming to IP 65 protection 3D printed with EMI/EMC compatible FE 32 material for the enclosure. All the 3D/CAD models must be provided for review before the enclosre are fitted with AUTO CAD/PRO drawings shall be provided. Note: Complete system shall be warratied with 24 hrs rectification for any non functioning for a peroid of 1 year replacement warranty. (a) One transmitter for over Head Tank and one receiver for Pump House . Note : Contractor has to visit the site before execution. Any cable required deemed to be included in quoted rate. No extra payment will be made on this account.
Supply only Calcium Hypochlorite calcium based high strength granular chlorine having 65 % - 70 % chlorine content packed in 45 Kgs PVC sealed container, superior quality suitable for treatment of drinking water ( Much more stable than chlorine gas, bleaching power and sodium hypochlorite) all as specified and directed. NOTE :- Approval of chemical (calcium hypochlorite) shall be given after verification of test certificates of chemical of various manufactures and other factors like chemical and safety and health hazard aspects of usage of chlorination . Make of the chlorination of chemical must be stated in production of certificate duly certified by govt laboratory conforming compliance of specification suitable for drinking water with a declaration from the laboratory that from the technical strength stability health safety and operation point of view , this product is used for drinking water applications for consumption by humans and the brand/make of calcium hypochlorite is suitable for drinking water chlorination and its sample has been tested by Govt Laboratory. Traditional means of chemical shall be used subject to fulfill the parameters specified in the manual on water supply and treatment (Third edition May 1999) issued by Central Public Health and Environmental Engineering Organization (CPHEEO), Ministry of Urban Development New Delhi. The contractor shall produce manufacturers "Certificate of Compliance" indicating date of manufacturer in original alongwith every consignment of supply. Test certificate from Govt approved Test Laboratory shall accompany with every consignment of supply to ensure that the materials supplied are in with conformity with relevant IS.
S&F, connecting and testing in repair of Cast Iron non return (Reflux) valves flanged ends in swing type design IS-5312 part-I, K517, PN-1.6, 150 mm dia both ends flanged etc including jointing materials of sizes complete all as specified and directed.
Supply and fixing of New water meters of make (Chambal) the meters are confirming to ISO 4064:2005, including MS flange, nut bolts, rubber packing and flange thickness conforming to IS:7322-1985 and flange dimension conforming IS: 1538-1993 of size 300 mm dia MS/DI/CI pipe line, by cleaning and grinding by 3 core welding of the pipe outside welding of the joint including cost of gas oxygen acetylene, welding machines, skilled and semi skilled workers internal lighting arrangements and all other incidental and operational charges etc., complete all as directed by Engineer in Charge.
Supply and fixing of New water meters of make (Chambal) the meters are confirming to ISO 4064:2005, including MS flange, nut bolts, rubber packing and flange thickness conforming to IS:7322-1985 and flange dimension conforming IS: 1538-1993 of size 150 mm dia MS/DI/CI pipe line, by cleaning and grinding by 3 core welding of the pipe outside welding of the joint including cost of gas oxygen acetylene, welding machines, skilled and semi skilled workers internal lighting arrangements and all other incidental and operational charges etc., complete all as directed by Engineer in Charge.
Haasith constructions
bethelenterprises
SN POWER TECH
sandhya enterprises
Srinivasa Consructions
vvcenterprises
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .