| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.1 LAccepted-Finance | L1 | Accepted-Finance Accepted |
Tender Value
Refer Docs
EMD Value
₹11,200
Closing Date
30 May 2022, 2:00 pmClosed
SE/TEDC/Theni
O/o SE/TEDC/Theni, NRT Nagar Main Road, Theni
Work Contract Agri feeder Segregation in 22 KV Royappanpatty feeder in Town Uthamapalayam Section under RDSS scheme
2022_EB_233709_1
008
Open Tender
Electrical Works
Item Rate
120 days
Town / Uthamapalayam
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹11,200
Yes
31 May 2022
24 May 2022
31 May 2022
24 May 2022
30 May 2022
24 May 2022
Excavation of POLE PITS For pole above 8.00m length by using JCB/Manual
Excavation of POLE PITS In Hard Soil (common to all size of poles)
Excavation of Stay pit of 4.5 ' to 5 ' depth using JCB / Manual
Excavation of Stay pit in Hard rock soil
Erection of metal supports above 9m / RSJ / Rail Pole/Tubular Poles
Erection of stay set complete in the rock area by blasting
Fixing of Line Materials V cross arm 4.5 feet
Fixing of LT 3 phase cross arm
Fixing of HT / LT Ti fitting
Fixing of HT PIN insulator with Pin 22 kv
Fixing of HT strain disc 22 KV
Fixing of Two Tapping cross arm per cut point upto 33 KV line including fixing of Discs,insulators and Jumpering etc..
Fixing of shackle
Fixing of Aluminium knob
Fixing of HT LAS (3 Nos.)
Fixing of LT LAS (3 Nos.)
Paving and stringing of conductors of above 7/2.59 mm ACSR or other equivalent conductor upto 7/3.35mm ACSR or other equivalent conductor
Paving and stringing of conductors of 7/4.09mm ACSR or other equivalent conductor
Releasing and reerection (resagging) of one run of all sizes of conductor
Erection of Distribution Transformer structure complete as per TNEB standard including painting, feeders arrangrment, colour washing of RCC poles etc.. Fixing of poles type to be unit HT / LT LAS and jumpering 3 Nos Earth pits with earth trough except erection of Distribution Transformer. (Data as per Annexure II)
Erection of Distribution Transformer including loading of Distribution Transformer at stores and erection at structure or vice versa. Upto 25 KVA Distribution transformer / Metering set.
Erection of Distribution Transformer including loading of Distribution Transformer at stores and erection at structure or vice versa. Above 25 KVA to 100 KVA
Erection of DP structure with stay as per TNEB standard including fixing of top channel, cross bracing, concreting, painting, colour washing etc., With 22 / 33 KV AB switch using all types of poles of size 9.14 m and above length
Concreting with 1:4:8 mix using 40 mm Jelly including curing(Material + labour)Mass concreting of poles
Concreting with 1:4:8 mix using 40 mm Jelly including curing(Material + labour) Sleeve concreting
Concreting with 1:4:8 mix using 40 mm Jelly including curing(Material + labour) Stay concreting
Earthing of poles with GI wires 4 or 6 SWG by coil earthing
Pipe earthing including excavation of earth pit and fixing earth pipe 3 m length
Loading or unloading of Distribution Transformer Upto 100 KVA
Loading or unloading All REC, RCC pole above 8.00 m length
Loading or unloading Metal poles all sizes
Loading of Conductor
Unloading of Conductor
Loading / Unloading of Iron & Steel
Loading / Unloading of line materials
Loading / Unloading of 11 KV strain disc
Loading / Unloading of LT Pin insulator shackle, guy shackle, LT Pin, Metal parts, HT pin etc.,
Transportation of all types and sizes of poles and other associated materials from Road side to pole pit and vice versa upto 0.50 KM
Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) For a lead upto 5 KM
Transporting of conductors of all sizes from road side to pit locations upto one KM of Conductor
Transporting of Distribution Transformer / Line materials from stores to office / site upto 10 KM distance by engaging 1 Ton capacity Minidor (Lorry)
Painting of distribution transformer of all capacities (paint to be supplied by the Board) including cleaning of DT
Numbering of poles including base painting and with cost of paint
Painting of Cement poles by Distember coating including cost of distember
Painting of structure materials distribution transformers with aluminium paint of structure poles and writing of transformer details (Items 1 to 6 brush to be owned by the contractor)(Paint to be supplied by Department)
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_275358.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .