Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹62.4 LAdmitted-Finance | L1 | Admitted-Finance |
Tender Value
₹66.1 L
EMD Value
₹1.3 L
Closing Date
5 Jan 2026, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Secretary BDA
MG Road, Yamunapuram Commercial Complex, Bulandshahr
Work No 2 Old GT Road Se Gram Hazratpur Ko Jane Wale Pauch Marg Per Pani Nikasi hetu RCC Drain Nirman Karya
2025_BDAB_1102082_1
7767/BKDA/2025-26 Dt.24-12-2025 TB
Open Tender
Civil Works
Percentage
365 days
BKDA
Tender Fee, EMD and Other documents as per the tender document/NIT
2 documents required · 2 mandatory
₹2,655
VC BDA eTendering A/c No 50100165330599
₹1.3 L
28 Feb 2026
27 Dec 2025
6 Jan 2026
27 Dec 2025
5 Jan 2026
27 Dec 2025
Excavation in foundation in soil mixed with Moorum, shingle, kankar requiring the use of special tools and plant such as pickaxes, sabbals etc.including lift upto 1.50M. & including filling watering &ramming of excavated earth into the trenches or into the space between the building & the sides of the foundation trenches or into the plinth & removal & disposal of surplus earth as directed by the Engineer-in charge upto a distance of 30M. from the foundation trenches. [SI. No.252/SOR-2022]
Cement Concrete with 4 cm gauge approved stone ballast, coarse sand & cement in the proportion of 8:4:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work. [SI. No.281/SOR-2022]
R.C.C. work with Cement approved coarse sand and 2 cm.(3/4") gauge approved stone ballast in the proportions of 1:1.5:3 in R.C.C. Raft foundation and footing excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W. G.G.I., binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and T & P etc. required for proper completion of the work. Excluding cost of Binding wire. [SI. No.287a+279a-279/SOR-2022]
R.C.C. work with Cement approved coarse sand and 2 cm.(3/4") gauge approved stone ballast in the proportions of 1:1.5:3 in R.C.C.column & wall. excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W. G.G.I., binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and T & P etc. required for proper completion of the work. Excluding cost of Binding wire. [SI. No.289/SOR-2022]
R.C.C. work with Cement approved coarse sand and 2 cm.(3/4") gauge approved stone ballast in the proportions of 1:1.5:3 in R.C.C. slab. excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W. G.G.I., binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and T & P etc. required for proper completion of the work. Excluding cost of Binding wire. [SI. No.New item Ch-22/SOR-2022]
Cast Cement concrete door sills, chaukhats, boundary posts shelves and similar small work with cement, approved coarse sand and 2 cm.(3/4") gauge approved stone ballast in the proportions of 1:1.5:3 excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W. G.G.I., binding wire and including the cost of moulds and all other materials, labour and T & P etc. required for proper completion of the work. Excluding cost of Binding wire.[SI. No.282a/SOR-2022]
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. (D.S.R-5.22.6/2023)
Cleaning/desilting of Crossing Hume Pipe 1000 mm dia across old GT road approx 35 metre including labour and T & P etc. required for proper completion of the work (Analysis Rate)
First class Brick Work in 1:4 cement & fine sand 1.25 F.M. mortar in foundation and plinth including supply of all materials, labour and T&P etc. requried for proper completion of the work. [SI. No.305/SOR-2022]
12 mm thick plaster with cement and fine sand of 1.25 fineness modules in 1:4 over brick work minimum thickness not to be less than 1cm. including supply of all materials, labour, tools & plants etc. required for proper completion of the work. [SI. No.584/SOR-2022]
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
TD_TB_7767.pdf
Tender Documents • 0.88 MB
BOQ_2031937.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .