Tender Value
₹3.4 Cr
EMD Value
₹4.2 L
Closing Date
21 Sept 2026, 6:00 pm
Chief Engineer Chd Zone
HQ CE Chandigarh Zone N Area, Airport Road Chandigarh-160003
CE CHZ CHM T 10 2026 27 PROVN OF ETP AT COMMAND HOSPITAL AT CHANDIMANDIR
2026_MES_784253_1
CE CHZ/CHM/T-10/2026-27
Open Tender
Civil Works - Others
Lump-sum
275 days
Chandimandir
As per Tender Documents
8 documents required · 8 mandatory
₹2,000
GE (U) Chandimandir
₹4.2 L
Yes
17 Aug 2026
17 Aug 2026
23 Sept 2026
17 Aug 2026
21 Sept 2026
14 Sept 2026
17 Aug 2026 - 28 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Total amount of Sch 'A' Sec I (BUILDINGS WORKS) Lump sum price worked out by the contractor for " BUILDINGS WORKS " as listed in schedule 'A' Part-I | |||||
| 1.01 | Design, supply & construction of plant room of size 17.3 mtr X 10.40 mtr complete all as specified and directed. | 1 | Lump Sum | - | - |
| 2 | Total amount of Sch 'A' Sec II (SITE CLEARANCE, SITE DEVELOPEMENT & MISC. EARTH WORKS) Lump sum price worked out by the contractor for " SITE CLEARANCE & Earth Works " as listed in schedule 'A' Part-II | 1 | Lump Sum | 2,11,385.97 | ₹2,11,385.97 |
| 3 | Total amount of Sch 'A' Sec III (INTERNAL ELECTRIFICATION ) Lump sum price worked out by the contractor for " INTERNAL ELECTRIFICATION " as listed in schedule 'A' Part-III | 1 | Lump Sum | 1,52,480.09 | ₹1,52,480.09 |
| 4 | Total amount of Sch 'A' Sec IV (ROAD/PATH/CULVERT/HARD STANDING) Lump sum price worked out by the contractor for " ROAD/PATH/CULVERT/HARD STANDING " as listed in schedule 'A' Part-IV | 1 | Lump Sum | 17,13,358.2 | ₹17,13,358.2 |
| 5 | Total amount of Sch 'A' Sec V (AREA DRAINAGE WORKS) Lump sum price worked out by the contractor for " AREA DRAINAGE WORKS " as listed in schedule 'A' Part-V | 1 | Lump Sum | 4,01,281 | ₹4,01,281 |
| 6 | Total amount of Sch 'A' Sec VI (FENCING/GATE/COMPOUND GATE) Lump sum price worked out by the contractor for " FENCING/GATE/COMPOUND GATE " as listed in schedule 'A' Part-VI | 1 | Lump Sum | 24,50,044.86 | ₹24,50,044.86 |
| 7Schedule 'A'Section-VII (Misc Items of Works) Note : This schedule is not pre-priced by MES and the pre-priced rate indicated as "Rs 0.00" under Col. f siginifies this fact only. | |||||
| 8 | EFFLUENT TREATMENT PLANT (ETP)
Design, Engineering, Procurement, Supply, Civil Construction, Fabrication, Erection, Installation, Testing, Commissioning of a fully functional Effluent Treatment Plant (ETP) of 300 KLD nominal design capacity at command hosiptal Chandimandir, Haryana. The Contractor shall be responsible for every element of the work from receipt of the Department's inputs to the regulatory-compliant, fully operational plant.
A. DEPARTMENT'S INPUTS
The Department shall furnish following inputs.
(a) Site Plan: Approved site plan showing the physical boundaries of the area earmarked for the ETP, the inlet point (raw wastewater entry connection), and the outlet point (treated effluent discharge connection).
(b) Nominal Design Flow: 300 KLD (Kilolitres per Day). The Contractor shall note that actual flow will vary seasonally and diurnally. The ETP shall be designed to remain fully functional and performance compliant at any flow between minimum flow (min 50%of nominal capacity) to the plant to peak flow (peak factor of 3)
(c)Tentative Wastewater Characteristics: The Contractor shall conduct independent wastewater sampling and laboratory analysis and shall design the plant to treat the actual measured characteristics. However, a tentative wastewater characteristics for reference is provided in DBR.
(d) Water Supply Take-off Point: Location and pipe size of the nearest departmental water supply connection available for plant use. Provision of water beyond this take-off point is the Contractor's responsibility. | 1 | Each Job | - | - |
| 8.1 | (e) Electrical Take-off Point: Location, voltage (415V, 3-phase, 50 Hz), and available capacity of the nearest departmental electrical supply point. Wiring, panels, earthing, and all electrical works from this take-off point onwards are the Contractor's full responsibility.
B. INVESTIGATIONS & DESIGN to be done by the Contractor :-
B-1. Site Investigation & Soil Testing
The Contractor shall carry out a complete geotechnical site investigation comprising a minimum of three (03) boreholes to a depth of not less than 6 metres or to hard strata, whichever is greater. A soil test report from a NABL-accredited laboratory shall be submitted. All foundation and civil designs shall be based on the actual soil bearing capacity and groundwater table data so determined. The Contractor bears full responsibility for foundation adequacy
B-2. Independent Wastewater Characterization
The Contractor shall collect composite samples from various source points (eg Dialysis, Laundry, OT, Manhole etc, additional sample not mentioned but necessary for complete working design is deemed to be included) per day for one week. Samples shall be analysed by a NABL-accredited environmental laboratory for all parameters listed in DBR, any additional parameters the Contractor deems necessary for design. The Characterization Report shall be submitted to the Engineer-in-Charge. The Design shall be based on this actual data. | - | - | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.30 MB
FinalTender.pdf
Tender Documents • 5.47 MB
BOQ_879403.xls
BOQ • 5.98 MB
drg_10.PDF
Additional Documents • 0.12 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].