| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.4 CrAdmitted-Finance | ₹1.4 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.4 CrAdmitted-Finance | ₹1.4 Cr | L2 | Admitted-Finance |
| 3 | L3₹1.4 CrAdmitted-Finance | ₹1.4 Cr | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S HONEY ENTERPRISES L3 | R.D. ENTERPRISES L2 | M/S AVINA ENTERPRISES L1 |
|---|---|---|---|---|---|---|
| 1.00 | Handing and Dragging of Transformer from stacking yard to repairing hall with accessories. | - | - | - | - | - |
| 2.00 | 10 KVA | 100 | Nos. | 56 ₹5,600 | 55 ₹5,500 | 54 ₹5,400 |
| 3.00 | 16 KVA | 200 | Nos. | 59 ₹11,800 | 58 ₹11,600 | 57 ₹11,400 |
| 4.00 | 25 KVA | 2,700 | Nos. | 80 ₹2.2 L | 79 ₹2.1 L | 78 ₹2.1 L |
| 5.00 | 63 KVA | 500 | Nos. | 114 ₹57,000 | 113 ₹56,500 | 112 ₹56,000 |
| 6.00 | 100 KVA | 150 | Nos. | 115 ₹17,250 | 114 ₹17,100 | 113 ₹16,950 |
| 7.00 | Cutting of top cover plates & fitting of the transformers, draining of its oil & Detanking of core & coil Assembly. | - | - | - | - | - |
| 8.00 | 10 KVA | 100 | Nos. | 66 ₹6,600 | 65 ₹6,500 | 64 ₹6,400 |
| 9.00 | 16 KVA | 200 | Nos. | 66 ₹13,200 | 65 ₹13,000 | 64 ₹12,800 |
| 10.00 | 25 KVA | 2,700 | Nos. | 88 ₹2.4 L | 87 ₹2.3 L | 86 ₹2.3 L |
Tender Value
₹1.4 Cr
EMD Value
₹1.4 L
Closing Date
30 Dec 2024, 5:00 pmClosed
S.E., EWSC, LUCKNOW
SE, EWSC, SECTOR-I, GOEL CHAURAHA, ALIGANJ LUCKNOW
REPAIRING OF 10 KVA TO 630 KVA DAMAGED T/F AT RAIBAREILLY WORKSHOP
2024_MVVNL_985723_1
56/EWSC/LKO/2024-25
Open Tender
Miscellaneous Works
365 days
RAIBAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,900
A/c No. 104805001530, IFSC CODE. ICIC0001048
₹1.4 L
13 Jan 2025
21 Dec 2024
31 Dec 2024
21 Dec 2024
30 Dec 2024
21 Dec 2024
Amount
Handing and Dragging of Transformer from stacking yard to repairing hall with accessories.
Cutting of top cover plates & fitting of the transformers, draining of its oil & Detanking of core & coil Assembly.
Dismantling of core & coil Assembly and cleaning of core by using warm old oil and hot air making it dirt free.
Reconditioning of L.V leg coils strips including removing of old DPC covering then providing double paper covering and making of LV Leg coils of same size and No. of turns and dimensions as old one.
Making of L.V leg coils from new DPC strips, of same size and No. of turns and dimensions as old one.
Reconditioning/Making of H.V leg coils from new DPC or SE wire of same size and No. of turns and dimensions as old one.
Assembly of core & coil and fitting of other parts requiring replacements such as press board making supports between adjacent section by insulating spacers & tapping etc.
Shifting and keeping the assembled core& coil etc. in OVEN from the repairing hall
Dragging of transformers tank from the repairing hall to washing area and its cleaning of rust etc.
Repairing of damaged T/F body/radiator by electric/gas welding complete in all respect for arresting oil leakage.
Cleaning of T/F tank completely and making it ready for painting
Painting of inner side of T/F tank with heatproof zinc chromatic paints in two coats after providing primer of red oxide paint.
Dragging/shifting out empty tank after painting to repairing hall.
Taking out core and coils assembly from the OVEN and shifting to repairing hall.
Welding the top cover after tanking of core and coil assembly into painted tank and tightening of assembly into the tank and fitting all accessories of transformer and filling of oil.
Spray painting of transformer tank from outside with supper enamel synthetic Grey paint in two coats after providing primer of red oxide paint and package rate per transformer the supply item to be provided by the contractor for repairing of transformer details of supply item are annexed here to like – Oxygen gas, M-seal, Araldite, Paint and Brush for lettering, Welding electrode Gas cutter etc.
Dragging/shifting of repaired T/F near to the test cabin/testing place and dragging /shifting T/F to yard after testing and its stacking at identified place.
Part-B :- 160 KVA, 250 KVA, 400 KVA & 630 KVA
Handling and Dragging of damaged Transformer from stacking yard to repairing hall with accessories
Cutting/Opening of top cover plates & fittings of the transformers, draining of its oil & Detanking of core & coil Assembly.
Dismantling of core & coil Assembly and cleaning of core and tank (inside) by using warm old oil and hot air making it dirt free/sludge free.
Reconditioning of L.V leg coils strips including removing of old double paper covering and cleaning of strip than providing double paper covering
Making of L.V leg coils from reconditioned strips/new DPC strips, of same size and No. of turns and dimensions as old one.
Reconditioning of old damaged H.V. leg coils wire by removing old Double paper covering, cleaning of wire and providing new DPC insulation etc.
Making of H.V leg coils from reconditioned/new DPC wire of same size No. of turns and dimensions as old one.
Assembly of core, channel (dully painted by zinc chromatic paint) & coil and fitting of other parts requiring replacements such as press board making supports between adjacent section by insulating spacers & tapping etc.
Shifting and keeping the assembled core & coil etc. in OVEN from the repairing area
Dragging of transformer tank to washing area and cleaning of rust/dirt etc from outer surface by using caustic soda & water solution.
Repairing of damaged T/F body/radiator by electric/gas welding complete in all respect for arresting oil leakage.
Completely drying & Cleaning of T/F tank (inside and outside) by using hot air/cotton waste/sand paper etc completely and making it ready for painting
Painting of inner side of T/F tank with heatproof zinc chromatic paints in two coats after providing primer of red oxide paint.
Dragging/shifting out empty tank after painting to assembly area.
Taking out core and coils assembly from the OVEN and shifting to repairing area & again tightening the assembly.
Tightening/Welding the top cover after tanking of core and coil assembly into tank and tightening of assembly into the tank and fitting all accessories of transformer and filling of oil.
Spray painting of transformer tank from outside with supper enamel synthetic Grey paint in two coats after providing primer of red oxide paint.
Dragging/shifting of repaired T/F near to the test cabin/testing place and dragging /shifting T/F to yard after testing and its stacking at identified place.
Part-c Round Body Single Phase 10 KVA To 16 KVA
Handling and Dragging of damaged Transformer from stacking yard to repairing hall with accessories
Cutting/Opening of top cover plates & lifting of the transformers, draining of its oil & Detanking of core & coil Assembly.
Dismantling of core & coil Assembly and its cleaning.
Dismantling of Shell Core and coil assembly. Removing of HV and LV Leg coils for assessing its reuse, reuse of major insulating material if possible, checking and recording of physical dimensions of coil.
Making of complete HV & LV leg Alu. Leg coils identical to original one with same number of turns, weight etc providing super enameled/DPC conductor/ Strip confirming to IS 1971 153 in place of old and damage coil. Alu.coil, wire strip will be provided by the department. All coil assembly of identical voltage shall be interchangeable without requiring any special equipment. Shell Coil shall be supported between adjacent sections by insulations (flick Paper) Paper, spacers, beamers and other insulations. Rewinding shall be arranged to ensure free circulation of oil to reduced hot spots in winding. The insulation of coil shall be treated with suitable insulating, varnish or equivalent compound to develop the full electrical strength of
Assembly of Shell core (Three Limbs) coils and fitting of top and other parts. Replacement of insulation such as press board, craft paper, making support between adjacent section by insulating spacers and wrapping etc. shifting of repaired core coil assembly and placement inside the oven for proper dry out.
Shifting and keeping the assembled core& coil etc. in OVEN from the repairing hall
Dragging of transformers tank from the repairing hall to washing area and its complete washing, cleaning, removing of rust and carbon etc.
Repairing of damaged T/F body/radiator by electric/gas welding complete in all respect for arresting oil leakage.
Painting of inner side of T/F tank with heatproof zinc chromatic paints in two coats after providing primer of red oxide paint.
Dragging/shifting out completely dried empty tank after painting to repairing hall.
Taking out core and coils assembly from the OVEN and shifting to repairing hall.
Welding/Tightening the top cover after tanking of core and coil assembly into painted tank and tightening of assembly into the tank and fitting all accessories of transformer and filling of oil.
Spray painting of transformer tank from outside with supper enamel synthetic Grey paint in two coats after providing primer of red oxide paint.
Dragging/shifting of repaired T/F near to the test cabin/testing place and dragging /shifting T/F to yard after testing and its stacking at identified place.
Package rate per transformer of supply item to be provided by the Contractor for repairing of transformer. Details of supply items are annexed hereto.
R.D. ENTERPRISES (BID ID -4822902)
M/S HONEY ENTERPRISES (BID ID -4819314)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.38 MB
doc56.pdf
Tender Documents • 1.32 MB
BOQ_1737344.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid