| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
2 Aug 2024, 9:00 amClosed
SE EUDC
LAL DIGGI ALIGARH
Shifting of electrical Lines, Poles other electrical equipment against sanctioned package under Deposit Head for construction of 02 lane rail over bridge at railway crossing section near Begum Sultan Jahan Hostel AMU of Bareilly railway section on Al
2024_DVVNL_933880_3
EUDCA-05/2024-25
Open Tender
Electrical Works
Turn-key
90 days
EUDD-4 ALIGARH
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,180
DVVNL
₹10,000
16 Aug 2024
27 Jul 2024
2 Aug 2024
27 Jul 2024
2 Aug 2024
27 Jul 2024
Amount
Safe carriage of following materials from Store centre or any other place to the respective site of work through the Kachha/Pacca road including loading, unloading at the respective ends and erection of same including the work of dragging as per site requirement, jumphering of Transformer with 11 KV line through LT ABC cable, Weasal conductor etc. Cost of labour, T&P carrier etc. required for proper completion of work as per RESPO Norms/Estimate of the work.
ST Pole 11 Meter Long
ST Pole 09 Meter Long
Distribution Box with Clamp
Earthing of Pole
Stay Set Complete
11 KV XLPE Cable 3x185sq.mm. (Underground)
ACSR Dog Conductor
ABC Cable 3x120+1x95+1x16 sq.mm.
11 KV TPMO
11 KV Fuse Set
L.T. PVC Cable 3.5x150 mm.
11 KV Pin Insulator
11 KV Pin with Nut
11KV Disk Insulator
11KV Disk fitting
Supply, fixing and erection of following materials as per site requirement as per RESPO Norms:-
Stone Pad
ABC Connector 120mm
Suspention Clamp with I Hook
Deadend Clamp with I Hook
11 KV cable Jointing Kit 3x185sq.mm.
160 mm. ODPN-4PE-80 grade uv stabliyed HDPE
Cross Bracing Angle
Top Channel
Dropper Channel
F Braket
11 KV Tee off Chennal
Base Angle
GI Pile 6" Dia
Pole Clamp
Danger Board with Clamp
Barbed wire
Aluminum winding wire
Aluminum Paint
Red Oxide Paint
Nut Bolt & Washer
AL Leg long Barrel
Number Plate with clamp
Road Restroration (Pacca Road)
After opening of HT & LT Connections, dismantalling of 250 KVA KVA Distribution Transformer from double pole and its safe carriage from respective site to other site including loading & unloading at both ends and also mounting on double pole including proper jumpering from 11 KV line to the transformer and also connecting the LT site cables as per RESSPO Manual.
Construction of plinth at various 11/0.4 KV Sub-station suitable for distribution transformer having size 5’x 5’ x 5’ out which 2’ below the ground. Work will include digging of foundation 2’ deep & brick work with Ist class bricks having cement and sand mortar of ratio 1:6 on all the walls, each of 9” thickness. The area inside the wall shall be duly filled by mud up to the height of appropriate level from ground level and shall be duly watered & rammed. Above the filling C.C. of ration 1:6:12 (Cement sand and brick ballast) giving 4” layer shall be provided. Above C.C. layer RCC layer having 4” thickness and with ratio 1:2:4 of cement sand and stone ballast shall be provided Re-enforcement shall be provided by providing net of (8 Nos. + 8 Nos.) M.S. rods of size 10 mm dia and each of 5’ length in the middle of the top of C.C. layer. The plinth shall be plastered with 12mm thick plaster in ratio 1:4 at all sides. This work will include cost of labour, T&P and all material required for construction of plinth which shall be provided by the contractor as per RESSPO Norms.
Neutral & body earthing of Distribution Transformer installed at various 11/0.4 kV Sub-stations by digging of pit upto water level depth (approx. 125 feet) and then inserting 1-¼” dia GI pipe of ‘A’ grade, conforming to the requirement of IS specification and then connecting the top of the inserted pipe and transformer body through GI strip of size 40x6 mm with the help of nut and bolt or through gas welding, as per direction of supervising engineer. It includes the cost of all material labour, T&P, carrier etc. required for proper completion of work. The aforesaid work shall be carried out as per RESSPO norms.
Dismantling and removal of following material from the existing line and then stacking in the respective JE’s (Store) as per direction of Supervising Engineer. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work.
Dismentling of old and used ST Pole
Dismentling of old and used Iron Scrap
Dismentling of Dog Conductor
KHAN ENTERPRISES
D N S ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .