| Sl No | Description | Qty | Unit | POOJA ENGINEERING L1 | PNAT CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation in all soils with initial lead and lift excepting all kinds of rock dumping the excavated materials away from work site manually within 50m initial lead and initial lift etc. complete as per direction of departmental officers. | 74 | M3 | 97.86 ₹7,241.64 Lowest | 98.88 ₹7,317.12 |
| 2.00 | Cement concrete 1:4:8 mix (one cement, four sand and eight aggregate) using 40mm hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted etc., complete complying with standard specification. | 74 | M3 | 5,041.99 ₹3,73,107.26 Lowest | 5,094.53 ₹3,76,995.22 |
| 3.00 | Supplying and erecting Shuttering including necessary supports for plane surfaces etc, using mild steel sheets and BG 10 stiffened with welded mild steel angles for boarding supported by Casuarinas props at suitable intervals etc., complete complying with standard specification and as directed. | 16 | M2 | 1,215.56 ₹19,448.96 Lowest | 1,228.22 ₹19,651.52 |
| 4.00 | Cement concrete 1:2:4 (one cement, two sand and three aggregate) using 20mm hard broken granite stone jelly for All RCC items of work excluding centering, shuttering, and cost of reinforcement grill but including curing finishing, vibrator charges etc., complete and also including fixing fan clamps and fixtures in RCC works wherever necessary as directed by departmental officer etc., complete. | 48 | M3 | 7,938.28 ₹3,81,037.44 Lowest | 8,020.99 ₹3,85,007.52 |
| 5.00 | Conveying the excavated earth from the site to the distance of 15kms out side of the city limit including all initial lead, lift, loading and unloading with transportation charges etc complete as per the direction of departmental officers. | 74 | M3 | 155.34 ₹11,495.16 Lowest | 155.34 ₹11,495.16 Lowest |
| 6.00Add :- GST @ 18% | |||||
Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
30 Jul 2024, 3:00 pmClosed
Assistant Commissioner,Coimbatore Corporation
Assistant Commissioner, East Zone, Coimbatore Corporation, Coimbatore
Providing Cement Concrete Pavement at Ward Area in ward No 6, East Zone.
2024_MAWS_466224_34
E4-2024-Eastzone
Open Tender
Civil Works - Roads
Works
90 days
Coimbatore Corporation, East Zone
As per Tender Condition
4 documents required · 4 mandatory
₹0
₹10,000
25 Feb 2026
27 Jul 2024
31 Jul 2024
27 Jul 2024
30 Jul 2024
27 Jul 2024
Amount
Earth work excavation in all soils with initial lead and lift excepting all kinds of rock dumping the excavated materials away from work site manually within 50m initial lead and initial lift etc. complete as per direction of departmental officers.
Cement concrete 1:4:8 mix (one cement, four sand and eight aggregate) using 40mm hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted etc., complete complying with standard specification.
Supplying and erecting Shuttering including necessary supports for plane surfaces etc, using mild steel sheets and BG 10 stiffened with welded mild steel angles for boarding supported by Casuarinas props at suitable intervals etc., complete complying with standard specification and as directed.
Cement concrete 1:2:4 (one cement, two sand and three aggregate) using 20mm hard broken granite stone jelly for All RCC items of work excluding centering, shuttering, and cost of reinforcement grill but including curing finishing, vibrator charges etc., complete and also including fixing fan clamps and fixtures in RCC works wherever necessary as directed by departmental officer etc., complete.
Conveying the excavated earth from the site to the distance of 15kms out side of the city limit including all initial lead, lift, loading and unloading with transportation charges etc complete as per the direction of departmental officers.
Add :- GST @ 18%
PNAT CONSTRUCTIONS (BID ID -1094394)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .