| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹30.5 CrAccepted-AOC | ₹30.5 Cr | L1 | Accepted-AOC Due to lowest bid price |
| 2 | L2₹31.5 CrRejected-Finance | ₹31.5 Cr | L2 | Rejected-Finance Due to high bid price |
| 3 | L3₹31.5 CrRejected-Finance DIRBA MANDI | ₹31.5 Cr | L3 | Rejected-Finance Due to high bid price |
| 4 | L4₹31.8 CrRejected-Finance KACHA PAHA PREET NAGAR ST NO 2 WARD NO 8 SUNAM DISTRICT SANGRUR PB | ₹31.8 Cr | L4 | Rejected-Finance Due to high bid price |
| 5 | L5₹32.0 CrRejected-Finance 1586 LAKHI COLONY ST NO 1 NEAR MANIA HEALTH CENTRE BARNALA | BARNALA | PUNJAB | 148100 | ₹32.0 Cr | L5 | Rejected-Finance Due to high bid price |
Tender Value
₹34.8 Cr
EMD Value
₹69.6 L
Closing Date
28 Jan 2026, 12:00 pmClosed
Executive Engineer
Provincial Division PWD BandR DAC Complex Sangrur
Modernization of various Link roads under Special Central Assis. Scheme Phase 2 in AC Dirba and Lehra Group 4 including 5 year maintenance
2026_CEPW_157863_1
Bid No 84 Dt. 14-01-2026
Open Tender
Civil Works - Roads
365 days
Sangrur
Please refer Tender documents.
6 documents required · 6 mandatory
₹50,000
₹69.6 L
Yes
Sangrur
28 Feb 2026
15 Jan 2026
28 Jan 2026
15 Jan 2026
28 Jan 2026
15 Jan 2026
23 Jan 2026
Select, At Par, Excess (+), Less (-) IOCL
Tender Inviting Authority: EXECUTIVE ENGINEER, Provincial Division PWD B&R Sangrur
Name of Work: Moderization of various link roads under Special Central Assistance (Phase-II) Scheme in Assembly Constituency Dirba & Lehra (G-IV) Including Maintenance of Road for 5 Year (One year Defects Liability Period + Four Year Maintenance Period)
Name of the Bidder/ Bidding Firm / Company :
Sl. No. Work Name Item Code / Make Quantity Unit Rate Rs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT in Rs. P TOTAL AMOUNT With Taxes TOTAL AMOUNT In Words
Excavation in Soil (any type) using Hydraulic Excavator CK 90 Excavation with hydraulic excavator of 0.9 cum bucket capacity including cutting trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, including all lift and combined lead up to 60 mtr. Cum. Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Construction of embankment with good quality earth obtained from borrow pits including compensation of earth, loading, unloading, carriage to site of work, spreading, grading to required slope and compacting to meet requirement of table 300-2 as per technical clause 305 of MORT&H specifications. Cum. Excess(+) Full Conversion INR INR One Crore Twelve Lakh Eighty Four Thousand Two Hundred & Five Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Relaying of Construction of embankment with earth obtained from roadway cutting or excavation including spreading, grading to required slope and compacting to meet requirement of table 300-2 as per technical clause 305 of MORT&H specifications CSR Item No.24.5 b Cum Excess(+) Full Conversion INR INR Eight Lakh Sixty Two Thousand Three Hundred & Eleven Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Compaction of earth work & Preparation of sub grade including loosening, leveling of earth 225mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 300-2 as per Technical clause 305 of MORT&H specifications. (In case of link roads earth work to be done by villagers) Sqm. Excess(+) Full Conversion INR INR Four Lakh Eighty One Thousand Nine Hundred & Forty Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Dismantling of exisiting road crust taking it as solling as per complete in all respects as per PWD Specification Cum. Excess(+) Full Conversion INR INR Eighteen Lakh Twenty Seven Thousand Four Hundred & Sixty Nine Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Dismetling of Brick Edgning in all respects as per PWD Specification Cum. Excess(+) Full Conversion INR INR One Lakh Ninety Eight Thousand Seven Hundred & Ninety Seven Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Credit of brick bats Cum. Excess(+) Full Conversion INR INR Minus Three Lakh Sixty Five Thousand Seven Hundred & Five Only
Credit of bricks Nos Excess(+) Full Conversion INR INR Minus Five Lakh Twenty One Thousand Six Hundred & Forty Two Only
Making 50 mm x 50 mm furrows 45 degree to the center line of the road and at one metre interval in the existing bituminous wearing coarse including sweeping and disposal of excavated material within 1000 metres lead complete as per technical clause 404 of MORT&H specifications (Full surface area will be measured for payment) Sqm. Excess(+) Full Conversion INR INR Five Lakh Two Hundred & Eighty Eight Only
Providing and laying of Brick on end edging 6.83cm wide, 11.11cm long and 22.86cm high half brick deep including excavation, refilling and disposal of surplus earth up to 50mtr complete as per Punjab PWD specifications Mtr Excess(+) Full Conversion INR INR Eighty Two Lakh Forty One Thousand Nine Hundred & Twenty Two Only
Construction of granular sub-base by providing material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per MORD technical specifications (CSR 24.7) Cum. Excess(+) Full Conversion INR INR One Crore Ninety Three Lakh Thirteen Thousand Eight Hundred & Ninety Nine Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Relaying of recovered material obtained from dismantling of road crust as construction of granular sub-base by providing coarse graded matereal grading-II spreading in uniform layers with motor grader on prepared surface, mixing by mix by mix in place method with rotavator at OMC, and compacting with vibratory roller to achive the desired density, complete as per technical clause 401 o MORT&H specifications (CSR Item No.24.7 Labour rate) Cum. Excess(+) Full Conversion INR INR Six Lakh Eight Thousand Nine Hundred & Sixty Nine Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Water Bound Macadam Grading II (without screening for low volume Roads / undersigned Roads:- Providing, laying, spreading and compacting stone aggregates of Grading II to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical specifications Cum. Excess(+) Full Conversion INR INR Six Crore Eighty Nine Lakh Seventeen Thousand One Hundred & Fifty Four Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Water Bound Macadam Grading III (without screening for low volume Roads / undersigned Roads:- Providing, laying, spreading and compacting stone aggregates of Grading III to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical specifications Cum. Excess(+) Full Conversion INR INR Four Crore Twenty Nine Lakh Forty Six Thousand &Twenty Seven Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Providing and laying surface dressing in single coat using crushed stone aggregates of specified size on a layer of bituminous binder VG-10 @ 1kg per sqm laid on prepared surface after cleaning the road surface and rolling with 8-10 tonne smooth wheeled steel roller complete as per technical clause 509 of MORT&H specifications Sqm. Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Providing and applying tack coat with penetration grade bitumen VG-10 using bitumen pressure distributor at the rate of 0.40 kg per sqm on the prepared bituminous surface/granular surface treated with prime coat after cleaning the surface complete as per technical specifications Sqm. Excess(+) Full Conversion INR INR Fifty Seven Lakh Seventy Thousand &Ninety Two Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Providing and laying bituminous concrete 30mm to 45mm thick with batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30 @ 5.4%, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction complete as per technical clause 507 of MORT&H specifications NOTES:- (i) Job mix formula for the bituminous concrete shall be provided by the agency and shall be got approved from Punjab PWD, B&R Research laboratory Patiala before adoption at site for execution. (ii) The specifications of this item for analytic purpose is kept with bitumen content @ 5.4% weight of mix variation as compared with job mix formula shall be paid/ deducted accordingly. The limits of variations shall be worked out with the approved formula. TECHNICAL NOTE:- i.) Apart from the conformity with the grading and quantity requirement of individual ingredients exhibited above the mix aggregate i.e. coarse and fine aggregate for bituminous concrete shall meet all requirements set forth clause 507 of MORT&H specifications. ii.) The final grading for the aggregates required for bituminous concrete confirming to table 500.17 of MORT&H specifications shall be determined after getting the bituminous concrete designed from Punjab PWD, B&R Research Laboratory Patiala after obtaining 60% of material. The design mix so finally approved shall be termed as the approved mix. The aggregates shall be hydrophobic and of low porosity. The aggregates shall satisfy the physical requirement set forth in table 500-6 (addendum to latest revision). iii.) The approved mix shall exhibit the following details, source and location of all material:- (a) Binder expressed as percentage by weight of total mix. (b) Course expressed as percentage by weight of total mix. (c) Crushed bajri expressed as percentage by weight of total mix. (d) Fine aggregate expressed as percentage by weight of total mix. (e) A single definite percentage passing each sieve for mixed aggregates (f) Density of bituminous concrete after compaction will be not less than 2.35 gm/CC. Cum. Excess(+) Full Conversion INR INR Eleven Crore Forty Seven Lakh Twenty Thousand Three Hundred & Eighty Eight Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Road marking with hot applied thermoplastic compound 2.5mm thick including reflectorising glass beads @ 0.25kg per sqm area as per IRC:35 1997 complete as per technical clause 803 of MORT&H specifications Complete as per CSR Item No 24.57 Sqm. Excess(+) Full Conversion INR INR Seventy Four Lakh Twenty Two Thousand Two Hundred & Ten Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M-35 grade machine made rubber moulded smooth finish with strong vibratory process or with vibrohydraulic compaction machine and of approved size and design / shape laid in Ordinary Grey and pattern over and including 40 mm thick compacted bed of coarse sand, filling the joints with fine sand etc, all complete as per directions of Engineer-in-Charge for Non traffic Areas and streets having width less than 3.05 mt.( Also not to used over footoaths) Sqm. Excess(+) Full Conversion INR INR Seventeen Lakh Ninety Seven Thousand Nine Hundred & Eighty Three Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Supplying and fixing of single mould twin shank reflective road studs made out of poly carbonate/ABS moulded body and reflective panels with micro prismatic lens or Glass Beeds capable of providing total internal reflection of the light entering the lens face with retro reflectance and chromaticity values shall be as given in the detailed specifications and the product shall conform to ASTM D4280. The raised pavement marker shall also meet all the testing conditions of ASTM D4280 and fixed to the road surface using the adhesive. Two cylindrical Polymer Shanks of not less than 20 mm diameter and not less than 30 mm length shall be molded in the RPM body. The marker shall support a load of 13635 Kg tested in accordance with ASTM D4280. The marker shall withstand flexural strength of 909 kgf force in accordance with ASTM D4280. Marker lenses shall be moulded of Polycarbonate or methyl methecrylate conforming to ASTM D788. The supplier shall provide a 2 years warranty for satisfactory field performance as per clause 804.7.3 of MORT&H 5th revision specifications. Nos Excess(+) Full Conversion INR INR Twenty Five Lakh Sixty Two Thousand Eight Hundred & Seventy Nine Only
Providing and making rumble strips 15-20mm high at centre, 250mm wide placed at 1m centre to centre over freshly laid bituminous layer by using close graded premix surfacing material type B at locations to control speed and marked with 100mm wide white strips of thermoplastic road marking paint. The close graded premix surfacing material type B shall conform to technical clause 512 and thermoplastic road marking paint shall conform to technical clause 803 to MORT&H specifications as per CSR 24.60 a Mtr Excess(+) Full Conversion INR INR Forty Seven Thousand Nine Hundred & Sixty Four Only
Reinforced cement concrete M-15 grade ordinary kilometer stone of standard design for village roads as per IRC 8-1980 fixing in position including painting and printing etc. complete as per technical clause 804 of MORT&H specifications CSR 24.37 c Each Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Reinforced cement concrete M-15 grade boundary pillars of standard design as per IRC 25-1967 fixing in position including painting and printing etc. complete as per technical clause 806 of MORT&H specifications CSR 24.39 Each Excess(+) Full Conversion INR INR Four Lakh Eighty Six Thousand Nine Hundred & Ninety Six Only
Reinforced cement concrete M-15 grade village board of standard design fixing in position including painting and printing etc. complete as per PWD specifications CSR 24.40 Each Excess(+) Full Conversion INR INR One Lakh Sixty Four Thousand Nine Hundred & Forty Nine Only
Reinforced cement concrete M-15 grade 200 meter stone of standard design as per IRC 26- 1967 fixing in position including painting and printing etc. complete as per technical clause 804 of MORT&H specifications CSR 24.38 Each Excess(+) Full Conversion INR INR One Lakh Fifteen Thousand Eight Hundred & Sixty One Only
Construction of Cross Drain Type-A as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Each Excess(+) Full Conversion INR INR Eleven Lakh Ninety Nine Thousand Nine Hundred & Seventy Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Construction of 1.5' dia HPC as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Each Excess(+) Full Conversion INR INR Eighteen Lakh Four Thousand Two Hundred & Sixty Four Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Construction of 3 M Span Slab Type Culvert as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Each Excess(+) Full Conversion INR INR Twelve Lakh Ninety Thousand Nine Hundred & Eighty Six Only
Construction of 1.5 M Span Slab Type Culvert as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Each Excess(+) Full Conversion INR INR Three Lakh Sixty Nine Thousand Seven Hundred & Thirty One Only
Construction of 4.5' Retaining Wall as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Mtr Excess(+) Full Conversion INR INR Fifty Four Lakh Eighty Eight Thousand &Thirty One Only 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
Construction of side drain as per design provided by Engineer-in-charge complete in all respect as per PWD specifications. Mtr Excess(+) Full Conversion INR INR Fifty Two Lakh Sixty Five Thousand Five Hundred & Thirty Only
Videography of Road. Each Excess(+) Full Conversion INR INR Eight Thousand Only
Heritage & Culture Cess @ 1.00% percent Excess(+) Full Conversion INR INR Thirty Two Lakh Forty Seven Thousand Nine Hundred & Forty Seven and Paise Forty Four Only
Cancer Cess @ 1.00% percent Excess(+) Full Conversion INR INR Thirty Two Lakh Forty Seven Thousand Nine Hundred & Forty Seven and Paise Forty Four Only
Maintenance:- 1 Construction of chamber for 100mm sluices valve item1 10 1 Nos
Routine Maintenance after completion of Construction work as per periodicity to routine maintenance mentioned in the technical specifications. For 2nd Year Km Full Conversion INR INR Twenty Four Lakh Thirty Seven Thousand Three Hundred & Ninety Six Only
Routine Maintenance after completion of Construction work as per periodicity to routine maintenance mentioned in the technical specifications. For 3rd Year Km Full Conversion INR INR Thirty Lakh Sixty Six Thousand Four Hundred & Eighty Two Only
Routine Maintenance after completion of Construction work as per periodicity to routine maintenance mentioned in the technical specifications. For 4th Year Km Full Conversion INR INR Fifty Lakh Forty Thousand Nine Hundred & Twenty Nine Only
Routine Maintenance after completion of Construction work as per periodicity to routine maintenance mentioned in the technical specifications. For 5th Year Km Full Conversion INR INR Sixty One Lakh Eighteen Thousand Four Hundred & Sixty Eight Only
Heritage & Culture Cess @ 1.00% percent Excess(+) Full Conversion INR INR One Lakh Sixty Six Thousand Six Hundred & Thirty Two and Paise Seventy Five Only
Total in Figures INR Thirty Three Crore Twelve Lakh Ninety Thousand Six Hundred & Thirty Eight and Paise Eighty Eight Only 4 Construction of chamber for 100mm sluice plates item5 10 Nos
Quoted Rate in Figures Select INR One Crore Sixty Eight Lakh Twenty Nine Thousand Nine Hundred & Seven and Paise Seventy Five Only
Quoted Rate in Words INR One Crore Sixty Eight Lakh Twenty Nine Thousand Nine Hundred & Seven and Paise Seventy Five Only
Please Enable Macros to View BoQ information
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
BOQ_320134.xls
BOQ • 0.33 MB
SBDDirbaLehraGroup4.pdf
Tender Documents • 11.01 MB
Download all tender documents and submit your bid