Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹1.3 Cr+₹5.0 L (4.11%)Admitted-Finance 04 L BLOCK MARKET SECTOR 11 NOIDA 201301 UP GAUTAM BUDHA NAGAR | GAUTAM BUDDHA NAGAR | UTTAR PRADESH | 201301 | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | GEPS PROJECTS L2 | M/S Ravi Electrical L1 |
|---|---|---|---|---|---|
| 1.00 | Material & Labour for the fault diagnosis of a distribution transformer up to 1000 KVA by deployment of a qualified electrical team to perform the complete physical disconnection of all HT and LT cable terminations, including removal of the neutral and body earthing links to ensure total isolation for identify the fault with all necessary testing equipment and safety gear, specifically with a calibrated 5 kV digital megger, certified discharge rods for residual charge depletion, and personal protective equipment (PPE). The scope covers all consumables, such as lint-free cleaning cloths and contact cleaner (CRC) for bushing decontamination, followed by comprehensive insulation resistance (IR) testing between HV-LV, HV-Earth, and LV-Earth and to prepare detailed diagnostic report identifying the precise nature of the fault—such as winding insulation breakdown, moisture ingress, or internal short-circuiting for further course of action of department complete all as specified and directed. | 20 | Each Job | 4,500 ₹90,000 Lowest | 5,000 ₹1,00,000 |
| 2.00M&L for disconnecting all the electrical connections from H.T. and L.T. side of unserviceable transformer of follwoing capacity i.e. Jumpers/cable from the cable end box or bushings & earthing terminal of the transformers by removing the nuts bolts including taking down carefully of defective transformer from 2/4 pole structure/ platform mounted substation or AGE E/M store yard and transporting the same by loading, unloading of transformer & transportation by vehicle to workshop and opening the transformer cover, draining out of transformer oil, assembling, removing of the burnt parts ie. tape, paper insulating strings etc gently and carefully, washing of the dust, rust and dirt from all parts including taking out cooling tubes, welding and re-assembling after carrying out required repair including commissioning and testing and transporting back to site/MES store yard/ installation on existing 2/4 pole structure/ platform with necessary fixing arrengement including connecting up electrically, commissioning and testing all as directed by Engr- in- Charge for the following capaity of Transformer :- | |||||
| 2.01 | 63 to 315 KVA transformer | 10 | Each | 4,500 ₹45,000 Lowest | 14,000 ₹1,40,000 |
| 2.02 | 400 to 630 KVA transformer | 15 | Each | 6,000 ₹90,000 Lowest | 15,000 ₹2,25,000 |
| 2.03 | 1000 to 2000 KVA transformer | 4 | Each | 9,000 ₹36,000 Lowest | 16,000 ₹64,000 |
| 2.04NOTE :- (i) The contractor shall produce test certificate as per IS-2026 alongwith high voltage test from the firms after repair. (ii) To accertain the fault of transformer at installed location, the transformer will be tested with HT 10KV magger, multimeter in the presence of AGE E/M/JE E/M. All T&P required like HT magger 10KV, multimeter and cables will be arrenged by contractor. (iii) All the transformer shall be opened in presence of Engr- in- Charge/ his rep veryfy the various repairs/replacement involved and the transformer shall be assembled in the presence of Engr- in- Charge/his rep after necessary repairs/replacement. (iv) All the transformer shall be tested in the factory in the presence of Engr- in- Charge/ his rep, as per ser note No 1 above and also in addition the transformer where specified to be installed and commissioned on the 2/4 pole structure, platform and also shall be tested by the contractor in the presence of Engr- in- Charge.(v) All the testing arrangement shall be provided by the contractor without any extra payment. (vi) The contractor shall also furnished a guarantee certificate himself for rectification of the defects. If any noticed defect during liability period for 01 year from the certified date of completion.(vii) The above shall however does not absolve the responsibility of the contractor for rectification of any defect, if any noticed during guarantee period of 01 year as per condition 46 of IAFW-2249 and the contractor shall be solely responsible for entire completion of work and for rectification of the defect/replacement of items/parts and required pointed out by the GE during defect liability period of 01 year. Payment only for dehydration of the transformer oil and painting of the transformers | |||||
| 2.05replacement of certain items considered separately here- in- after shall only be made for separately all other minor repair/replacement as required and ordered by the Engr- in- Charge for entire completion of work shall be deemed to be included in the unit rate of the above items. (viii) The contractor shall also clear the breathers. The unit rate quoted by the contractor shall included this aspect also. (ix) Contractor shall provide all arrangement for carefully handling/conveyance of/ transportation of equipment by means of crane/chain pully/recovery van and vehicles as per requirements and directed by Enge- in- Charge. (xi) The rate quoted by contractor shall include all these aspect from (i) to (x) while quoting his tender that quoted rate also include the provision of providing electric connection to exisiting system. (x) Transformer oil tank rubberised 6.0mm thick gasket sheet pasted using gasket cement, oil level gauge, drain valve, painting inner side tank by zinc chromate paint and outer side by approved paint include in this item rate. | |||||
| 3.00 | M&L for shifting of transformer of capacity 63 to 2000 KVA from existing PCC platform/ four pole/two pole structure/MES store yard and fixing on platform/four pole/two pole structure at other location by suitable capacity of crane including necessary connection on HT & LT side and testing on completion complete all as specified and directed. | 15 | Each | 9,000 ₹1,35,000 | 5,000 ₹75,000 Lowest |
| 4.00Segregation of HT/LT leg coil from transformer and making new HT/LT leg coil with insulating copper wire of required gauge, craft paper, cotton tape HT/LT insulation as per IS specification of old transformer including ovening & heating after marking of coil as required of following capacity :- | |||||
| 4.01 | HT leg Coil copper | 3,500 | Kg | 1,215 ₹42,52,500 | 1,000 ₹35,00,000 Lowest |
Tender Value
₹75 L
EMD Value
₹1.4 L
Closing Date
2 Sept 2026, 6:00 pmClosed
HQ CWE Meerut
29J The Mall Road Meerut Cantt Uttar Pradesh 250001
REPAIR/MAINTENANCE OF TRANSFORMER INCLUDING ALLIED WORKS IN NORTH AREA OF AGE E/M (ES) UNDER GE (U) MEERUT CANTT
2026_MES_780609_1
94383/MRT/2026-27/E8
Open Tender
Civil Works
Item Rate
180 days
MEERUT CANTT
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,000
GE (U) MEERUT
₹1.4 L
Yes
15 Sept 2026
24 Jul 2026
8 Sept 2026
24 Jul 2026
2 Sept 2026
14 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Material & Labour for the fault diagnosis of a distribution transformer up to 1000 KVA by deployment of a qualified electrical team to perform the complete physical disconnection of all HT and LT cable terminations, including removal of the neutral and body earthing links to ensure total isolation for identify the fault with all necessary testing equipment and safety gear, specifically with a calibrated 5 kV digital megger, certified discharge rods for residual charge depletion, and personal protective equipment (PPE). The scope covers all consumables, such as lint-free cleaning cloths and contact cleaner (CRC) for bushing decontamination, followed by comprehensive insulation resistance (IR) testing between HV-LV, HV-Earth, and LV-Earth and to prepare detailed diagnostic report identifying the precise nature of the fault—such as winding insulation breakdown, moisture ingress, or internal short-circuiting for further course of action of department complete all as specified and directed. | 20 | Each Job | - | - |
| 2M&L for disconnecting all the electrical connections from H.T. and L.T. side of unserviceable transformer of follwoing capacity i.e. Jumpers/cable from the cable end box or bushings & earthing terminal of the transformers by removing the nuts bolts including taking down carefully of defective transformer from 2/4 pole structure/ platform mounted substation or AGE E/M store yard and transporting the same by loading, unloading of transformer & transportation by vehicle to workshop and opening the transformer cover, draining out of transformer oil, assembling, removing of the burnt parts ie. tape, paper insulating strings etc gently and carefully, washing of the dust, rust and dirt from all parts including taking out cooling tubes, welding and re-assembling after carrying out required repair including commissioning and testing and transporting back to site/MES store yard/ installation on existing 2/4 pole structure/ platform with necessary fixing arrengement including connecting up electrically, commissioning and testing all as directed by Engr- in- Charge for the following capaity of Transformer :- | |||||
| 2.01 | 63 to 315 KVA transformer | 10 | Each | - | - |
| 2.02 | 400 to 630 KVA transformer | 15 | Each | - | - |
| 2.03 | 1000 to 2000 KVA transformer | 4 | Each | - | - |
| 2.05 | replacement of certain items considered separately here- in- after shall only be made for separately all other minor repair/replacement as required and ordered by the Engr- in- Charge for entire completion of work shall be deemed to be included in the unit rate of the above items.
(viii) The contractor shall also clear the breathers. The unit rate quoted by the contractor shall included this aspect also.
(ix) Contractor shall provide all arrangement for carefully handling/conveyance of/ transportation of equipment by means of crane/chain pully/recovery van and vehicles as per requirements and directed by Enge- in- Charge.
(xi) The rate quoted by contractor shall include all these aspect from (i) to (x) while quoting his tender that quoted rate also include the provision of providing electric connection to exisiting system.
(x) Transformer oil tank rubberised 6.0mm thick gasket sheet pasted using gasket cement, oil level gauge, drain valve, painting inner side tank by zinc chromate paint and outer side by approved paint include in this item rate. | - | - | - | - |
| 3 | M&L for shifting of transformer of capacity 63 to 2000 KVA from existing PCC platform/ four pole/two pole structure/MES store yard and fixing on platform/four pole/two pole structure at other location by suitable capacity of crane including necessary connection on HT & LT side and testing on completion complete all as specified and directed. | 15 | Each | - | - |
| 4Segregation of HT/LT leg coil from transformer and making new HT/LT leg coil with insulating copper wire of required gauge, craft paper, cotton tape HT/LT insulation as per IS specification of old transformer including ovening & heating after marking of coil as required of following capacity :- | |||||
| 4.01 | HT leg Coil copper | 3,500 | Kg | - | - |
| 4.02 | LT Coil copper | 3,850 | Kg | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.26 MB
TD3.pdf
Tender Documents • 0.24 MB
TD1.pdf
Tender Documents • 0.38 MB
TD2.pdf
Tender Documents • 0.22 MB
TD4.pdf
Tender Documents • 0.57 MB
BOQ_874417.xls
BOQ • 3.48 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .