| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.8 LAdmitted-Finance | -35.83% | ₹3.8 L | L1 | Admitted-Finance |
| 2 | L2₹3.8 LAdmitted-Finance | -35.10% | ₹3.8 L | L2 | Admitted-Finance |
| 3 | L3₹4.0 LAdmitted-Finance | -32.20% | ₹4.0 L | L3 | Admitted-Finance |
| 4 | L4₹4.1 LAdmitted-Finance | -30.60% | ₹4.1 L | L4 | Admitted-Finance |
| 5 | L5₹4.1 LAdmitted-Finance | -30.30% | ₹4.1 L | L5 | Admitted-Finance |
Tender Value
₹5.9 L
EMD Value
₹11,760
Closing Date
21 Aug 2026, 6:00 pmClosed
Executive Engineer
XEN
As BOQ
2026_RDPR_320048_15
57 REW Samba of 2026-27 Dated-08-08-2026
Open Tender
Civil Works
Percentage
30 days
Bari Brahmana
Please refer Tender documents.
3 documents required · 3 mandatory
₹600
Executve Engineer Rew Samba
₹11,760
25 Aug 2026
10 Aug 2026
22 Aug 2026
10 Aug 2026
21 Aug 2026
10 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation trenches including dressing of sides and ramming of bottoms, lift upto 1.5m including getting out the excavated soil and disposal of surplus excavated soil 1m from cutting edge. | 33.96 | cum | 479.3 | ₹16,277.03 |
| 2 | Providing and Laying in position cement concrete of specified grade excluding the cost of centring and shuttering – All work upto plinth level 1: 5: 10: ( 1: cement 5: coarse sand : 10 graded crushed stone aggregate 40mm nominal size | 5.66 | cum | 4,826.5 | ₹27,317.99 |
| 3 | Providing and Laying in position cement concrete of specified grade excluding the cost of centring and shuttering – All work upto plinth level 1: 3: 6: ( 1: cement 3: coarse sand : 6 graded crushed stone aggregate 20mm nominal size | 34.87 | cum | 5,733.6 | ₹1,99,930.63 |
| 4 | Dumping of Stone all Lifts and Lead. Complete | 10.41 | cum | 700 | ₹7,287 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form work for:
Foundations, footings, bases for columns | 97.5 | sqm | 286.35 | ₹27,919.13 |
| 6 | Brick work with FPS bricks of class designation 75 in foundation and plinth in 1 cement: 6 fine sand mortar | 20.16 | cum | 7,571.55 | ₹1,52,642.45 |
| 7 | Extra for brick work in superstructure above plinth level upto floor V level. | 20.16 | cum | 1,455.65 | ₹29,345.9 |
| 8 | 12mm thick cement plaster of 1cement:6 fine sand mix: Sarpanch room, Pantry, Secy room, meeting hall, computer room, corridor, toilet, ver./entrance, deductions, Toilet D, Window W | 114.7 | sqm | 266.2 | ₹30,533.14 |
| 9 | 15 mm thick cement plaster of 1 cement: 6 fine sand mix: Externally, Window W, V | 114.7 | sqm | 306.85 | ₹35,195.7 |
| 10 | Engaging Labour for Dismantling, shifting & fixing of Old Gate | 6 | no | 550 | ₹3,300 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.95 MB
BOQ_1063553.xls
BOQ • 0.26 MB
5777.pdf
PDF • 0.51 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].