Tender Value
₹10.0 L
EMD Value
₹99,968
Closing Date
21 Sept 2026, 3:00 pmClosed
chief engineer
Nirman Vibhag Nagar Nigam Saharanpur
Work of maintance transformar wale park for jatav nagar at ward no. 07
2026_NNSAH_1183467_1
6198 B
Open Tender
Civil Works
Percentage
45 days
Saharanpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹826
₹99,968
9 Sept 2026
9 Sept 2026
22 Sept 2026
9 Sept 2026
21 Sept 2026
9 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismenteling of interloking tiles work including labour T&P etc all complete | 142.5 | sqm | 38 | ₹5,415 |
| 2 | Dismenteling of brick work including labour T&P etc all complete | 9.66 | cum | 400 | ₹3,864 |
| 3 | Deduction of old brick bats | 1,555.26 | no | 5.8 | ₹9,020.51 |
| 4 | Deduction of brick bats | 6.28 | m3 | 800 | ₹5,024 |
| 5 | Excavation in foundation in ordinary soil (Loam, clay or sand) Including lift upto 1.50 M and lead upto 30 M and including filing watering and rammind of excacated earth into the treaches or into the space between the building and the sides of foundation trenchs or into the plinth and removal and disposal of surplus earth as directed by the engineer in charge upto a distance of 30 M from the foundation trenches SOR UP PWD S1-251A) | 44.8 | m3 | 90 | ₹4,032 |
| 6 | Disposal of malwa upto 5km including loading and unloading labour T&P etc in all work complete. | 21.5 | m3 | 130 | ₹2,795 |
| 7 | Concrete with 4 cm gauge brick ballast fine sand and cement in proportion are 1:6:12 in foundation and under floors, including supply of all materials, labour. T&P etc. required for proper completion the work | 19.85 | m3 | 2,985 | ₹59,252.25 |
| 8 | M-150 Brick work in 1:6 one cement and four course sand, mortar in foundation in plinth including supply of all material labour, T &P etc. required for proper completion of the work. | 21.74 | m3 | 4,090 | ₹88,916.6 |
| 9 | 2.50 cm. thick DPC with 1:1.5:3 with 10mm Stone grite inclding labour T&P etc all complete | 24.5 | m3 | 320 | ₹7,840 |
| 10 | M-150 Brick work in 1:4 one cement and four course sand, mortar in foundation in plinth including supply of all material labour, T &P etc. required for proper completion of the work. | 35.9 | m3 | 4,520 | ₹1,62,268 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 8.23 MB
BOQ_2225802.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .