Tender Value
Refer Docs
EMD Value
₹4.1 L
Closing Date
20 Oct 2026, 11:00 am
Executive Engineer
Office of the EE PWD NH Division Barmer
Short Term Maintenance Contract of NH168A from Km. 0.00 To Km. 11.800 (Length 11.80 Km) in state of Rajasthan.
2026_MoRTH_927954_2
EE NH BMR NIT 03/2026-27 Sr. 1 to 3
Open Tender
Civil Works - Highways
Percentage
270 days
Sanchore
GST Registration, EDM, POA, Tender Fee and as per Bidding Documents
2 documents required · 2 mandatory
₹10,000
RPAO MoRTH Jaipur
₹4.1 L
Office of the Executive Engineer PWD NH Division B
28 Sept 2026
28 Sept 2026
21 Oct 2026
28 Sept 2026
20 Oct 2026
28 Sept 2026
28 Sept 2026 - 8 Oct 2026
12 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Stripping excess soil from the shoulder surface including disposal of excess earth side slopes to achieve the approved level and compacting with plate compactor up to 75mm average depth complete as per MoRTH specification clause 3003. | 70,800 | Sqm | 12.71 | ₹8,99,868 |
| 2 | Restoration of rain cuts with soil, Morrum, gravel or a mixtureof these includingall leads and lifts and cost of arrangement of land, clearing the loosesoil, benching for 300mmwidth, laying fresh material in layers not exceeding 250mm and compacting with plate compactor or power rammer to restore theoriginal alignment levels & slopes complete as per MoRTH specification Clause 3002. | 6,000 | Cum | 118.64 | ₹7,11,840 |
| 3 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material up to a lead of 1000m including removal and disposal of top organic soil not exceeding in 150 mm thickness as per MoRTH specification clause 201 By mechanical Means. In area of light jungle. (Twice in a year) | 5.9 | Hect. | 28,394.92 | ₹1,67,530.03 |
| 4 | Clearing slab/box type culvert and pipe culvert including clearing, cleaning and reshaping of upstream and downstream phases of these culvert with in right of way. The job includes disposal of excess material recovered from site including vegetation outside ROW with all leads and lifts complete in all respects as per direction in charge (frequency of cleaning will be one time in a year i.e. before start of mansoon).
Slab/pipe culvert | 37 | Nos | 1,461.86 | ₹54,088.82 |
| 5 | Repair of pot holes by Wet Mix Macadam material by removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, compacting base of excavation as per clause 503, back filling the pot holes with wet mix macadam material by manual means as per clause 406, compacting with roller 8-10T, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004. | 3,400 | Cum | 1,217.8 | ₹41,40,520 |
| 6 | Filling pot-holes and patch repairs with bituminous concrete, 40 mm with removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per Clause 503 back filling the pot holes with hot bituminous material using 60/70 grade bitumen @ 5.0% of total mix & mixed in hot mix plant 40-60 TPH capacity and carriage with all leads as per clause 509, compacting with smooth wheel roller 8-10 tonne, trimming & finishing the surface to form a smooth continuous surface, all as per MoRTH specification Clause 3004.2 | 8,900 | Sqm | 377.12 | ₹33,56,368 |
| 7 | Supply, placing and compacting readymade cold bituminous pothole patching mix in accordance with IRC : 116-2014 Specifications in 50 Kg Plastic - lined sturdy bags with 10 Km. average lead for supply and 20 Km average lead for placement. Mix Shall contain at least 5.6 % MC-800 Cut-back bitumen and suitable anti-stripping agent. Mix shall be workable and usable for at least 6 months. All 50 Kg. bags shall be transported to a storage facility designated by the Engineer. Since the mix contains volatile kerosene, sealed bags shall not be stored in a closed building or warehouse. No open flame or smoking shall be permitted near the stored mix. | 250 | Per 50 Kg Bag | 350 | ₹87,500 |
| 8Painting with superior grade enamel paint of approved quality to give an even shade including writing littering figuring etc. complete as per IRC standards of:- | |||||
| 8.1 | 5th Km. stone | 3 | Each | 200.85 | ₹602.55 |
| 8.2 | Km. Stone for ODR & MDR | 12 | Each | 127.12 | ₹1,525.44 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.58 MB
BOQ_975193.xls
BOQ • 0.30 MB
NIT03.pdf
Tender Documents • 0.57 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .