Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹79.4 LAccepted-AOC PLOT NO F AND G RAKBA DARAKHERA PROFESSOR COLONY NAGAR PARISAD THANESAR KURUKSHETRA HARYANA 136 118 | ₹79.4 L | 1 | Accepted-AOC ok |
| 2 | 2₹92.9 LRejected-AOC | ₹92.9 L | 2 | Rejected-AOC ok |
| 3 | 3₹96.7 LRejected-AOC | ₹96.7 L | 3 | Rejected-AOC ok |
| 4 | 4₹1.1 CrRejected-AOC | ₹1.1 Cr | 4 | Rejected-AOC ok |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹1.0 Cr
EMD Value
₹2.0 L
Closing Date
7 May 2026, 5:00 pmClosed
Harvinder Kumar
Electrical Hissar
Providing Grid Connected Roof Top Solar Power Plant without Battery Bank in Sewage Treatment Plant and Water Work at Jind.
2026_HBC_517085_1
20266F82D188 393F 4C19 9174 A7143F378C54246HSV
Open Tender
Electrical Works
Works
120 days
Jind
Providing Grid Connected Roof Top Solar Power Plant without Battery Bank in Sewage Treatment Plant and Water Work at Jind.
2 documents required · 2 mandatory
₹3,000
₹2.0 L
Yes
21 Aug 2026
23 Apr 2026
8 May 2026
23 Apr 2026
7 May 2026
23 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 32.70.2
Supply Installation testing commissioning of Solar Photovoltaic grid connected roof top Plant conforming to MNRE specifications as amended, consisting of Mono/Poly Crystalline silicon solar cells, net metering facility, necessary protections, earthing, mounted on Aluminium/GI structure of suitable strength with following components complete as required:-
(a) Solar Photovoltaic Module manufactured in India, conforming to IS 14286/IEC 61215, IS/IEC 61730-Part-1, IS/IEC 61730-Part-2. Solar Photovoltaic Module conversion efficiency shall not be less than 16.5%. PV modules used in solar power plants/ systems must be warranted for their output peak watt capacity, which should not be less than 90% at the end of 10 years and 80% at the end of 25 years.
(b) Power Conditioning Unit (PCU) of 350-800 V DC Input voltage range and 400 V AC, three phase, 4 wire, 50Hz plus /- 2.5 Hz, output voltage suitable to generate AC
(c) Power with efficiency not less than 97%, total harmonic distortion less than 3% and suitable for ambient temperature from 0 to 50 degrees C. The PCU shall adjust the voltage and frequency level to suit grid frequency
(d) Data Monitoring System complete with accessories.
(e) Fixing of Array junction box and Main junction box with IP 65 protection and termination arrangement for incoming and outgoing cable along with glands, lugs and other accessories etc. as required.
(f) Lightning and surge voltage protection.
(g) Connections and Interconnections by supplying and fixing required size XLPE insulated copper conductor 1.1 kV grade armoured power and control cables between solar modules, main power cable to grid supply PCU unit along with supplying and fixing of necessary channel/conduit lugs and other accessories etc. as required. 2. Above 10 kWp and up to 100 Kwp [Through Rate] | - | KWp | - | - |
| - | 32.70.3
Supply Installation testing commissioning of Solar Photovoltaic grid connected roof top Plant conforming to MNRE specifications as amended, consisting of Mono/Poly Crystalline silicon solar cells, net metering facility, necessary protections, earthing, mounted on Aluminium/GI structure of suitable strength with following components complete as required:-
(a) Solar Photovoltaic Module manufactured in India, conforming to IS 14286/IEC 61215, IS/IEC 61730-Part-1, IS/IEC 61730-Part-2. Solar Photovoltaic Module conversion efficiency shall not be less than 16.5%. PV modules used in solar power plants/ systems must be warranted for their output peak watt capacity, which should not be less than 90% at the end of 10 years and 80% at the end of 25 years.
(b) Power Conditioning Unit (PCU) of 350-800 V DC Input voltage range and 400 V AC, three phase, 4 wire, 50Hz plus /- 2.5 Hz, output voltage suitable to generate AC
(c) Power with efficiency not less than 97%, total harmonic distortion less than 3% and suitable for ambient temperature from 0 to 50 degrees C. The PCU shall adjust the voltage and frequency level to suit grid frequency
(d) Data Monitoring System complete with accessories.
(e) Fixing of Array junction box and Main junction box with IP 65 protection and termination arrangement for incoming and outgoing cable along with glands, lugs and other accessories etc. as required.
(f) Lightning and surge voltage protection.
(g) Connections and Interconnections by supplying and fixing required size XLPE insulated copper conductor 1.1 kV grade armoured power and control cables between solar modules, main power cable to grid supply PCU unit along with supplying and fixing of necessary channel/conduit lugs and other accessories etc. as required. 3. Above 100 kWp and up to 500 Kwp [Through Rate] | - | KWp | - | - |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.12 MB
BOQ_595952.xls
BOQ • 0.32 MB
AD0158732.pdf
Additional Documents • 0.33 MB
OT0158732.pdf
Other Document • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].