| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.3 LAccepted-AOC | L1 | Accepted-AOC L1 Accepted | |
| 2 | L2₹25.8 L+₹1.4 L (5.82%)Rejected-AOC | L2 | Rejected-AOC L2 Rejected | |
| 3 | L3₹26.2 L+₹1.8 L (7.56%)Rejected-AOC | L3 | Rejected-AOC L3 Rejected | |
| 4 | L4₹27.1 L+₹2.7 L (11.2%)Rejected-AOC | L4 | Rejected-AOC L4 Rejected | |
| 5 | L5₹31.3 L+₹6.9 L (28.4%)Rejected-AOC NO 101 A KILMUDALAMBEDU POST PERUVOYAL VILL GUMMIDIPOONDI TALUK TIRUVALLUR 601206 | GUMMIDIPOONDI | TIRUVALLUR | TAMIL NADU | 601206 | L5 | Rejected-AOC L5 Rejected |
| Sl No | Description | Qty | Unit | KMKandCO L4 | SREE DURGA ENTERPRISES L3 | T MASTHAN L1 | P.MUTHUSAMY L2 | M/s. SARASWATHI ENTERPRISES L5 |
|---|---|---|---|---|---|---|---|---|
| 1.001. Improvements of BG, CC Road-50m, Compound Wall-20m at ST Colony in Chedhilpakkam Panchayatat | ||||||||
| 2.00CEMENT ROAD | ||||||||
| 3.00 | Earthwork excavation for foundation (for narrow excavation) to full depth as per designed in all soils and sub soils except soft disintegrated rock not requiring blasting and hard rock requiring blasting and bailing water wherever necessary. Refilling the sides of foundation with excavated earth other than sand in layers of well rammed and compacted and depositing the surplus earth in places shown by the departmental officers with an initial lead of 10m and initial lift of 2m and clearing and leveling the site etc. complete complying with standard specification. | 1.5 | cu.m | 225 ₹337.5 | 120 ₹180 Lowest | 206 ₹309 | 220 ₹330 | 224 ₹336 |
| 4.00 | Plain Cement Concrete 1 : 4 :8 ( one part of cement, four parts of sand and eight parts of hard broken stone ) using 40 mm gauge hand broken hard broken granite stone jelly complying with standard specifications in foundations and basement. | 14.2 | cu.m | 5,670 ₹80,514 | 4,486 ₹63,701.2 Lowest | 5,180 ₹73,556 | 5,500 ₹78,100 | 5,630 ₹79,946 |
| 5.00 | Towards centering chargers for all labour charges etc | 47.5 | sq.m | 100 ₹4,750 | 113 ₹5,367.5 | 91 ₹4,322.5 Lowest | 99 ₹4,702.5 | 99.5 ₹4,726.25 |
| 6.00 | Cement Concrete 1:3:6 (One cement, Two sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly fincluding cost conveyance and all labour charges etc. complete. | 4.6 | cu.m | 6,400 ₹29,440 | 5,616 ₹25,833.6 Lowest | 5,834 ₹26,836.4 | 6,341 ₹29,168.6 | 6,341 ₹29,168.6 |
| 7.00 | Cement Concrete 1:2:4 (One cement, Two sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly fincluding cost conveyance and all labour charges etc. complete. | 11.25 | cu.m | 7,100 ₹79,875 | 6,259 ₹70,413.75 Lowest | 6,446 ₹72,517.5 | 6,500 ₹73,125 | 7,007 ₹78,828.75 |
| 8.00 | Supplying and fixing of Bitumen pad for expansion joints | 2.25 | sq.m | 235 ₹528.75 | 230 ₹517.5 | 213 ₹479.25 Lowest | 232 ₹522 | 232 ₹522 |
| 9.00COMPOUND WALL | ||||||||
| 10.00 | Earth work Excavation in all classes of soils except hard rock in Hard Ordinary soil with initial lead and lift including all other charges and labour charges etc,. | 6.12 | cu.m | 225 ₹1,377 | 240 ₹1,468.8 | 206 ₹1,260.72 Lowest | 224 ₹1,370.88 | 224 ₹1,370.88 |
Tender Value
₹26.7 L
EMD Value
₹27,000
Closing Date
12 Sept 2025, 3:00 pmClosed
Project Director Joint Director DRDA Tiruvallur
Project Director Joint Director DRDA Tiruvallur
1.Improvement of BG, CC road 50m Compound Wall 20m at Chedhilpakkam ST colony in Chedhilpakkam Pancyayat 2. Providing Pipe line at Chedhilpakkam ST Colony in Chedhilpakkam Panchayat 3. Construction Anganwadi Building at ST colony GPD 12
2025_RDTN_597687_1
2974/2024/A3
Open Tender
Civil Works
Item Rate
120 days
Gummidipoondi Block
Refer Tender Document
5 documents required · 5 mandatory
₹0
₹27,000
Yes
DRDA Tiruvallur
7 Nov 2025
26 Aug 2025
12 Sept 2025
26 Aug 2025
12 Sept 2025
3 Sept 2025
3 Sept 2025
Amount
1. Improvements of BG, CC Road-50m, Compound Wall-20m at ST Colony in Chedhilpakkam Panchayatat
CEMENT ROAD
Earthwork excavation for foundation (for narrow excavation) to full depth as per designed in all soils and sub soils except soft disintegrated rock not requiring blasting and hard rock requiring blasting and bailing water wherever necessary. Refilling the sides of foundation with excavated earth other than sand in layers of well rammed and compacted and depositing the surplus earth in places shown by the departmental officers with an initial lead of 10m and initial lift of 2m and clearing and leveling the site etc. complete complying with standard specification.
Plain Cement Concrete 1 : 4 :8 ( one part of cement, four parts of sand and eight parts of hard broken stone ) using 40 mm gauge hand broken hard broken granite stone jelly complying with standard specifications in foundations and basement.
Towards centering chargers for all labour charges etc
Cement Concrete 1:3:6 (One cement, Two sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly fincluding cost conveyance and all labour charges etc. complete.
Cement Concrete 1:2:4 (One cement, Two sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly fincluding cost conveyance and all labour charges etc. complete.
Supplying and fixing of Bitumen pad for expansion joints
COMPOUND WALL
Earth work Excavation in all classes of soils except hard rock in Hard Ordinary soil with initial lead and lift including all other charges and labour charges etc,.
C.C 1:4:8 Mix Using 40mm ISS HBG Metal including cost and conveyance and all materials and all labour charges etc,.Completed.
Supply and Fabrication of steel including cost and conveyance of all materials to site and all labour charges for placing in position etc,..completed..
Supply and errecting for centering including cost and conveyance and labour charges with materials charges with MS sheet completed
Upto Basement
Above Basement
RCC 1:1.5:3 Mix using 20mm HBG metal including cost and conveyance and all labour charges and materials charges completed..
Brick work in CM 1:5 mix using country Bricks including cost and conveyance of all materials to site mixing, placing,curing and all labour charges etc,..
Plastering in CM 1:5 Mix using 12mm thick including cost and conveyance and all lab our charges and materials charges completed..
Painting two coats with Exterior/interior first quality Emulsion of approved colour over one coat of primer including cost and conveyance and all lab our charges and materials charges completed..
CREMATION SHED
Earth work Excavation in all classes of soils except hard rock in Hard Ordinary soil with initial lead and lift including all other charges and labour charges etc,.
C.C 1:4:8 Mix Using 40mm ISS HBG Metal including cost and conveyance and all materials and all labour charges etc,.Completed.
Cement Concrete 1:2:4 mix using 20 mm ISS H.B.G. metal including cost and conveyence of all materials to site and all other albour charges etc., completed.
Brick Work In C.M 1:5 mix using good quality of country bricks including cost and conveyence of all materials to site and all other labour charges etc., completed.
Supplying and filling the excavated earth including cost of labour charges for filling etc., completed.(Refilling charges)
Collection and supply of sand and filling conveyance to the siteand all labour charges for filling as per standard speecifications in all etc
Dry Brick work wall Including all labour charges as per standard specifications in all etc
Brick Work In C.M 1:5 mix using good quality of country bricks including cost and conveyence of all materials to site and all other labour charges etc., completed.
Supply and erection of steel centering for all R.C.C items of works including hire charges and labour charges for errection etc., completed. (Below Ground level)
Supply and errection of steel centering for all R.C.C items of works including hire charges and labour charges for errection etc., completed.
Supplying and fabrication of steel including cost and conveyance and cutting, bending, tying and placing in position.etc.complete
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.
Plastering with C.M 1:3 mix -10mm thick including cost and conveyence of al materials to site and all other labour charges etc., completed.
Finishing the top of roof with one course of machine pressed tiles size of 200 mm *200 mm*2mm of approved quality laid inC.M 1:3 mix including all cost of materials and labour charges etc.,
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Provision for Chimney cover slab etc..,
2. Providing of Pipe Line at ST Colony in Chedhilpakkam Panchayat
Laying and joining of following sizes of 63 mm PVC pipe including the cost of , lowering of PVC pipes in to the trenches, laying in to proper grade and algnment and refilling the excavated earth atfter the GI pipes are laid and including the const of GI pipes etc, completed.
63 mm PVC Bend P26-1.5-3
63 mm PVC Threaded coupler
63 MM TEE
50 mm GI Gate Valve
3. Construction of Anganwadi Building at ST Colony in Chedhilpakkam Panchayat
Earthwork excavation for foundation (for narrow excavation) to full depth as per designed in all soils and sub soils except soft disintegrated rock not requiring blasting and hard rock requiring blasting and bailing water wherever necessary. Refilling the sides of foundation with excavated earth other than sand in layers of well rammed and compacted and depositing the surplus earth in places shown by the departmental officers with an initial lead of 10m and initial lift of 2m and clearing and leveling the site etc. complete complying with standard specification.
Supply and Filling with M.Sand including cost and conveyance and all materials and all labour charges etc,.Completed.
C.C 1:4:8 Mix Using 40mm ISS HBG Metal including cost and conveyance and all materials and all labour charges etc,.Completed.
Brick work in CM 1:5 mix using country Bricks including cost and conveyance of all materials to site mixing, placing,curing and all labour charges etc,..
Brick work in CM 1:5 mix using country Bricks including cost and conveyance of all materials to site mixing, placing,curing and all labour charges etc,..
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.
Supply and erection of steel centering for all R.C.C items of works including hire charges and labour charges for errection etc., completed. (Below Ground level)
Supply and errection of steel centering for all R.C.C items of works including hire charges and labour charges for errection etc., completed.
Supplying and fabrication of steel including cost and conveyance and cutting, bending, tying and placing in position.etc.complete
Paving the Top of roof with Solar reflective ceramic tiles of size 305 x 305 x 7mm thick of approved quality and colour laid in Cement mortar 1:3 (One cement and three M.Sand) 12mm thick and pointed with tile grout (Nitotile Grout or equivalent) and cement in the ratio of 1:3 for joint, curing etc., complete complying with standard specification and as directed by the departmental officers. (The make and brand of the tiles should be got approved by the Executive Engineer before use on works)
Plastering with cement mortar 1:5, 12mm thick including cost and conveyance and all labour charges etc., complete as per standard specification.
Plastering with cement mortar 1:3, 10mm thick including cost and conveyance and all labour charges etc., complete as per standard specification.
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work.
Granolithic floor finish with C.M. 1: 2:4 mix to 25mm thick using 10 to 12 mm chips including cost and conveyance and all labour charges etc,. complete as per standard specification.
Paving the Floor with shahabad stone size 600x600x20mm laid in CM 1;3,10mm thick and pointing with white cement 0.40kg per sqm mixed with colouring pigment to suit the colour of the tiles including cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification.
Paving the Floor with Antiskid tiles of size 305x305x6mm laid in CM 1;2,10mm thick and pointing with white cement 0.40kg per sqm mixed with colouring pigment to suit the colour of the tiles including cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification.
Supply and fixing doors and windows including all charges etc., complete as per standard specification. Door D
Door D1
Door D2
Window W1
Window W
upvc ACRYLIC SHUTTERWindow W1
ventilator
ventilator
Provision for electrification arrangements with service connection etc., complete as per standard specification. Light point SD 25
Fan point SD 25
Fan SOR SD 107
Plug point SD 38
CFL lamp-BH fitting SD 80
DPIC swtich of 500 V SD 154
G I Pipe (40mm)
Service Wire SD 64
Exhaust fan SD 114
Bulk head fitting SD 83
E B Deposit
Painting two coat with approved quality of oil bound distemper with colour over one coat of white cement for primier coat for the base including preparing surface and all materials cost labour etc., complete as per standard specification.
Painting two coat with ready mixed plastic emulsion of first quality paint and of approved colour over a priming coat including thorogh scarpping clean removal of dirt etc., complete as per standard specification.
Painting two coats using Ist quality readymix enamel paint of approved colour over new iron work including cost and conveyance and all labour charges etc., complete as per standard specification.
Towards the cost and supply of 4" Rainwater Downfall pipe fixing with clamps etc., complete as per standard specification.
Provision for European water closet including labour charges
Provision for 500 liters watertank
Provision for RWH arrangements 4Nos 1.5m DIA RCC RINGS WITH 40mm,20mm,SAND FILLING
Provision of BaLA painting , cartoons in hall and toilet & Letters, Pictures & Board, etc.
Provision for baby friendly basin
Supplying and fixing in position best quality and approved make Indian made white earthernware wash hand basin of size 550 x 400mm without pedestal with a pair of cast iron brackets, including cost 15mm dia brass CP pillar tap, 32mm dia "B" class GI waste pipe with rubber plug and chain, 15mm dia GM wheel valve, 15mm brass nipple, 15mm dia nylone connection, 32mm dia CP brass waste coupling including fixing of wash basin using CI brackets on to the wall in position with TW plugs and screws, rubber washers, white lead and giving necessary water supply connection and painting the brackets with two coat of painting over a priming coat of anti-corrosive paint including testing for leakages etc., complete complying with standard specification and as directed by the departmental officers. (The wash hand basin and specials should be got approved by the Executive Engineer before use on works).
Provision for Tactile and Signages for Disabled persons
Provision for water supply and sanitary arrangemets
Provision for Stainless steel handle for disabled persons-toilet and Provision for Ramp -Anganwadi and Disabled Toilet
Provision for procuring play equipments for children
Provision for Citizen Information Board
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
P.MUTHUSAMY (BID ID -1456702)
SREE DURGA ENTERPRISES (BID ID -1456570)
KMKandCO (BID ID -1455643)
M/s. SARASWATHI ENTERPRISES (BID ID -1457053)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .