| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹16.3 LAccepted-Finance | 1 | Accepted-Finance Accept | |
| 2 | Rejected-Technical | - | Rejected-Technical Reject |
| Sl No | Description | Qty | Unit | Ellappan contractor L1 | DHANALAKSHMI L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete | 20.48 | Cum | 263 ₹5,386.24 Lowest | 265 ₹5,427.2 |
| 2.00 | CC 1:4:8 mix using 40mm ISS HBG metal with cost and conveyance including all other labour charges etc complete | 20.48 | Cum | 5,344 ₹1,09,445.12 Lowest | 5,350 ₹1,09,568 |
| 3.00 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) . | 120.96 | Cum | 2,470 ₹2,98,771.2 Lowest | 2,475 ₹2,99,376 |
| 4.00 | Centering with suttering for all cc works using MS sheet with cost and conveyance Incluidng all other labour charges etc complete | 307.2 | Sqm | 181 ₹55,603.2 Lowest | 182 ₹55,910.4 |
| 5.00 | CC 1:2:4 mix using 20mm ISS HBG metal with cost and conveyance including all other labour charges etc complete | 126.72 | Cum | 6,630 ₹8,40,153.6 Lowest | 6,635 ₹8,40,787.2 |
| 6.00 | Supply and fixing of bituminous pad with cost and conveyance including all other labour charges etc complete | 16.13 | Sqm | 475 ₹7,661.75 Lowest | 480 ₹7,742.4 |
| 7.00 | Compaction of Pavement using Concrete Vibrators with cost and conveyance including all other labour charges etc complete | 806.4 | Sqm | 81 ₹65,318.4 Lowest | 83 ₹66,931.2 |
| 8.00 | GST Amount for providing Service to Government Contract Works for the above Construction Works.
{ GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}18% | 1 | GST Amount | 2,48,821.11 ₹2,48,821.11 Lowest | 2,49,433.63 ₹2,49,433.63 |
Tender Value
₹16.6 L
EMD Value
₹17,000
Closing Date
13 Feb 2026, 3:00 pmClosed
BDO BP
KTR
Providing Cement Concrete Road to Vandalur Perungathur Link Road in Vandalur Panchayat at Kattankolathur Panchayat Union
2026_RDTN_654207_1
RC.No 2442/2025/A2 dt 09/02/26
Open Tender
Civil Works
Item Rate
90 days
BDO KTR
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹17,000
Yes
23 Feb 2026
10 Feb 2026
13 Feb 2026
10 Feb 2026
13 Feb 2026
10 Feb 2026
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
CC 1:4:8 mix using 40mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Centering with suttering for all cc works using MS sheet with cost and conveyance Incluidng all other labour charges etc complete
CC 1:2:4 mix using 20mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Supply and fixing of bituminous pad with cost and conveyance including all other labour charges etc complete
Compaction of Pavement using Concrete Vibrators with cost and conveyance including all other labour charges etc complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}18%
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_784457.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.14 MB
BOQ_784457.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .