| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.8 CrAdmitted-Finance 41 21 A KMC TOWERS C2 C2 SCHEME ROAD THENI 625531 | THENI | TAMIL NADU | 625531 | ₹8.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹9.2 Cr+₹36.7 L (4.16%)Admitted-Finance PUDUKKOTTAI PUDUKKOTTAI | PUDUKKOTTAI | TAMIL NADU | 613301 | ₹9.2 Cr+₹36.7 L (4.16%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | P Pandiaraj L2 | KMC Associates, Theni L1 |
|---|---|---|---|---|---|
| 1.01 | Earthwork excavation in soft disintegrated rock not requiring blasting except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS. | 1,263.76 | Cum | 483 ₹6,10,396.08 | 460 ₹5,81,329.6 Lowest |
| 1.02 | Earthwork excavation in Medium Rock & Dense Medium rock not requiring blasting except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as Bailing our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for (OPEN FOUNDATION)UNDER ABUTMENTS & PIERS BELOW SILL LEVEL. | 1,263.76 | Cum | 711.17 ₹8,98,748.2 | 677.3 ₹8,55,944.65 Lowest |
| 1.03 | Blasting and removing the hard rock with blasting measured in solid in the foundation and removing the blasted stones and stacking the same for pre-measurement at site including the all other labour and incidental charges including the cost of the blasting materials and all other tools and plants employed etc., complete as per standard specifications for FOUNDATION OF ABUTMENTS, PIERS AND WINGS WALLS | 384.52 | Cum | 1,615.85 ₹6,21,326.64 | 1,538.9 ₹5,91,737.83 Lowest |
| 1.04 | Providing and fixing Dowel Bars with 32mm steel rods of 1.5m length embedded into the rock to a depth of 0.6m by providing required depth of holes by drilling the rock in 50mm dia wherever necessary including fixing in position by grouting the embedded portion with CM 1:2 after placing the bars for sub-structure of abutment / pier/wing and top footing of open foundation/raft foundation | 324 | Nos | 1,092 ₹3,53,808 | 1,040 ₹3,36,960 Lowest |
| 1.05 | Vibrated Cement Concrete of grade M 15 (Nominal Mix) using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments , Piers Footing | 64.09 | Cum | 6,050.45 ₹3,87,773.34 | 5,762.33 ₹3,69,307.73 Lowest |
| 1.06 | Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Footing Under Abutment, Wing Wall & Piers Below Sill Level. | 1,160.89 | Cum | 9,607.5 ₹1,11,53,250.68 | 9,150 ₹1,06,22,143.5 Lowest |
| 1.07 | Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, BELOW SILL LEVEL. | 126.16 | Cum | 11,035.5 ₹13,92,238.68 | 10,510 ₹13,25,941.6 Lowest |
| 1.08 | Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, ABOVE SILL LEVEL. | 122.45 | Cum | 11,644.5 ₹14,25,869.03 | 11,090 ₹13,57,970.5 Lowest |
| 1.09 | Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF CIRCULAR COLUMN PIERS BELOW SILL LEVEL. | 62.2 | Cum | 106.05 ₹6,596.31 Lowest | 10,100 ₹6,28,220 |
| 1.10 | Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF CIRCULAR COLUMN PIERS ABOVE SILL LEVEL. | 226.99 | Cum | 13,419 ₹30,45,978.81 | 12,780 ₹29,00,932.2 Lowest |
Tender Value
Refer Docs
EMD Value
₹8.5 L
Closing Date
30 Mar 2022, 3:00 pmClosed
Project Director
1st floor, DRDA, Theni
Construction of Bridge across vaigai river Melavadipatti village at A.Vadipatti panchayat in Periyakulam Block of Theni District under NABARD RIDF-XXVII(2021-22)Tranche.
2022_RDTN_223669_1
DIPR/751/Tender/2022 Dt-31.01.2022 (THE HINDU)
Open Tender
Civil Works - Bridges
Item Rate
540 days
Theni
As per tender document
3 documents required · 3 mandatory
₹0
₹8.5 L
1st floor, DRDA, Theni
3 Feb 2023
3 Mar 2022
30 Mar 2022
3 Mar 2022
30 Mar 2022
14 Mar 2022
14 Mar 2022
Amount
Earthwork excavation in soft disintegrated rock not requiring blasting except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
Earthwork excavation in Medium Rock & Dense Medium rock not requiring blasting except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as Bailing our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for (OPEN FOUNDATION)UNDER ABUTMENTS & PIERS BELOW SILL LEVEL.
Blasting and removing the hard rock with blasting measured in solid in the foundation and removing the blasted stones and stacking the same for pre-measurement at site including the all other labour and incidental charges including the cost of the blasting materials and all other tools and plants employed etc., complete as per standard specifications for FOUNDATION OF ABUTMENTS, PIERS AND WINGS WALLS
Providing and fixing Dowel Bars with 32mm steel rods of 1.5m length embedded into the rock to a depth of 0.6m by providing required depth of holes by drilling the rock in 50mm dia wherever necessary including fixing in position by grouting the embedded portion with CM 1:2 after placing the bars for sub-structure of abutment / pier/wing and top footing of open foundation/raft foundation
Vibrated Cement Concrete of grade M 15 (Nominal Mix) using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments , Piers Footing
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Footing Under Abutment, Wing Wall & Piers Below Sill Level.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, BELOW SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, ABOVE SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF CIRCULAR COLUMN PIERS BELOW SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF CIRCULAR COLUMN PIERS ABOVE SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS.
Vibrated reinforced Cement Concrete of grade M 35 (Design Mix) using 20 & 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RCC Capping beam above column pier
Vibrated Reinforced cement concete of Grade M35 using 20mm, 12mm ISS Graded HBG graded metal including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel but including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working art depths, Tools and plants and incidential charges etc., complete as per relevant standard specifications, for PEDESTAL OVER CAPPING BEAM AND BED BLOCKS
Supplying and fixing of Elastomeric bearing of size 45 x 30 x 9.6 cm as shown in the drawing including cost and conveyance to work site, labour for fixing the bearing in position and all other incidental charges etc., complete
Vibrated Reinforced cement concete of Grade M35 using 20mm, 12mm ISS Graded HBG graded metal including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel but including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working art depths, Tools and plants and incidential charges etc., complete as per relevant standard specifications, for T-BEAM AND CROSS BEAM GIRDER
Vibrated Reinforced cement concete of Grade M35 using 20mm, 12mm ISS Graded HBG graded metal including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel but including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working art depths, Tools and plants and incidential charges etc., complete as per relevant standard specifications, for FOR DECK SLAB
Providing and fixing seepage pipes of 100 mm dia. PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm. Dia. Semi spherical back fill arrangements with 100 mm. size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS.
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8
Filling behind Abutment and Wings with clean gritty gravel of Ø value not less than 35° including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete as per standard specifications.
Providing and fixing STRIP STEEL EXPANSION JOINT in between Deck Slabs over abutment and pier as shown in the drawing including cost and conveyance of expansion joints including Shalimar pad and joint sealent etc,complete.
Vibrated Cement Concrete of grade M 15 using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for BASECOURSE BELOW APPROACH SLAB
Vibrated reinforced cement concrete M 35 Grade using 20mm&12mmISS size hard granite broken graded metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel but including cost of form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete working at heights, hire chargs for tools and plants, including all other incidental charges etc., complete as per standard specifications for Approach Slab
Add Supply and fixed of high quality PVC Pipe of 100mm dia including cost and Conveyance of Pipe to Site for providing utility services to footpath
Vibrated cement Concrete M35 using 20mm,12mm IRC Metal HBG graded metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges,formwork,cost of premoulded expansion joints and fixing the same in position etc., complete for wearing coat of 75mm uniform thickness over deck slab and approach slab.
Vibrated Reinforced Cement Concrete M-25 using 20 mm & 12 mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site including cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, and curing concrete,working at heights,hire charges for tools and plants,including all other incidental charges,etc, complete for RCC HAND RAIL AND POSTS OVER DECK SLAB.
Vibrated Cement Concrete M20 grade using 20mm, 12mm ISS size hard granite broken metal including cost and form work and centering conveyance of all materials to site and cement at sitel including labour charges for mixing,transporting, laying, and curing concrete,working at heights for PCC PARAPET OVER WINGS.
Providing and fixing of cast iron drainage spouts 100mm dia as per MOST drawing SD/205 with grating arrangements at top as shown in the drawing using 12mm x 25mm flats for grating arrangements, and 100mm dia drainage spout projecting beyond the bottom of deck slab as shown in the drawing including cost and conveyance of cast iron pipes and flats and fixing them in position etc,complete.
Supply and fabrication of High Yield Strength Deformed Bar with Grade Designation Fe.500, conforming to IS:1786 2008, steel required for all RCC items of works involved in the schedule cost of steel at site fabrication labour charges for cleaning, bending tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc., complete, Fe.500 grade.
Approach Road
Excavation for Road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5m and lead upto 1000m as per Technical Specification Clause 302.3
98% Compaction
100% Compaction
Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers as necessary including watering, consolidating by the power roller rolling and all labour charges for soiling including hire charges for consolidation etc. complete.(Gravel Shoulder)
Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller to achieve the desired density, complete as per Technical Specifications Clause 401 Grading III (GSB)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam (WBM - II) specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. (Grading II)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam (WBM - III) specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. (Grading III)
Providing and applying Tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 4 kg / 10 sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete
Diversion Road
Excavation for Road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5m and lead upto 1000m as per Technical Specification Clause 302.3
98% Compaction
Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller to achieve the desired density, complete as per Technical Specifications Clause 401 Grading III (GSB)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam (WBM -II) specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. (Grading II)
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
Provision for Retaining wall (PCC)
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER RETAINING WALL.
Vibrated Cement Concrete of grade M 15 Nominal Mix using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments,Footing & Retaining Wall.
Vibrated Cement Concrete of Grade M-20 using 20mm & 12mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, complete as per relevant standard specification for FOOTINGS OF RETAINING WALLS.
Vibrated Cement Concrete of grade M20 Design Mix using 20mm & 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for STEM OF RETAINING WALLS.
Providing and fixing seepage pipes of 100 mm dia. PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm. Dia. Semi spherical back fill arrangements with 100 mm. size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS.
Provision for Conical Revertment
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER TOE WALL.
Vibrated Cement Concrete of grade M 15 using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below toe Wall.
Vibrated Cement Concrete of Grade M-20 using 20mm, 12mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork and centering, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, complete as per relevant standard specification for FOOTINGS OF TOE WALLS.
Fillling in foundation trenches as per drawing and technical specification Clause 305.3.10 behind abutment, wing wall, return wall to the full height, compacted to firm
Gravel Bedding
Providing and laying of pitching of slopes / laying of apron with cement concrete blocks of size 300mm x 300mm x 300mm as per Table 1300.1 cast in-situ and made with nominal mix of M-15 grade cement concrete as per drawing and technical specifications clause 1301
Provision for sign board
Provision for name board
Provision for Reflectors
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
P Pandiaraj
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .