| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹31.7 LAccepted-Finance 1 306 VISHAL KHAND GOMTI NAGAR LUCKNOW | GHAZIABAD | UTTAR PRADESH | 201001 | ₹31.7 L | 1 | Accepted-Finance lowest bid rate |
| 2 | 2₹32.7 LRejected-Finance 1 306 LUCKNOW | LUCKNOW | UTTAR PRADESH | 226001 | ₹32.7 L | 2 | Rejected-Finance higher bid rate |
| 3 | 3₹33.0 LRejected-Finance | ₹33.0 L | 3 | Rejected-Finance higher bid rate |
| Sl No | Description | Qty | Unit | SHAILESH SINGH L3 | MANJULA MISHRA L1 | M/S S S ENTERPRISES L2 |
|---|---|---|---|---|---|---|
| 1.00 | Fencing of Walkway by GI Chain Link Mesh and with MS Door for protection of mechanical items and safety of people on the superstructure of dam with providing GI Chain Link Jali, Angle support, welding rod etc and including all cost of material, labour and T&P etc. for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 1 | Job | 11,45,370 ₹11,45,370 | 10,85,258 ₹10,85,258 Lowest | 11,35,260 ₹11,35,260 |
| 2.00 | Replacement of worm wheel, Coupling and Bearing overhauling of Redicon unit with replacing gear oil, damaged packing and seal cover of Redicon unit by new gear oil, packing and seal cover including cost of all material, and other allied work, labour, T&P etc. required for proper completion of work Guntanala Dam..The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | 1,11,350 ₹3,34,050 | 1,07,646 ₹3,22,938 Lowest | 1,10,146 ₹3,30,438 |
| 3.00 | Replacing of bottom rubber seal size 80x20 mm as par IS code 11855 by installing new steel strip and rubber seal by making hole and surface preparation including cost of all material, labour, T&P and scaffolding required for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | 69,055 ₹2,07,165 | 66,355 ₹1,99,065 Lowest | 67,855 ₹2,03,565 |
| 4.00 | Replacing of Side rubber seal size 250x15 mm as par IS code 11855 by installing new steel strip and rubber seal by making hole and surface preparation including cost of all material, labour, T&P and scaffolding required for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job | 82,595 ₹4,95,570 | 80,298 ₹4,81,788 Lowest | 81,800 ₹4,90,800 |
| 5.00 | Procuring and Installing 30 watt LED Light inbuilt with Solar PV Panel and 30 Ah battery at Ohan dam by providing Self powered, auto switching LED light inbuilt with solar panel and lithiom Ion Battery at Guntanal damThe work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 8 | Job | 36,590 ₹2,92,720 | 35,150 ₹2,81,200 Lowest | 36,200 ₹2,89,600 |
| 6.00 | Fabrication/erection of missing cover of Balance Box of Gunta Dam by providing of M.S. sheet, M.S. angle etc. and fabrication by cutting, welding as per sample including cost of all material, labour & T&P required for completion of work at site.at Guntanala damThe work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | 98,570 ₹2,95,710 | 96,449 ₹2,89,347 Lowest | 97,700 ₹2,93,100 |
| 7.00 | Fabrication/erection of cover of Gear Box by providing of M.S. sheet, M.S. angle etc. and fabrication by cutting, welding as per sample including cost of all material, labour & T&P required for completion of work at Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job. | 45,980 ₹2,75,880 | 44,256 ₹2,65,536 Lowest | 45,550 ₹2,73,300 |
| 8.00 | Installing new Plummer Block, Gun metal Bush in place of missing one by new Bolts and other allied work including all cost of material , labour and T&P etc. for proper completion of work per Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job | 42,995 ₹2,57,970 | 41,495 ₹2,48,970 Lowest | 42,280 ₹2,53,680 |
Tender Value
Refer Docs
EMD Value
₹67,100
Closing Date
3 Jun 2026, 10:00 amClosed
Executive Engineer
Office of Executive Engineer, Barrage Mechanical Maintenance Division, Kanpur, Irrigation Department U.P., 67-A, Cantt, Kanpur-208004
Fencing of Walkway, overhauling of Redicon unit, Replacing of rubber seal,Procuring and Installing LED Light,Fabrication and erection of missing cover and Installing new Plummer Block at Guntanala Dam, Chitrakoot
2026_UPIDM_1153132_1
22/EE/BMMDK/2026-27 (LOT-2)
Open Tender
Miscellaneous Works
Fixed-rate
240 days
Guntanala Dam, Chitrkoot
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
₹67,100
17 Aug 2026
25 May 2026
3 Jun 2026
25 May 2026
3 Jun 2026
25 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Fencing of Walkway by GI Chain Link Mesh and with MS Door for protection of mechanical items and safety of people on the superstructure of dam with providing GI Chain Link Jali, Angle support, welding rod etc and including all cost of material, labour and T&P etc. for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 1 | Job | - | - |
| 2 | Replacement of worm wheel, Coupling and Bearing overhauling of Redicon unit with replacing gear oil, damaged packing and seal cover of Redicon unit by new gear oil, packing and seal cover including cost of all material, and other allied work, labour, T&P etc. required for proper completion of work Guntanala Dam..The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | - | - |
| 3 | Replacing of bottom rubber seal size 80x20 mm as par IS code 11855 by installing new steel strip and rubber seal by making hole and surface preparation including cost of all material, labour, T&P and scaffolding required for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | - | - |
| 4 | Replacing of Side rubber seal size 250x15 mm as par IS code 11855 by installing new steel strip and rubber seal by making hole and surface preparation including cost of all material, labour, T&P and scaffolding required for proper completion of work Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job | - | - |
| 5 | Procuring and Installing 30 watt LED Light inbuilt with Solar PV Panel and 30 Ah battery at Ohan dam by providing Self powered, auto switching LED light inbuilt with solar panel and lithiom Ion Battery at Guntanal damThe work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 8 | Job | - | - |
| 6 | Fabrication/erection of missing cover of Balance Box of Gunta Dam by providing of M.S. sheet, M.S. angle etc. and fabrication by cutting, welding as per sample including cost of all material, labour & T&P required for completion of work at site.at Guntanala damThe work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 3 | Job | - | - |
| 7 | Fabrication/erection of cover of Gear Box by providing of M.S. sheet, M.S. angle etc. and fabrication by cutting, welding as per sample including cost of all material, labour & T&P required for completion of work at Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job. | - | - |
| 8 | Installing new Plummer Block, Gun metal Bush in place of missing one by new Bolts and other allied work including all cost of material , labour and T&P etc. for proper completion of work per Guntanala Dam.The work shall be carried out according to the specification and as per direction of the Engineer-in-Charge. (G.S.T. will be paid extra as per Government norms) . | 6 | Job | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.20 MB
TD22Lot-2.pdf
Tender Documents • 1.19 MB
BOQ_2160212.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].