Loading…
Loading…
Tender Value
₹23.1 Cr
EMD Value
₹13.1 L
Closing Date
23 Jan 2026, 2:30 pmClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
BRIDGELINE
14 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work costing not less than the amount equal to 60% of advertised value of the tender. Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate. Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender.
Definition of Similar Work :- "Fabrication and erection/launching of steel bridges/FOB." Note:- In case of any steel bridge having substructure of other than steel then only the component of steel fabrication, erection/launching will be considered for assessment of technical eligibility.
34 conditions · 8 needing a document upload
Please submit bank details of the firm / individual/ JV / partnership etc. i.e. Name of the Bank along with Bank Branch Code, Account Number, IFSCCode, PAN Number and other necessary & relevant documents.
Please furnish list of Works on hand indicating Description of Work, Contract Value, Approximate value of balance work yet to be done and Date of award.
Please furnish documents in support of your claim to fulfill the eligibility criteria as mentioned in the tender documents. Each page of the copy of documents /certificates in support of credentials, submitted by the you, shall be self attested/ digitally signed by the you or authorized representative of the your firm. Only those documents which are declared explicitly by you as "documents supporting the claim of qualifying the laid down eligibility criteria", will be considered for evaluating the offer or otherwise available in the offer.
Please furnish statement of deviations from tender conditions, if any.
Requisite documents proving technical eligibility criteria and financialeligibilitycriteria has been uploaded along with those required as perexplanation givenin clause 10 of IRGCC-2022 (Works Matter).
All requisite valid documents regarding constitution of business of thebiddingfirm should be submitted along with the tender as per clause 14 ofIRGCC-2022 (Works Matter),otherwise their offer will be consideredincomplete andshall not be considered.
Joint Venture firms, if applicable in the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 17 of IRGCC-2022(Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
Partnership firms, if bidding for the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 18 of IRGCC-2022(Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall be summarily rejected. A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be submitted after award of work, specifically authorizing him/them to deal with all other contractual activities subsequent to signing of agreement, if required. Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued. However, the Power of Attorney provided by Bidders from countries that have signed the Hague Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a conforming Appostille certificate. Reference: para 15 of IRGCC-2022 (Works matter),otherwise their offer will be considered incomplete and shall not be considered.
For tenders having advertised value more than Rs. 20 crore, The tender/technical bid will be evaluated based on bid capacity formula detailed as Annexure-VI of IRGCC 2022 & as amended from time to time.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Rates are inclusive of all taxes/octroi, license fee, royalty charges etc. legally leviable by State, Central Govt. and/or any other local authority. If any Tax/Royalty/Octori is quoted extra, the same will neither be considered for evaluation of the tender nor will be paid. However any changes in rate of taxes or any new tax /cess on Works Contract will be dealt according to clause 37 of IRGCC-2022 (Works Matter).
Sales tax/Business tax will be recovered as per extant instruction on thesubject
In case the date of closing mentioned in the Notice Inviting Tender is declared a holiday/bandh/strike etc. on any account, the date of closing tender online will not be changed as the application in the website of IREPS does not permit submission of any offer after closing date and time of the tender. However, opening of tenders online will be on any convenient day after the closing date/time of tenders.
All terms and conditions in the tender documents are binding on the Tenderers.
Tenderers are advised to visit the site of work to ascertain all aspects of the site conditions viz accessibility, availability of approach road, nature of the soil, availability of material, availability of labour etc. that may be encounteredincourse of execution of work.
Tenderer should see the website for the corrigendum/addendum to the NIT/tender document, if any that may be uploaded prior to tender opening(inclusive) as there will not be any separate communication for that.
The tenderer for carrying any construction work in Uttar Pradesh must get the mselves registered from the registering Officer under Section - 7 of the Building and Other Construction Workers Act, 1996 and rules made there to by the Uttar Pradesh Govt. and submit certificate of Registration(Labour Department). For enactment of this Act, the tenderer shall be required to pay cess @ 1% of cost of construction work to be deducted from each bill.
The contractor(s) shall observe all the formalities, perform all the actsandabide by all the provisions contained in the Contract Labour Act-1970andContract Labour Central Rules, 1971 which in addition to other stipulations provides that the contractor(s) shall obtain license(s) from appropriate licensing officer of the area before commencement of the work and shall produce a copy thereof along with the original to the Railway office, which will be returned to the contractor after verification.
If any complaint is received against the contractor regarding violationofcontract laws, (exposing Principal Employer to the risk of legalproceedingsunder labour laws), the guilty contractor will be black listed andtheir contractshall be terminated following the due procedure, apart frominitiating criminalproceedings against him with the help of Labour departmentofficials.(Authority: RB letter no.2008/E (LI)/AT/CNR/3, dated 24.01.2018).
It is the responsibility of the tenderer to see corrigendum, if any, to tender notice up to the date of tender opening. IRGCC2022 (works matter)uploaded for reference only. Any correction issued by competent authority upto date of opening will be applicable. Tenderer should quote accordingly.
STAGES OF PAYMENT- 1. On Approval of Methodology/ scheme (Numerical Modelling and Design of instrumentation scheme/ Methodology). (The methodology shall be proof checked by IIT and subsequently approved by the Railways) - 20%. 2. On Completion of Data collection with respect to the subject bridge for First Season - 15%. 3. On Data analysis and furnishing of final report with respect to the subject bridge (First Season report duly proof checked by IIT and subsequently approved by the Railways) - 25%. 4. On Completion of Data collection with respect to the subject bridge for Second Season - 15%. 5. On Data analysis and furnishing of final report with respect to the subject bridge for (Second Season report duly proof checked by IIT and subsequently approved by the Railways) - 25%. Note: Methodology shall mean review of methodology of similar type of work and details of procedure to be followed for instrumentation of bridge herein as per RDSO BS-106R with details of sensors and equipment to be utilized in the project and operation manual of sensors and equipment.
Replacement of old FOB by new FOB and Provision of 02 Nos. Ramp at existing FOB at various stations between PRYJ to TDL section under Dy.CE/Bridge/Line/PRYJ of PRYJ Division.
2025-09~NCR
2025-09
Open
Works - General
12 Months
Prayagraj, Uttar Pradesh
₹0
₹13.1 L
23 Jan 2026
3 Jan 2026
9 Jan 2026
46 items across 6 schedules · ₹21,10,80,419.31 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| fencing along running to be done in close maintaining during and removing after work as per direction of shall consist of self angles of size 50mm x long provided with embedded in CC 1:2:4 block x 0.23m placed at along track. 12mm dia layers shall be tack posts. Note : Released property of the contractor work. Cost of cement blocks shall be paid | — | — | — | — | |
| 1 | painting verticals & luminous paints / strips gap of 30 cm. | Metre | 1380.00 | 112.03 | 1,54,601.4 |
| excavation by mechanical Excavator)/Manual Means floors of the bridges, including setting out, ramming of bottom, excavated material, back approved material and layers by ramming and all lift, disposal of lead of 300m, all types with all labour and as per drawing and as directed by Note: This item will be work in connection with works also like side OHE masts and other in connection with Doubling, New lines. | — | — | — | — | |
| 2 | All kinds of soils | cum | 2964.00 | 196.66 | 5,82,900.24 |
| in position Plain specified Nominal Mix works like side drains, masts and other excluding the cost and shuttering - All : | — | — | — | — | |
| 3 | coarse sand (zone-III) : 4 20 mm nominal | cum | 230.00 | 3,562.71 | 8,19,423.3 |
| Cement at Worksite | — | — | — | — | |
| 4 | Cement 43 grade | MT | 80.00 | 8,153.06 | 6,52,244.8 |
| assembling of all of specified spans with conforming to Quality "B0" E250 conforming to slewing / end launching cranes or any other methods as per site requiring traffic block) on provision of trolley as per approved QAP conforming to IRS-B1-2001 codes and specifications. fabrication and erection methodology will be contractor and got Railway. 2. The rate is all launching in position, except cost of (i) (ii) Bearings & (iii) shall be paid extra under The payment shall be theoretical weight of main gusset plates only. 4. (i) Receipt of material at of girders: 20% (iii) 20% (iv) Completion in | — | — | — | — | |
| 5 | Through Girder (Steel Work) | MT | 239.00 | 1,00,144.26 | 2,39,34,478.14 |
| 6 | conforming to Quality uality "B0" of Grade per IS:2062. | MT | 239.00 | -3,077.26 | -7,35,465.14 |
| work of girders with after surface blasting, followed primer (IS:5666) & one primer (IS:104) and paint (IS:2339) with material as a complete to all relevant process given under IRS-B1-2001. Note: Nominal Aluminium coating DFT of Zinc chrome microns and DFT of paint shall be 12-14 | — | — | — | — | |
| 7 | fabrication | Sqm | 2950.00 | 665.66 | 19,63,697 |
| fixing various size HTS conforming to relevant in concrete column or in proper nuts, bolts, grouting of holes with concrete with all material, complete job. | — | — | — | — | |
| 8 | Cost of cement shall be | Kg | 8012.00 | 127.5 | 10,21,530 |
| plate/composite bridge scaffolding along with / hanging scaffolding required. | — | — | — | — | |
| 9 | Aluminium paint in dual to IS:2339 with DFT each coat. | Sqm | 16337.00 | 93.17 | 15,22,118.29 |
| 10 | and erecting welded riveted steel work in trusses and framed work, Gauge etc. for Steel bridge girders, using channels/flats, plates, square bars, cleats, bolts own steel including straightening, drilling, fixing, erecting, welding, Providing stiffeners per approved drawing a priming coat of a with all contractor's tools & plants, lead & lift tracks if required etc., specification and as Engineer-in-charge. Note: The made on the theoretical components and gusset | MT | 1021.00 | 87,491.62 | 8,93,28,944.02 |
| Schedule total | ₹11,92,44,472.05 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .