Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹78.4 LAdmitted-Finance | ₹78.4 L | L1 | Admitted-Finance |
| 2 | L2₹89.9 L+₹11.6 L (14.8%)Admitted-Finance 001 BHOOMI COLOSSA PLOT NO 04 SECTOR 19 AIROLI NEW MUMBAI 400 708 | NEW MUMBAI | THANE | MAHARASHTRA | 400708 | ₹89.9 L+₹11.6 L (14.8%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | J K Infra Project L1 | P. K. Enterprises L2 |
|---|---|---|---|---|---|
| 1.00 | Dismantling plain cement concrete manually / by mechanical means carefully without damaging adjacent structures including disposal of debris within 200 m lead as per direction of Engineer-in-charge | 6 | CuM | 1,500 ₹9,000 | 1,275 ₹7,650 Lowest |
| 2.00 | Dismantling brick work in Cement mortar carefully without damaging adjacent structures including stacking of materials and dispoal of unserviceable materials within 100 m lead as per direction of Engineer-in-charge | 15 | CuM | 1,500 ₹22,500 | 1,075 ₹16,125 Lowest |
| 3.00 | Dismantling doors, windows and clear storey openings (steel / wood) shutter including chowkhats, architraves, holdfasts etc. complete and stacking within 100 m lead (full windows) Of area 3.00 Sq.M and below | 10 | Nos | 375 ₹3,750 Lowest | 375 ₹3,750 Lowest |
| 4.00 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 100 m lead For thickness of tiles above 10 mm and up to 25 mm | 787 | SqM | 120 ₹94,440 Lowest | 175 ₹1,37,725 |
| 5.00 | Dismantling G.I pipes of all diameter external work including excavation and refilling trenches after taking out pipes manually / by mechanical means including stacking of pipes within 100 m lead as per direction of Engineer-in-charge | 64 | RM | 56.25 ₹3,600 Lowest | 175 ₹11,200 |
| 6.00 | Dismantling flushing cistern of any size including stacking of useful materials near the site and disposal of unserviceable materials within 100 m lead | 8 | Nos | 3,375 ₹27,000 | 975 ₹7,800 Lowest |
| 7.00 | Dismantling old plaster / skirting carefully , raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 100 m lead | 110 | SqM | 120 ₹13,200 Lowest | 375 ₹41,250 |
| 8.00Lead charges for lead Exceeding 4 KM not exceeding 5 KM, by mechanical transport includinmg loading,unloading, stacking / levelling etc. | |||||
| 8.10 | Debris Beyond 4 Km but up to and including 5 km.Note: The rates in respect of above item are applicable for the NET Quantities arrived at after making deductions for voids @ 20% in respect of Soils and 30% in respect of debris from the corresponding stack/truck measurements. | 45 | CuM | 4,500 ₹2,02,500 | 575 ₹25,875 Lowest |
| 9.00 | Providing and laying in position cement concrete of 1:2:4 (1 cement, 2 crushed sand, 4 graded stone aggregate of nominal size 20 mm) including consolidation, finishing, curing etc. complete as per specification and drawings but excluding the cost of Formwork shuttering, centering and steel reinforcement at all Levels Note : The minimum cement content for Cement Concrete works should be as per the latest revision of the relevant IS code. | 2 | CuM | 5,500 ₹11,000 Lowest | 8,425 ₹16,850 |
Tender Value
₹76.3 L
EMD Value
₹1.8 L
Closing Date
12 Jun 2026, 3:00 pmClosed
Chief Engineer
Civil Engineering Division, Bhabha Atomic Research Centre, Trombay, Mumbai-400085
Renovation of toilets, staircase, structural Repair, painting and other miscellaneous civil works in Engineering Hall 6 and other Hill side buildings at North site, BARC, Trombay, Mumbai.
2026_BARC_906386_1
BARC/CED/ET/7/2026-2027 Dated 21/04/2026
Open Tender
Civil Works
Item Rate
450 days
North Site, BARC, Trombay, Mumbai.
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹1.8 L
CED, BARC, Trombay, Mumbai-400085
20 Aug 2026
27 Apr 2026
17 Jun 2026
27 Apr 2026
12 Jun 2026
15 May 2026
27 Apr 2026 - 4 May 2026
5 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling plain cement concrete manually / by mechanical means carefully without damaging adjacent structures including disposal of debris within 200 m lead as per direction of Engineer-in-charge | 6 | CuM | - | - |
| 2 | Dismantling brick work in Cement mortar carefully without damaging adjacent structures including stacking of materials and dispoal of unserviceable materials within 100 m lead as per direction of Engineer-in-charge | 15 | CuM | - | - |
| 3 | Dismantling doors, windows and clear storey openings (steel / wood) shutter including chowkhats, architraves, holdfasts etc. complete and stacking within 100 m lead (full windows) Of area 3.00 Sq.M and below | 10 | Nos | - | - |
| 4 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 100 m lead For thickness of tiles above 10 mm and up to 25 mm | 787 | SqM | - | - |
| 5 | Dismantling G.I pipes of all diameter external work including excavation and refilling trenches after taking out pipes manually / by mechanical means including stacking of pipes within 100 m lead as per direction of Engineer-in-charge | 64 | RM | - | - |
| 6 | Dismantling flushing cistern of any size including stacking of useful materials near the site and disposal of unserviceable materials within 100 m lead | 8 | Nos | - | - |
| 7 | Dismantling old plaster / skirting carefully , raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 100 m lead | 110 | SqM | - | - |
| 8Lead charges for lead Exceeding 4 KM not exceeding 5 KM, by mechanical transport includinmg loading,unloading, stacking / levelling etc. | |||||
| 8.1 | Debris Beyond 4 Km but up to and including 5 km.Note: The rates in respect of above item are applicable for the NET Quantities arrived at after making deductions for voids @ 20% in respect of Soils and 30% in respect of debris from the corresponding stack/truck measurements. | 45 | CuM | - | - |
| 9 | Providing and laying in position cement concrete of 1:2:4 (1 cement, 2 crushed sand, 4 graded stone aggregate of nominal size 20 mm) including consolidation, finishing, curing etc. complete as per specification and drawings but excluding the cost of Formwork shuttering, centering and steel reinforcement at all Levels Note : The minimum cement content for Cement Concrete works should be as per the latest revision of the relevant IS code. | 2 | CuM | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.37 MB
Tendernotice_2.pdf
PDF • 1.32 MB
BOQ_952710.xls
BOQ • 0.30 MB
TechnicalbidET7.xls
Tender Documents • 0.08 MB
ScheduleAET7.pdf
Tender Documents • 0.22 MB
ProformaofScheduleET7.pdf
Tender Documents • 0.65 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .