| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.4 LAccepted-AOC | ₹6.4 L | 1 | Accepted-AOC Low |
| 2 | 2₹6.7 L+₹24,651 (3.83%)Rejected-AOC | ₹6.7 L+₹24,651 (3.83%) | 2 | Rejected-AOC High |
| Sl No | Description | Qty | Unit | SUDHAN CONSTRUCTION L1 | Paari construction L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring and strutting and balling out water wherever necessary refilling the sides of foundation with excavated earth in layers of not more complete complying with standard specification | 169 | M3 | 263 ₹44,447 Lowest | 270 ₹45,630 |
| 2.00 | Plain Cement Concrete 1:4:8 mix (One Cement and Four Sand and eight aggregate) including cost and using 40mm metal including Cost and Conveyance of all materials to site and all labour charges etc., complete complying with standard specification. | 1 | M3 | 5,447 ₹5,447 Lowest | 5,460 ₹5,460 |
| 3.00 | Supplying and erecting centering to sides and soffits including supports and strutting with necessary including cost and conveyance of all materials to site. complete as per standard specification | 25 | M2 | 525 ₹13,125 Lowest | 540 ₹13,500 |
| 4.00 | Plain Cement Concrete 1:2:4 Mix (one part cement, two part m.sand and four part of aggrigate) 20 mm size ISS HBG metal from approved quarry including cost and conveyance of all materials to site. | 11 | M3 | 6,820 ₹75,020 Lowest | 6,840 ₹75,240 |
| 5.00 | Exterior Emulsion paint Two coats with good quality of approved Emulsion paint including cost of all materials to site and all labour charges for mixing applying and proper curring etc., Complete as per Standard Specifications | 16 | M2 | 263 ₹4,208 Lowest | 280 ₹4,480 |
| 6.00 | Re-filling the excavation earth filing including cost and conveyance of all materials to site and all labour charges etc complete as per standard specification. | 163 | M3 | 45 ₹7,335 Lowest | 55 ₹8,965 |
| 7.00 | Supply and fixing of PVC 6ksc class pipe from approved company and including cost and conveyance of materials and all etc complete complying with std specifications - 63mm pvc 6ksc pipe | 400 | m | 73 ₹29,200 Lowest | 90 ₹36,000 |
| 8.00 | Conveyance and lowering of following PVC 6ksc pipe&GI pipe and specials into trenches and laying and jointing with cutting and threading to grade and alignment including charges for testing of pipe line with water after the pipes are laid and jointed etc.,complete complying with std specifications - 63mm pvc 6ksc pipe | 400 | m | 23 ₹9,200 Lowest | 35 ₹14,000 |
| 9.00 | Conducting Geophysical survey, quality and quantity test and transportation charges etc., ( This includes labour charges in the field, rent of the vehicle for reaching the place, rent of the instrument and excluding charges for the geologist) | 1 | No. | 4,200 ₹4,200 Lowest | 4,250 ₹4,250 |
| 10.00 | Drilling of 150 / 180mm dia vertical bores in hard rock formation to any required depth as directed by the departmental officers including labour charges for inserting casing pipe, assembling in the drilled hole, including welding the joints if necessary grouting the casing pipe etc., and including transportation charges for the rig and supporting vehicles from one place to another place. | 1 | M | - | - |
Tender Value
₹8 L
EMD Value
₹16,000
Closing Date
13 Aug 2026, 3:00 pmClosed
Executive Officer
Kolathupalayam Town Panchayat
Providing Borewell Pumpset and Extension of Pipeline with HDPE Tank Bed at Karaiyur in Kolathupalayam Town Panchayat.
2026_DTP_691439_1
172/2026/A1-5
Open Tender
Civil Works - Water Works
Works
Kolathupalayam Town Panchayat
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹16,000
Yes
20 Aug 2026
6 Aug 2026
14 Aug 2026
6 Aug 2026
13 Aug 2026
6 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring and strutting and balling out water wherever necessary refilling the sides of foundation with excavated earth in layers of not more complete complying with standard specification | 169 | M3 | - | - |
| 2 | Plain Cement Concrete 1:4:8 mix (One Cement and Four Sand and eight aggregate) including cost and using 40mm metal including Cost and Conveyance of all materials to site and all labour charges etc., complete complying with standard specification. | 1 | M3 | - | - |
| 3 | Supplying and erecting centering to sides and soffits including supports and strutting with necessary including cost and conveyance of all materials to site. complete as per standard specification | 25 | M2 | - | - |
| 4 | Plain Cement Concrete 1:2:4 Mix (one part cement, two part m.sand and four part of aggrigate) 20 mm size ISS HBG metal from approved quarry including cost and conveyance of all materials to site. | 11 | M3 | - | - |
| 5 | Exterior Emulsion paint Two coats with good quality of approved Emulsion paint including cost of all materials to site and all labour charges for mixing applying and proper curring etc., Complete as per Standard Specifications | 16 | M2 | - | - |
| 6 | Re-filling the excavation earth filing including cost and conveyance of all materials to site and all labour charges etc complete as per standard specification. | 163 | M3 | - | - |
| 7 | Supply and fixing of PVC 6ksc class pipe from approved company and including cost and conveyance of materials and all etc complete complying with std specifications - 63mm pvc 6ksc pipe | 400 | m | - | - |
| 8 | Conveyance and lowering of following PVC 6ksc pipe&GI pipe and specials into trenches and laying and jointing with cutting and threading to grade and alignment including charges for testing of pipe line with water after the pipes are laid and jointed etc.,complete complying with std specifications - 63mm pvc 6ksc pipe | 400 | m | - | - |
| 9 | Conducting Geophysical survey, quality and quantity test and transportation charges etc., ( This includes labour charges in the field, rent of the vehicle for reaching the place, rent of the instrument and excluding charges for the geologist) | 1 | No. | - | - |
| 10 | Drilling of 150 / 180mm dia vertical bores in hard rock formation to any required depth as directed by the departmental officers including labour charges for inserting casing pipe, assembling in the drilled hole, including welding the joints if necessary grouting the casing pipe etc., and including transportation charges for the rig and supporting vehicles from one place to another place. | 1 | M | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.13 MB
BOQ_831391.xls
BOQ • 0.32 MB
TechnicalBidSDRFFive.pdf
PDF • 0.69 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .