Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 CrAccepted-AOC | ₹4.9 Cr | L1 | Accepted-AOC AOC |
| 2 | L2₹5.6 Cr+₹72.4 L (14.8%)Rejected-Finance 11 JAMES HICKEY SARANI 2ND FLOOR KOLKATA 700069 | KOLKATA | KOLKATA | WEST BENGAL | 700069 | ₹5.6 Cr+₹72.4 L (14.8%) | L2 | Rejected-Finance Not Being L1 |
| 3 | L3₹5.8 Cr+₹86.9 L (17.8%)Rejected-Finance 107 1F TOLLYGUNGE ROAD KOLKATA 700026 | KOLKATA | KOLKATA | WEST BENGAL | 700026 | ₹5.8 Cr+₹86.9 L (17.8%) | L3 | Rejected-Finance Not Being L1 |
| 4 | Rejected-Technical | - | - | Rejected-Technical Rejeted due to requsite documents not uploaded |
| Sl No | Description | Qty | Unit | S.M.CONSTRUCTIONS L3 | D R STEEL CONSTRUCTION COMPANY PRIVATE LIMITED L2 | SHEFALI ENTERPRISE L1 |
|---|---|---|---|---|---|---|
| 1.00Schedule "A" Part-I to Schedule "A" Part "XI" Note: Schedule "A" Part-I to Schedule "A" Part "XI" are prepriced by MES,Bidders shall enter their lumpsum amount in green field under colum 8 only | ||||||
| 2.00 | Lumpsum price worked out by the contractor for "Buildings & Structures" as listed in Schedule " Part-I " on serial page no 29R | 1 | Each Job | 2,46,00,000 ₹2,46,00,000 | 1,80,60,000 ₹1,80,60,000 Lowest | 2,04,58,658 ₹2,04,58,658 |
| 3.00 | Lumpsum price worked out by the contractor for "EARTHWORK , SITE CLEARANCE AND SITE DEVELOPMENT" as listed in Schedule " Part-II " on serial page no 30R | 1 | Each Job | 8,49,000 ₹8,49,000 | 9,75,000 ₹9,75,000 | 8,13,520 ₹8,13,520 Lowest |
| 4.00 | Lumpsum price worked out by the contractor for "INTERNAL WATER SUPPLY" as listed in Schedule " Part-III " on serial page no 32R | 1 | Each Job | 45,000 ₹45,000 | 26,700 ₹26,700 Lowest | 41,000 ₹41,000 |
| 5.00 | Lumpsum price worked out by the contractor for "INTERNAL ELECTRIC SUPPLY " as listed in Schedule " Part-IV" on serial page no 37R | 1 | Each Job | 6,25,000 ₹6,25,000 | 5,39,000 ₹5,39,000 | 5,13,200 ₹5,13,200 Lowest |
| 6.00 | Lumpsum price worked out by the contractor for "EXTERNAL WATER SUPPLY" as listed in Schedule " Part-V " on serial page no 38R | 1 | Each Job | 1,49,000 ₹1,49,000 | 1,20,000 ₹1,20,000 Lowest | 1,46,500 ₹1,46,500 |
| 7.00 | Lumpsum price worked out by the contractor for "EXTERNAL ELECTRIC SUPPLY, P" as listed in Schedule " Part-VI " on serial page no 40R | 1 | Each Job | 5,95,000 ₹5,95,000 | 4,91,000 ₹4,91,000 Lowest | 5,01,300 ₹5,01,300 |
| 8.00 | Lumpsum price worked out by the contractor for "SEWAGE DISPOSAL" as listed in Schedule " Part-VII " on serial page no 42R | 1 | Each Job | 3,00,000 ₹3,00,000 | 2,90,000 ₹2,90,000 | 2,63,000 ₹2,63,000 Lowest |
| 9.00 | Lumpsum price worked out by the contractor for "AREA DRAINAGE" as listed in Schedule " Part-VIII " on serial page no 43R | 1 | Each Job | 13,50,000 ₹13,50,000 | 14,50,000 ₹14,50,000 | 12,02,300 ₹12,02,300 Lowest |
| 10.00 | Lumpsum price worked out by the contractor for ROAD/PATH/HARDSTANDING/CULVERT" as listed in Schedule " Part-IX " on serial page no 45R | 1 | Each Job | 27,50,000 ₹27,50,000 | 16,50,000 ₹16,50,000 Lowest | 25,31,000 ₹25,31,000 |
Tender Value
₹4.9 Cr
EMD Value
₹5.7 L
Closing Date
23 May 2026, 6:00 pmClosed
GE (I)(CGN) KOLKATA
GE (I)(CGN) KOLKATA 700023
PROVISION OF UNIT RUN CANTEEN AT 25 ACRES LAND ADJACENT TO VIKRAM ENCLAVE AT CGDHQ 8 HALDIA UNDER GE (I)(CGN) KOLKATA
2026_MES_760787_1
8701/02/2026-2027/E8
Open Tender
Civil Works
Lump-sum
365 days
Haldia
As per Tender documents
9 documents required · 9 mandatory
₹2,000
GE (I)(CGN)
₹5.7 L
Yes
22 Jun 2026
17 Apr 2026
25 May 2026
17 Apr 2026
23 May 2026
17 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Schedule "A" Part-I to Schedule "A" Part "XI"
Note: Schedule "A" Part-I to Schedule "A" Part "XI" are prepriced by MES,Bidders shall enter their lumpsum amount in green field under colum 8 only | - | - | - | - |
| 2 | Lumpsum price worked out by the contractor for "Buildings & Structures" as listed in Schedule " Part-I " on serial page no 29 | - | Each Job | - | - |
| 3 | Lumpsum price worked out by the contractor for "EARTHWORK , SITE CLEARANCE AND SITE DEVELOPMENT" as listed in Schedule " Part-II " on serial page no 30 | - | Each Job | - | - |
| 4 | Lumpsum price worked out by the contractor for "INTERNAL WATER SUPPLY" as listed in Schedule " Part-III " on serial page no 32 | - | Each Job | - | - |
| 5 | Lumpsum price worked out by the contractor for "INTERNAL ELECTRIC SUPPLY " as listed in Schedule " Part-IV" on serial page no 37 | - | Each Job | - | - |
| 6 | Lumpsum price worked out by the contractor for "EXTERNAL WATER SUPPLY" as listed in Schedule " Part-V " on serial page no 38 | - | Each Job | - | - |
| 7 | Lumpsum price worked out by the contractor for "EXTERNAL ELECTRIC SUPPLY, P" as listed in Schedule " Part-VI " on serial page no 40 | - | Each Job | - | - |
| 8 | Lumpsum price worked out by the contractor for "SEWAGE DISPOSAL" as listed in Schedule " Part-VII " on serial page no 42 | - | Each Job | - | - |
| 9 | Lumpsum price worked out by the contractor for "AREA DRAINAGE" as listed in Schedule " Part-VIII " on serial page no 43 | - | Each Job | - | - |
| 10 | Lumpsum price worked out by the contractor for ROAD/PATH/HARDSTANDING/CULVERT" as listed in Schedule " Part-IX " on serial page no 45 | - | Each Job | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.25 MB
BOQ_852196.xls
BOQ • 1.16 MB
Drawings.pdf
Tender Documents • 14.90 MB
tender02.pdf
Tender Documents • 2.20 MB
prepriced.pdf
Tender Documents • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .