Loading…
India Infra Updates on WhatsApp
Join the Tenderkart WhatsApp channel for India Infra Updates
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹50.8 LAccepted-AOC | L1 | Accepted-AOC L1 Tenderer | |
| 2 | L2₹53.2 L+₹2.3 L (4.61%)Rejected-Finance NO 23A V V | L2 | Rejected-Finance L2 Tenderer | |
| 3 | L3₹57.4 L+₹6.6 L (13.0%)Rejected-Finance | L3 | Rejected-Finance L3 Tenderer | |
| 4 | L4₹58.0 L+₹7.2 L (14.1%)Rejected-Finance | L4 | Rejected-Finance L4 Tenderer |
Tender Value
₹55.6 L
EMD Value
₹56,000
Closing Date
27 Oct 2023, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
The Project Director,DRDA,Kancheepuram
O/o Project Director,DRDA,Kancheepuram
Strengthening of Ulunthankandigai Road km 0/0 - 1/200 (R-78) in Thulasapuram Panchayat in Sriperumbudur Union in Package No TNKPM 06/2023-24
2023_RDTN_378933_1
R.C. No. DIPR/5562/Tender/2023 dated.12.10.2023
Open Tender
Civil Works - Roads
Item Rate
180 days
DRDA
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹56,000
Yes
O/o Project Director,DRDA,Kancheepuram
14 Nov 2023
13 Oct 2023
27 Oct 2023
13 Oct 2023
27 Oct 2023
13 Oct 2023
25 Oct 2023
Amount
Clearingthe light jungle including all labour charges for burrying and burning etc., complete.
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25mm THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Filling gravel for shoulders and berms including cost and conveyance of all materials to site and stacking them to departmental guage for premeasurements and labour charges for filling etc., complete
Construction of RCC Slab Culvert 1.50m Span @ Ch 0/250, 1/000 (2 No's)
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering shuttering including necessary supports for planesurface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etcusing mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (countrywood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centrecomplete complying with standard specifications and as directed by departmental Officers etc.Complete.
Up to Ground Level
Above to Ground Level
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous surface
Provision for KM Stone etc complete
Provision for HM Stone etc complete
Provision for 60 cm Equilateral triangle cautionary signboard
Provision for Name board.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
sankaran construction
BRB CONSTRUCTION
MRP Infratech Private Limited
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .