| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.4 CrAdmitted-Finance DIVYA CONCELX TV TOWER STATION ROAD KARYAYUR UTTARAKHAND | UTTARAKHAND | -0.25% | ₹1.4 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.4 CrAdmitted-Finance | -0.22% | ₹1.4 Cr | L2 | Admitted-Finance |
| 3 | L3₹1.4 CrAdmitted-Finance | -0.18% | ₹1.4 Cr | L3 | Admitted-Finance |
Updated dates
Tender Value
₹1.4 Cr
EMD Value
₹2.8 L
Closing Date
29 Apr 2026, 5:00 pmClosed
Executive officer
Nagar Panchayat Maharajganj Raebareli
Work on the development of infrastructure facilities at the Shri Daneshwar Mahadev Temple, situated in Nagar Panchayat Maharajganj, Raebareli.
2026_DOLBU_1132669_1
703/NPM-date-30-03-2026
Open Tender
Civil Works
90 days
Nagar Panchayat Maharajganj Raebareli
Please refer Tender documents.
3 documents required · 3 mandatory
₹16,340
Executive officer
₹2.8 L
26 May 2026
2 Apr 2026
30 Apr 2026
2 Apr 2026
29 Apr 2026
2 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1घाटो का निर्माण कार्य-परिक्रमा पथ का निर्माण कार्य एवं सी0सी0 रोड का निर्माण कार्य। | ||||||
| 1.01 | Cleaning jungle including uprooting of rank, vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. as per PWD sl no. 2.8.1 | - | sqm | - | - | BI01010001010000000000000515BI0100001113 |
| 1.02 | Cost of Dewatering including cost of boring, laying of 100 mm pvc pipe, hire charge of pump set with diesel pvc pipe all complete | - | hr | - | - | BI01010001010000000000000515BI0100001114 |
| 1.03 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. | - | cum | - | - | BI01010001010000000000000515BI0100001115 |
| 1.04 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth,
sides of foundation etc. complete | - | cum | - | - | BI01010001010000000000000515BI0100001116 |
| 1.05 | Providing and laying cement concrete 1: 6 :12 (1 cement: 6 C.sand: 8 graded brick aggregate 40mm nominal size.) including supply of all materials, labour and T&P etc required for proper completion of the work | - | cum | - | - | BI01010001010000000000000515BI0100001117 |
| 1.06 | Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment
shall be measured up to bottom of pile cap 450 mm dia piles | - | RM | - | - | BI01010001010000000000000515BI0100001118 |
| 1.07 | 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ) | - | cum | - | - | BI01010001010000000000000515BI0100001119 |
| 1.08 | Mild steel or iron in plain work such as reinforced concrete or reinforced, brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks | - | qtl | - | - | BI01010001010000000000000515BI0100001120 |
| 1.09 | Centering and shuttering including strutting, propping etc. and removal
of form for Foundations, footings, bases of columns, etc. for mass concrete | - | sqm | - | - | BI01010001010000000000000515BI0100001121 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.35 MB
BOQ_2114257.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid