| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 CrAccepted-AOC | ₹4.8 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹4.8 CrRejected-Finance 1 SADHANA SOCIETY DEV BAUG DEVBAUG BHAVNAGAR GUJARAT 364001 UDYAM GJ 05 0006749 24AACFK2418A1Z4 B R MSME STATUS AS VERIFIED | BHAVNAGAR | GUJARAT | 364001 | ₹4.8 Cr | L2 | Rejected-Finance Other than L1 |
| 3 | L3₹4.8 CrRejected-Finance | ₹4.8 Cr | L3 | Rejected-Finance Other than L1 |
| 4 | Rejected-Technical | - | - | Rejected-Technical Complete documents as asked vide RFP Instructions on filling and submission of tender not found enclosed |
| 5 | Rejected-Technical 346 NEAR SANJAY VATIKA WARD NO 4 PURANI ABADI SRIGANGANAGAR RAJASTHAN 335001 | SRIGANGANAGAR | SRIGANGANAGAR | RAJASTHAN | 335001 | - | - | Rejected-Technical Complete documents as asked vide tender specification of Instructions on filling and submission of tender not found enclosed |
| Sl No | Description | Qty | Unit | KRISHNA CONSTRUCTION COMPANY L2 | VIKESH KUMAR CONTRACTOR L1 | MS RAKSHA CONSTRUCTION CO L3 |
|---|---|---|---|---|---|---|
| 1.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for site clearance as per specification and drawing listed in Schedule 'A' Part -I | 38 | Each | 65,000 ₹24,70,000 | 49,500 ₹18,81,000 Lowest | 99,000 ₹37,62,000 |
| 2.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for steel including accessories as per specification and drawing listed in Schedule 'A' Part -II | 38 | Each | 95,000 ₹36,10,000 | 61,000 ₹23,18,000 Lowest | 90,000 ₹34,20,000 |
| 3.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for structural works as per specification and drawing listed in Schedule 'A' Part -III | 38 | Each | 5,01,000 ₹1,90,38,000 | 4,97,000 ₹1,88,86,000 Lowest | 5,10,000 ₹1,93,80,000 |
| 4.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for painting Items as per specification and drawing listed in Schedule 'A' Part -IV | 38 | Each | 3,11,000 ₹1,18,18,000 | 5,49,000 ₹2,08,62,000 | 3,02,000 ₹1,14,76,000 Lowest |
| 5.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for Lighting Conductor as per specification and drawing listed in Schedule 'A' Part -V | 38 | Each | 1,49,000 ₹56,62,000 | 41,500 ₹15,77,000 Lowest | 1,50,500 ₹57,19,000 |
| 6.00 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for Septic tank and Soakage well as per specification and drawing listed in Schedule 'A' Part -VI | 38 | Each | 1,50,100 ₹57,03,800 | 71,500 ₹27,17,000 Lowest | 1,21,000 ₹45,98,000 |
| 7.00Note: In case doubling/duplicancy of BOQ items , the lowest quoted rate shall be applicable for payment. | ||||||
Tender Value
Refer Docs
EMD Value
₹6.6 L
Closing Date
28 May 2026, 6:00 pmClosed
Commanding Officer
113 Engineer Regiment Firozepur Punjab-152001
Material and labour for construction of 38 x RCC PDs with Ancy in Ferozepur
2026_ARMY_765200_1
4141/OT /38/26-27 OF 2026-27
Open Tender
Civil Works
Item Rate
360 days
Firozepur
As per tender documents
8 documents required · 8 mandatory
₹0
₹6.6 L
Firozepur
15 Jun 2026
14 May 2026
3 Jun 2026
14 May 2026
28 May 2026
21 May 2026
20 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for site clearance as per specification and drawing listed in Schedule 'A' Part -I | 38 | Each | - | - |
| 2 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for steel including accessories as per specification and drawing listed in Schedule 'A' Part -II | 38 | Each | - | - |
| 3 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for structural works as per specification and drawing listed in Schedule 'A' Part -III | 38 | Each | - | - |
| 4 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for painting Items as per specification and drawing listed in Schedule 'A' Part -IV | 38 | Each | - | - |
| 5 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for Lighting Conductor as per specification and drawing listed in Schedule 'A' Part -V | 38 | Each | - | - |
| 6 | Lumpsum price worked out by the contractor for construction of RCC PDs with ancy for Septic tank and Soakage well as per specification and drawing listed in Schedule 'A' Part -VI | 38 | Each | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.38 MB
BOQ_857029.xls
BOQ • 2.01 MB
Tender4141.pdf
Tender Documents • 1.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].