| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.0 LAccepted-Finance | L1 | Accepted-Finance QUALIFIED | |
| 2 | L2₹2.2 L+₹23,205 (11.6%)Accepted-Finance | L2 | Accepted-Finance QUALIFIED | |
| 3 | L3₹2.9 L+₹93,345 (46.7%)Accepted-Finance | L3 | Accepted-Finance QUALIFIED |
Tender Value
₹2 L
EMD Value
₹2,000
Closing Date
15 May 2024, 11:00 amClosed
SE EDC III BULANDSHAHR
SE EDC III BULANDSHAHR
CONSTRUCTION OF 11 KV LINE AGRICULTRURE FEEDER AND OTHR WORK 33/11 KV SS RONDA UNDER EDD III BULANDSHAHR.
2024_PVVNL_924388_1
01/EDC-III/B/2024-2025
Open Tender
Electrical Works
Lump-sum
90 days
BULANDSHAHR
CONSTRUCTION OF 11 KV LINE AGRICULTRURE FEEDER AND OTHR WORK 33/11 KV SS RONDA UNDER EDD III BULANDSHAHR.
2 documents required · 2 mandatory
₹1,180
SE EDC III BULANDSHAHR
₹2,000
28 May 2024
8 May 2024
15 May 2024
8 May 2024
15 May 2024
8 May 2024
Amount
fo|qr forj.k [k.M&r`rh;] cqyUn'kgj ds dk;Z{ks= esa 33@11 dsoh fo|qr midsUnz&jkS.Mk ls iksf’kr Ñf"k iks"kd ls la;ksftr 11 dsoh o ,y-Vh- ykbZu o vU; dk;ZA
Carriage of fallowings from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 80 Kms.
PCC from E.S.C Bulandshahr to Site.
STP from E.S.C Bulandshahr to Site.
Carriage of All line Material from store to j.e store Sub station as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Erection of Single support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Single support shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Carriage of All line Material from store to j.e store Sub station as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc
Laying, sagging. Stringing and binding and jumpering of ACSR Weasel conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
fixing of Stay rod with Stay wire in proper way with Nozelling.
Grouting of Stay rods .
Earth rod complete.
Chopping of Tree branches..
Tightening of Stay
Grouting of PCC/STP Pole Old
Change of broken/Damaged/Missing following Items :-
Disc Insulator
Pin Insulator.
Nut & Bolt off size
Bended X-Arm/Angle/Channel
Ailment of PCC/STP Pole
F-Clamps
Stay Insulator
The following material is required to be The following material is required to be supplied by the contractor.
Stay clamp.
Stay insulator.
L.T. clamp.
L.T. shackle insulator.
L.T. insulator bolt 6 ench.
F clamp.
Bolt & nut off size.
Vivek Electricals
C B S ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .