| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 CrAccepted-AOC | ₹1.6 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.7 Cr+₹7.4 L (4.64%)Rejected-AOC | ₹1.7 Cr+₹7.4 L (4.64%) | L2 | Rejected-AOC L2 |
Tender Value
₹1.6 Cr
EMD Value
₹1.6 L
Closing Date
10 Jan 2025, 3:00 pmClosed
The Project Director, DRDA, Kancheepuram
O/o The Project Director, DRDA, Kancheepuram
Strengthening of Gunagarambakkam colony Road Km 0/0 -2/740 (R-83) in Gunagarampakkam Panchayat at Sriperumbudur Union of Kanchipuram District PKG No.TNKMP-05/NBD30/2024-25 under Scheme NABARD - RIDF XXX (2024-25)
2024_RDTN_514685_1
DIPR/5603/Tender/2024 dt.26.12.2024
Open Tender
Civil Works - Roads
Item Rate
180 days
DRDA, Kancheepuram
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
₹1.6 L
O/o The Project Director, DRDA, Kancheepuram
26 Feb 2025
27 Dec 2024
10 Jan 2025
27 Dec 2024
10 Jan 2025
27 Dec 2024
31 Dec 2024
Amount
Strengthening of Gunagarambakkam colony Road Km 0/0 -2/740 (R-83) in Gunagarampakkam Panchayat at Sriperumbudur Union
Clearing the Scrub jungle including all labour charges for burying and burning etc., Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, scrubs, saplings and trees of girths up to 300mm, removal of stumps of such trees cut Earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, up to a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. complete
Picking the worn out Bt surface inlcuding all other labour charges etc complete
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing & laying spreading & Compacting graded stone aggeragate to wet mix macadam specification including premixing the material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with paver in Sunbase/base course on well prepared surface & compacting with vibratory roller to achieve the desired as per MORT & H specification 406 IV Revision
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it inlcuding all other labour charges etc complete
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Providing and Laying 50mm compacted thick bitumenious macadam using 0.20Cum of 26.5-13.2mm metal.0.43Cum of 13.26-2.36mm metal and 0.08m3 o 2.36m metal with 38Kgs of Bitumen of all materials etc complete (Using CMP & Finishing with Paver Machine)
Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 46.28kgs of VG30 bitumen and 4.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing and laying including cost and conveyance of Gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for power roller, water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc. comp for base-course and side berms inlcuding all other labour charges etc complete
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous surface
Provision for KM Stone etc complete
Provision for HM Stone etc complete
Provision for 60cm Equilateral Triangle cautionary signboard
Provision for Retro reflection Board
Provision for Cost of reflectors
Provision for Name board.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (for Construction & maintenance) above this row in column "BB" for all works in this package}
DCB INFRA (BID ID -1229639)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .